SOW 212004 Roof Sustainment Amendment 1.pdf
PDF 214 KB Posted
- Attached to
- 137th SOW Roof Sustainment Project
- Solicitation number
- W50S8T-21-B-0003
- Issued by
-
Department of the Army National Guard
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W50S8T-21-B-0003-0002.pdf | ||
| Pre-Bid RFI Log - 212004 Sustain Roofs Basewide3.30.2021.xlsx | XLSX spreadsheet | |
| W50S8T-21-B-0003-0001.pdf | ||
| Pre-Bid RFI Log - 212004 Sustain Roofs Basewide3.30.2021.xlsx | XLSX spreadsheet | |
| W50S8T-21-B-0003.pdf | ||
| Roofs Obase 2.24.2021.pdf | ||
| SOW 212004 Sustain Roofs Basewide.pdf | ||
| 21-2004 Specs Sustain Roofs Basewide.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 12 4/20/2021
April 20, 2021
SCOPE OF WORK
For
CONSTRUCTION
Sustain Roofs Base-wide Project # YZEU 21-2004
Location: Will Rogers Air National Guard Base; B1001, B1007, B1008, B1009, B1010, B1011, B1016, B1020, B1033, B1035, B1040, B1041, B1043, B1044, B1045, B1046, B1047, B1048, B1049, B1050, B1052, B1056.
Value Engineering Statement: Contractors are encouraged to draw on their special 'know-how' and experience to propose changes that cut costs while maintaining or enhancing quality, value, and functional performance. You will be required to provide samples of any material(s) you propose as a better value substitute. Otherwise, the specific materials described in this document will be required.
Access and General Protection/Security Policy and Procedures. Contractor employees with an area of performance within Will Rogers Air National Guard Base shall comply with the following. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Badging Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
For Contractors that do not require CAC, but require access to a DoD Facility and/or
Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations. Contractors will work with the base engineering shop and Security Forces to obtain badging for the base.
Task List: Repair Roofs on building Base wide as indicated on each building and described below. All repairs are to be done in accordance with “UFC 3-110-03 Roofing, with change 5”.
This UFC can be found at the Whole Building Design Guide website “wbdg.org”. Use this UFC in conjunction with the current editions of the National Roofing Contractors Association (NRCA) Roofing Manuals and NRCA technical bulletins. Also follow Metal Building Manufacturers Association (MBMA) Metal Roofing Systems Design Manual (MBMA Roofing Manual) for all repairs. All repairs shall be done in such a way as to keep the existing warranty for the roof intact. Therefore the general contractor shall have the responsibility to coordinate with the warranty holder and any resulting fees for said coordination. The general contractor shall be responsible to gather input as needed from health and safety engineers and/or structural engineers to meet OSHA requirements on the install of safety systems (roof anchors, railings, and ladder fall arrest systems).
Page 2 of 12 4/20/2021
The scope of work is broke out into Base Bid and Options 1 thru 5.
Base Bid includes all roofing repairs, safety railings, and roof hatch safety posts.
Option 1 includes all the ladder and roofing anchor installations except for B1052 ladders.
Option 2 is to remove and replace a cut metal panel on B1020.
Option 3 is to adjust the piping for the roof drains on B1047.
Option 4 is to remove and replace panels with cuts in the parapet walls at B1052.
The following table lists the buildings that have existing warranties. Contact with warranty holder may be necessary prior to performing repairs. Copies of warranties and contact information shall be made available as requested.
Warranty Holder/ Warranty #
Original Installer
Building
Roof Section
Berridge/ 05-046 Allwine Roofing 1001 A Petersen Aluminum/ OKOCBR Oklahoma Roofing 1007 A, B, C Petersen Aluminum/ OKOCBR Oklahoma Roofing 1008 B,C Johns Mannville/ ANB051009573 Oklahoma Roofing 1009 A, B, C Johns Mannville/ ANM118013713 Oklahoma Roofing 1011 B, C Johns Mannville/ ANM117227616 Oklahoma Roofing 1011 E,F, G, H, I, J, K Petersen Aluminum/ 512472, 512473, 3009898
Oklahoma Roofing 1016 A
Petersen Aluminum/ Oklahoma Roofing 1020 A, B Malarkey/ 20120032 Midwest Roofing and Custom Metals 1033 A, B
Red Shield System/ RO025654 Oklahoma Roofing 1035 B Johns Mannville/ ANB111026825 Oklahoma Roofing 1040 A, B, C, D Petersen Aluminum/ Oklahoma Roofing 1052 C See drawings for approximate locations and approximate quantity for each type of repair listed in SOW below.
Base Bid
Contractor shall make the following repairs for each building as identified and listed below:
1) B1001:
a) Roof Section A:
1. Remove existing flashing and replace with new properly seated flashing.
Approximately 2 linear foot.
