Attachment 1 SOW-Pipe Loop.pdf

PDF 828 KB Posted

Attached to
Water Treatment Facility Pipe Loop
Solicitation number
W50S9024QA003
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to add a water pipe loop to the Water Treatment Facility at Biddle Air National Guard Base in Horsham, Pennsylvania.

The key details are:

  • The contractor shall install a new pipe loop with an air/vac valve to the effluent line after water exits the granular activated carbon (GAC) system in Building 20 of the Water Treatment Facility. This will stop the flow of water when the GAC is turned off at the control panel, without the need for manual valve operation.
  • The performance period is 120 days. Required submittals include product data, shop drawings, operation and maintenance data, hazardous material inventory, and construction logs.
  • The government will maintain a quality assurance program to ensure the work is performed per the SOW and all applicable regulations. The contractor shall provide a 1-year warranty on the work.
  • The related federal contract opportunity, solicitation number W50S9024QA003, is a 100% small business set-aside with a price range between $25,000 and $100,000. Responses are due by 5 June 2024, and a site visit is scheduled for 23 May 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Water Treatment Facility Pipe Loop Biddle Air National Guard Base, Horsham, Pennsylvania 19044

Project Number ZAWA242005

2 November 2023

PURPOSE & SCOPE: All work will be located inside Bldg. 20, Water Treatment Facility (WTF) at Biddle ANG Base. Operation of the current WTF is primarily automated, however some daily functions require manual operation. This repeated motion runs the risk of deteriorating parts which could result in failure. The granular activated carbon (GAC) vessels have valves that control water flow during the filtration process. A valve needs to be opened and closed to start and stop the water flow from the GAC to the clear well. Currently, the valve must be opened and closed manually and does require significant force to do so. The repeated physical operation of the valve can result in functional issues in the long term. If the valve fails, the GAC vessel will drain completely causing overflow issues to the clear well below.

The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary to add a pipe loop to the effluent line as necessary to stop the flow of water once the granular activated carbon (GAC) system has been turned off at the control panel. The contractor shall make the necessary adjustments to stop the flow of water once the GAC has been turned off, without the need to manually turn valves. All information included in this document, along with the instructions and standards referenced in the document, shall be considered as part of the Statement of Work.

1. LOCATION OF WORK: The pipe loop will be installed in Building 20, Water Treatment

Facility (WTF), at Biddle Air National Guard Base in Horsham, PA.

2 GENERAL

2.1 All work is to be accomplished during normal business hours, 7:00am –

4:30pm, Monday through Friday. Deliveries and passes can be obtained/received between 7:00am and 2:30pm, Monday through Friday. The base is closed on weekends, and Federal Holidays.

2.2 The commercial vehicle entrance for shipments or large vehicles is open Monday

– Friday from 7:00 AM to 3:00 PM. All trucks must be at the gate prior to 2:45PM to gain access to the base.

2.3 All contractors and subcontractors must receive a pass to gain entry onto Biddle

Air National Guard Base. Prior to entry, individuals must complete enrollment through the Defense Biometric Identification System (DBIDS) web site at https://dbids- global-enroll.dmdc.mil/. Follow the step by step directions and fill out all information requested. Please note that applicants must fill out all the information even if it is listed as optional. When asked for a sponsor name, please enter Mrs. Ritu Kroh’s information listed below. Once pre-enrollment is completed a 6-digit code will be issued to applicants. This code must be https://dbids-global-enroll.dmdc.mil/ https://dbids-global-enroll.dmdc.mil/ forwarded to CE along with the applicant’s full name and company. The DBIDS process must be completed, and 6-digit code returned to the Government prior to arriving on base. Within 72 hours, you will receive a response on whether the person can enter the installation. This application process needs to only be done once. If you already have a DBIDS card from another facility this process is not required. T h e individual’s DBIDs access card can be updated if they already are in possession of a current, valid card, by submitting the person’s name and date of birth. The vetting information should be emailed to Mrs. Ritu Kroh, ritu.kroh.1@us.af.mil

2.4 In the event of a declared Local or National Emergency the Contracting Officer may be required to stop work on this contract for security reasons. Contractor shall provide the Contracting Office with a current "Off Duty" point of contact and telephone number that can be reached all times to facilitate notification of work stoppage due to a higher installation security posture as well as to notify when work can resume on the project.

2.5 Prior to taking any photographs/video recordings, either for their own record or as required by the terms of the contract, the Contractor shall prepare a request for photography permit, in letter format, and submit it to the Contracting Office via an AF Form 3000. The request must include the contract number, the term of the contract, location, or site to be photographed, dates and time to be accomplished, and indicate whether the Contractor intends to take photos and/or videos. If photography is required by the terms of the contract, a copy of any/all photographs and/or video recordings shall be provided to the Government, via an AF Form 3000, within ten calendar days of being taken. The photographs shall be digital images on a CD. Each image will be appropriately titled and dated for easy identification. Videos will be in digital format on a DVD disk. Each video segment will be appropriately titled for easy identification.

2.6 Contractor shall follow all federal, state, and local environmental regulations, laws and ordinances.

2.7 The contractor shall use and purchase environmentally sustainable materials, when possible, without impacting the quality and durability of the final work.

2.8 Hazardous materials brought on base as part of this project that will be stored for more than 24-hours require registration with our Environmental Management section. Maintain the original Safety Data Sheet (SDS) on site and submit one copy to the Environmental section. Hazardous materials must remain in original manufacturer’s containers. Advise Environmental section when the material has been used and the empty container properly discarded. POC is Mr. Lee dePersia, 215-323-8387. Civil Engineering in coordination with the Contractor and the Fire Department will locate a suitable location to stockpile hazardous materials.

2.9 The contractor shall take every reasonable precaution to prevent hazardous material spills. In the event of a spill, the Contractor shall immediately notify the Environmental Management Section, POC is Mr. Lee dePersia, 215-323-8387.

The contractor is responsible for all clean-up costs.

mailto:ritu.kroh.1@us.af.mil

2.10 All waste material & debris (non-regulated or regulated, hazardous or non-hazardous) generated by work under this project shall be stored, processed, handled, transported, and disposed of by the Contractor in accordance with all federal, state, local regulations, and laws. The contractor shall always, keep the construction area and any storage area free from accumulation of waste materials or rubbish. Prior to completion of each workday, remove from the construction site all waste materials or rubbish not in approved containers. The Government is to sign all manifests and pre-approve the disposal procedures and locations. Under no circumstance shall the Contractor dispose of such materials or any wastes in base dumpsters.

2.11 All measurements, referenced in this "Statement of Work" or attached drawing(s), if any, are approximate. Field confirmation by the contractor is required prior to ordering materials, making any purchases, or committing resources.

2.12 Work in OSHA defined confined spaces requires a “confined space permit” AF

Form 1024, prior to entry. The base may have additional sites designated as confined spaces which will require compliance with this section. The contractor must perform all OSHA required actions and have the required safety equipment on site and set up ready for use. The contractor must use trained staff to perform confined space work and is responsible to “gas free test” the space. The government does not “gas free test” areas on behalf of contractors for liability reasons.

2.13 Reasonable required amounts of water, sewer, and electricity essential to contract performance will be made available at no cost to the Contractor from existing systems, outlets, and supplies. Any tie-in to or alteration of existing utility systems will be at contractor expense. Connection to the natural gas system shall be coordinated with PECO and any fees and connection costs will be paid for directly by the contractor. The Government may not be held responsible for interruption of utility service and will not be liable for contractor delays, damages, or increased cost caused by such an interruption of service. Any temporary connections or lines shall be installed, maintained, and removed by the contractor at their own expense and in a manner acceptable to the Contracting Officer.

2.14 Contractor’s compliance with OSHA Standards and applicable AFOSH

Standards is mandatory. Contractors are subject to inspection of job sites by the Department of Labor (OSHA) and Air Force Safety Inspectors. Resolution of Department of Labor Citations for violations of OSHA Standards shall be the responsibility of the Contractor. It shall be the responsibility of the contractor to initiate and maintain a worksite safety and health program. The program shall include the education and training of employees and subcontractors’ personnel in the recognition, avoidance and prevention of unsafe conditions. Army Corps of Engineers Safety Manual, EM385-1- 1, and other OSHA guidance shall be followed.

2.15 Any additional work completed by the contractor without approval by the

Contracting Officer shall be at the contractor’s expense.

2.16 The contractor shall attend a Pre-Construction Conference prior to starting any work. The Pre-construction conference will be scheduled after contract award. At a minimum, the contractor shall have the project manager and site superintendent at the meeting. The contractor shall provide the following documents at the Pre- Construction Conference.

2.16.1 Project construction schedule

2.16.2 Safety Plan

2.16.3 Quality Control Plan

3 SCHEDULE: The performance period is 120 days.

4 SUBMITTALS: Are defined as follows.

4.1 Product Data: Submit manufacturer's product data and installation instructions for equipment and materials used. Manufacturer’s certification must accompany submittals. Provide products of acceptable manufacturers, which have been in satisfactory use in similar service for three years.

4.2 Shop Drawings: Submit shop drawings indicating material characteristics, details of construction, connections, and relationship with adjacent construction.

4.3 Operation and Maintenance Data. Submit manufacturer’s operation and maintenance data, including operating instructions, list of spare parts and maintenance schedule.