2. Clean area and apply sealant, solder or elastomeric membrane patch. Approximately
1 linear foot.
3. Install rain diverters and base flashing to direct rain water flow around 2 newly installed vent fans. The install of the flashing shall be done according to roofing manufacturer’s recommendations and specifications. Furthermore install of the rain diverter flashing shall be done in coordination with roof warranty holder. 2 each
Page 3 of 12 4/20/2021
b) Roof Section B:
3. Repair damaged base flashing by overlapping each localized defect with new base flashing. Approximately 1 linear foot.
4. Place stripping felts and surfacing material over edge metal joints which are split.
Approximately 1 linear foot.
2) B1007:
a) Roof Section A:
1. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 3 linear foot.
b) Roof Section B:
2. Install new drawband. 1 each.
3. Contractor shall install railing along the roof edge over the mechanical room and surrounding the HVAC equipment. Railing shall comply with OSHA regulations for height and strength requirements. Preference is for a non-destructive type railing to keep roof penetrations to a minimum. Any roof work associated with the rail installation shall be coordinated with the roof warranty holder in order to keep the existing warranty intact. Approximately 40 linear foot.
3) B1008:
a) Roof Section A:
1. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 1 linear foot.
b) Roof Section C:
2. Remove damaged boot and install new boot. 1 each
3. Install new drawband. 5 each
4) B1009:
a) Section A:
1. Remove all corrosion, prime and coat corroded pitch pans with corrosion resistant paint or replace damaged pitch pan. 7 each
b) Section B:
2. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 1 linear foot.
c) Section C:
3. Prime and apply stripping ply over the edge metal flange in area of loose or missing stripping felts. Approximately 1 linear foot.
4. Reseal failed joints in metal coping cap and reattach. Approximately 1 linear foot.
5) B1010:
1. Cut and re-secure un-bonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 47 linear foot.
b) Section B:
2. Prime exposed and deteriorated base flashing and coat with heavy bodied asphalt coating. Approximately 48 linear foot.
3. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 1 linear foot.
Page 4 of 12 4/20/2021
6) B1011:
1. Cut and re-secure un-bonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 1 linear foot.
b) Section E:
2. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 2 linear foot.
c) Section F:
3. Install extension of counter flashing over exposed top termination of base flashing.
Three course open side laps in base flashing. Approximately 1 linear foot.
d) Section G:
4. Prime and apply stripping ply over edge metal flange in area of loose or missing stripping plies. Approximately 1 linear foot.
5. Restore surfacing material on blisters which have exposed modified bitumen.
Approximately 2 square feet.
e) Section H:
6. Prime and apply stripping ply over edge metal flange in area of loose or missing stripping plies. Approximately 2 linear foot.
f) Section I:
7. Prime and apply stripping ply over edge metal flange in area of loose or missing stripping plies. Approximately 1 linear foot.
g) Section J:
8. Prime and apply stripping ply over edge metal flange in area of loose or missing stripping plies. Approximately 2 linear foot.
h) Railing Sections E&F:
9. Contractor shall install railing along the roof edge each side of the existing fixed ladders. The railing shall extend along the edge for 3’ each side of the ladders.
Railing shall comply with OSHA regulations for height and strength requirements.
This railing shall be installed near the fixed ladders for both the north and south lean-to’s (sections E and F). Preference is for a non-destructive type railing to keep roof penetrations to a minimum. Any roof work associated with the rail installation shall be coordinated with the roof warranty holder in order to keep the existing warranty intact. Any resulting consultation fees from a health and safety engineer, or structural engineer shall be the responsibility of the general contractor.
i) Railing Section A:
10. Contractor shall install railing on either side of the fixed ladder on the 3rd floor annex.
The railing shall extend along the edge for 3’ each side of the ladder. Railing shall comply with OSHA regulations for height and strength requirements (section A).
Preference is for a non-destructive type railing to keep roof penetrations to a minimum. Any roof work associated with the rail installation shall be coordinated with the roof warranty holder in order to keep the existing warranty intact. Any resulting consultation fees from a health and safety engineer, or structural engineer shall be the responsibility of the general contractor
7) B1016:
1. Install new drawband. 2 each.
8) B1020:
1. Install new drawband. 4 each.
Page 5 of 12 4/20/2021
b) Section B:
2. Install new drawband. 2 each.
9) B1033:
1. Reseal failed joints in metal coping cap and reattach. Approximately 3 linear foot.
2. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 5 linear foot.
b) Section B:
3. Reseal failed joints in metal coping cap and reattach. Approximately 5 linear foot.
4. Repair damaged base flashing by overlaying each localized defect with new base
10) B1035:
1. Reseal failed joints in metal coping cap and reattach. Approximately 10 linear foot.
2. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 5 linear foot.
3. Prime exposed and deteriorated base flashing and coat with heavy bodied asphalt coating. Approximately 300 linear foot.
4. Repair deteriorated felts and restore surfacing aggregate. Approximately 10 square feet.
b) Section B:
5. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 4 linear foot.
6. Replace improper equipment supports with device allowing for movement of equipment. Approximately 20 square feet.
7. Prime exposed and deteriorated base flashing and coat with heavy bodied asphalt coating. Approximately 310 linear foot.
8. Reseal failed joints in metal coping cap and reattach. Approximately 3 linear foot.
c) Railing Section A:
9. Contractor shall install railing along the roof edge directly south of one particular Roof Top Unit. The length of the railing shall extend 2’ beyond the length of the RTU each side; for example if the RTU is 6’ long the railing shall be 10’. The railing shall be installed near the edge of the roof, and the center of the rail will line up with the center of the RTU. Railing shall comply with OSHA regulations for height and strength requirements. Preference is for a non-destructive type railing to keep roof penetrations to a minimum. Although there is no warranty for this roof, any roof work associated with the rail installation shall be done in accordance with roofing manufacturer recommendations. Approximately 10 linear foot of railing.
d) Roof Hatch Section A:
10. Contractor shall install a safety post to the fixed ladder at the roof hatch access location. Safety post shall meet OSHA requirements. 1 each.
11) B1040:
1. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 2 linear foot.
2. Reseal failed joints in metal coping cap and reattach. Approximately 1 linear foot.
Page 6 of 12 4/20/2021 flashing. Approximately 5 linear foot.
4. Reseal failed joints in metal coping cap and reattach. Approximately 2 linear foot.
5. Remove damaged flashing sleeves or curbs and replace. Approximately 1 linear foot.
6. Replace improper equipment supports with device allowing for movement of equipment. Approximately 10 square feet.
c) Section C:
7. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 1 linear foot.
d) Section D:
8. Replace improper equipment supports with device allowing for movement of equipment. Approximately 20 square feet.
9. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 3 linear foot.
10. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 2 linear foot.
e) Roof Hatch Section C:
11. Contractor shall install a safety post to the fixed ladder at the roof hatch location.
Safety post shall meet OSHA requirements. 1 each.
12) B1041:
11. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 1 linear foot.
12. Prime exposed and deteriorated base flashing and coat with heavy bodied asphalt coating. Approximately 12 linear foot.
13) B1043:
11. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 152 linear foot.
12. Reseal failed joints in metal coping cap and reattach. Approximately 6 linear foot.
13. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 2 linear foot.
14. Prime exposed and deteriorated base flashing and coat with heavy bodied asphalt coating. Approximately 1 linear foot.
b) Section B:
5. Reseal failed joints in metal coping cap and reattach. Approximately 15 linear foot.
6. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 340 linear foot.
7. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 2 linear foot.
c) Section C:
8. Reseal failed joints in metal coping cap and reattach. Approximately 50 linear foot.
9. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 500 linear foot.
10. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 2 linear foot.
Page 7 of 12 4/20/2021
d) Section D:
11. Reseal failed joints in metal coping cap and reattach. Approximately 20 linear foot.
12. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 326 linear foot.
13. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 6 linear foot.
14. Remove deteriorated stripping felts around drains and scuppers, clean surface and prime. Replace stripping felt and restore surfacing materials. 1 each.
e) Section E:
15. Reseal failed joints in metal coping cap and reattach. Approximately 50 linear foot.
16. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 270 linear foot.
17. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 2 linear foot.
f) Roof Hatch Section D:
18. Contractor shall install a safety post to the fixed ladder at the roof hatch location.
14) B1044:
1. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 300 linear foot.
2. Reseal failed joints in metal coping cap and reattach. Approximately 20 linear foot.
15) B1045:
1. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 2 linear foot.
2. Reseal failed joints in metal coping cap and reattach. Approximately 250 linear foot.
3. Prime exposed and deteriorated base flashing and coat with heavy bodied asphalt coating. Approximately 250 linear foot.
b) Section B:
4. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 15 linear foot.
5. Prime exposed and deteriorated base flashing and coat with heavy bodied asphalt coating. Approximately 250 linear foot.
6. Reseal failed joints in metal coping cap and reattach. Approximately 250 linear foot.
16) B1046:
1. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 4 linear foot.
2. Reseal failed joints in metal coping cap and reattach. Approximately 30 linear foot.
3. Replace improper equipment supports with device allowing for movement of equipment. Approximately 60 square feet.
4. Remove damaged flashing sleeves or curbs and replace. Approximately 1 linear foot.
5. Reseal failed joints in metal coping cap and reattach. Approximately 5 linear foot.
6. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 3 linear foot.
Page 8 of 12 4/20/2021
c) Section C:
7. Reseal failed joints in metal coping cap and reattach. Approximately 10 linear foot.
8. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 1 linear foot.
d) Section D:
9. Reseal failed joints in metal coping cap and reattach. Approximately 3 linear foot.
e) Section E:
10. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 3 linear foot.
11. Reseal failed joints in metal coping cap and reattach. Approximately 2 linear foot.
17) B1047:
1. Reinstall displaced metal cap flashing or replace with new material. Approximately 4 linear foot.
2. Reseal failed joints in metal coping cap and reattach. Approximately 100 linear foot.
3. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 1 linear foot.
b) Section B:
4. Reseal failed joints in metal coping cap and reattach. Approximately 50 linear foot.
5. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 3 linear foot.
c) Section C:
6. Reseal failed joints in metal coping cap and reattach. Approximately 30 linear foot.
d) Section D:
7. Reseal failed joints in metal coping cap and reattach. Approximately 20 linear foot.
18) 1048:
1. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 2 linear foot.
2. Reseal failed joints in metal coping cap and reattach. Approximately 12 linear foot.
b) Section B:
3. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 3 linear foot.
4. Reseal failed joints in metal coping cap and reattach. Approximately 1 linear foot.
5. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 5 linear foot.
c) Section C:
6. Reseal failed joints in metal coping cap and reattach. Approximately 1 linear foot.
7. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 42 linear foot.
8. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 1 linear foot.
d) Section D:
9. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 9 linear foot.
Page 9 of 12 4/20/2021
19) B1049:
1. Reseal failed joints in metal coping cap and reattach. Approximately 50 linear foot.
2. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 100 linear foot.
20) B1050:
1. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 1 linear foot.
2. Reseal failed joints in metal coping cap and reattach. Approximately 4 linear foot.
b) Section B:
3. Cut and re-secure unbonded base flashing, mechanically fasten slipped flashing and apply cold patch over all repairs. Approximately 120 linear foot.
4. Reseal failed joints in metal coping cap and reattach. Approximately 30 linear foot.
5. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 2 linear feet.
c) Section C:
6. Reseal failed joints in metal coping cap and reattach. Approximately 10 linear foot.
7. Repair damaged base flashing by overlaying each localized defect with new base flashing. Approximately 6 linear foot.
21) B1052:
a) Section C:
1. Remove transition flashing and reattach so that all laps shed water or apply sealant, solder or elastomeric patch at joints. Approximately 1 linear foot.
b) Roof Hatch:
1. Contractor shall install a safety post to the fixed ladder at the roof hatch location.
22) B1056:
1. Clean and prepare area and overlay with new membrane. Approximately 4 linear foot.
2. Remove edge metal stripping which covers backed out fasteners and replace with new fasteners. Install new stripping to membrane. Approximately 2 linear foot.
3. Cut membrane over underlying lump and remove foreign material. Clean and prepare surface and overlay repair area with membrane patch. Approximately 3 square feet.
Page 10 of 12 4/20/2021
Option 1 Contractor shall install the ladders, anchors and or fall protection systems for each building as identified and listed below.
23) B1011:
a) Fixed Ladder Fall Arrest System and Roof Anchors
1. Contractor shall install 13 anchors compatible for install on a built-up asphalt roof in locations shown. The anchors are to be installed according to the roofing manufacturer’s recommendations, and shall meet OSHA guidelines. Anchors shall be able to support a horizontal lifeline fall arrest system to be used by base maintenance personnel for safety. Coordination with the roof warranty holder should be done prior to install of the anchors in order to keep existing warranty intact. Any resulting consultation fees from a health and safety engineer, or structural engineer shall be the responsibility of the general contractor. 13 each
2. Contractor shall install an OSHA approved fall arrest system on the existing fixed ladder that goes from section E (north lean-to built up roof) up to section A (the 3rd floor annex and elevator shaft built up roof). 1 each
24) B1041:
a) Roof Access Ladder
1. Contractor shall install new roof access fixed ladder attached to the building in location shown on the drawings. The ladder shall comply with all OSHA requirements. The ladder shall include an approved fall arrest system even though it may be below the 20’ requirement for OSHA. The ladder shall also have a lockable gate to control roof access. The ladder shall be painted to match existing ladders on the buildings (Van Dyke Brown SW 7041). 1 each
25) B1044:
1. Contractor shall install new roof access fixed ladder attached to the building in location shown on the drawings. The ladder shall comply with all OSHA requirements. The ladder shall include an approved fall arrest system even though it may be below the 20’ requirement for OSHA. The ladder shall also have a lockable
26) B1047:
1. Contractor shall install new roof access fixed ladder attached to the building in location shown on the drawings. The ladder shall comply with all OSHA requirements. The ladder shall include an approved fall arrest system even though it may be below the 20’ requirement for OSHA. The ladder shall also have