4.4 Quantity and format of Submittals shall be as requested by Civil Engineering at the pre-construction meeting.

4.4.1 All submittals shall have an AF Form 3000 attached and be submitted for approval by the Contracting Office prior to the procurement of the materials. Final payment will be withheld pending receipt and approval of any required submittals.

4.5 Submittals for this project consist of:

4.5.1 Product Data: Submit manufacturer's product data and installation instructions for equipment and materials used. Manufacturer’s certification must accompany submittals.

4.5.2 Shop Drawings: Submit shop drawings indicating material characteristics, details of construction, connections, and relationship with adjacent construction.

4.5.3 Operation and Maintenance Data: Submit manufacturer’s operation and maintenance data, including operating instructions, list of spare parts and maintenance schedule.

4.5.4 Hazardous Material Inventory Sheet: Submit inventory log for approval of all hazardous materials that will be stored on site along with their MSDS.

4.5.5 Daily construction logs must be filled out to encompass every workday of the project on AF Form 1477 and submitted to the contracting officer’s representative.

4.5.6 All debris generated from the project shall be properly disposed of in contractor furnished dumpsters, and resulting weight slips shall be furnished to the Contracting officer’s Representative.

4.5.7 Quantity and format of Submittals shall be as requested by Civil Engineering at the pre-construction meeting. All submittals shall have an AF Form 3000 attached and be submitted for approval by the Contracting Office prior to the procurement of the materials. Final payment will be withheld pending receipt and approval of any required submittals.

4.6 A 10% Retainage will be released upon receipt of the following items:

4.6.1 Operations and Maintenance manuals for all installed equipment

4.6.2 Contractor workmanship letter of warranty of at least one year

4.6.3 Recycling or Landfill proof of disposition document (if available)

5 DESCRIPTION OF WORK:

5.1 Install one (1) new pipe loop with an air/vac valve to the effluent line after water exits the GAC.

5.1.1 The pipe loop shall be added to the effluent line as it runs along the treatment plant back wall where it exits the valve rack before it elbows down to the floor and into the clear well.

5.1.2 The pipe loop shall intercept water before the elbow down, extend up to slightly above the top of the GAC vessel, elbow over a short spool piece tapped to an accept air valve, and extend back down to the original pipe allowing it to continue to the elbow down to the clear well.

5.1.3 Pipe supports shall be added as needed from the floor and wall to properly stabilize the loop addition.

5.1.4 The contractor shall furnish all piping, fittings, parts and accessories required to provide a complete and functional pipe loop to the current water treatment system.

5.2 Contractors are responsible for making their own measurements in determining their proposals for work under this project.

5.3 Refer to provided drawing and photo for additional information.

5.4 The government must approve materials prior to installation.

5.5 All subcontractors working for the contractor shall possess the applicable Pennsylvania

Contractors license.

6 QUALITY ASSURANCE:

6.1 Quality Control. Contractor shall develop and maintain a quality program to ensure work is performed as described in this Statement of Work and in accordance with all local, state and federal rules.

6.2 Quality Assurance. The Government will maintain a Quality Assurance Program to ensure work is performed as described in this Statement of Work and in accordance with all local, state, and federal rules. The Project Manager will manage the Government’s QA program.

6.2.1 Periodic inspection of the work in progress will be accomplished by a representative of the government for the purpose of ensuring the contractor is conforming to the requirements of the statement of work as well as verification of conformance with all safety, environmental, and employment regulations, practices and guidelines.

6.2.2 A one hundred percent (100%) inspection of the finished product will be accomplished. This inspection will be a two-part inspection consisting of a pre-final and a final inspection completed by the COR.

6.2.3 The contractor shall be held accountable for the successful execution of the project in accordance with the contract documents. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price.

7 WARRANTY OF WORK:

7.1 The Contractor warrants that work performed under this contract shall conform to the contract statement of work, manufacturer’s installation requirements, and be free from defects for a period of 1-year.

7.2 If the manufacturer provides a longer warranty, then that period shall be passed along to the government.

7.3 Provide any other standard manufacturer Warranties/Guarantees for other contract materials/equipment.

7.4 The contractor shall remedy, at the contractor’s expense, any failure to conform to conditions, or any damage to Government-owned, or controlled property, when such damage is the result of the contractor’s failure to conform to the contract requirements, applicable drawings, documents, or specifications.

7.5 All Warranties/Guarantees shall become valid upon final acceptance of the work by the Government.

Pipe Loop Required Location

Pipe Loop Location Drawing

**Pipe Loop is denoted in red

2 GENERAL
5 DESCRIPTION OF WORK:
6 QUALITY ASSURANCE:
7 WARRANTY OF WORK: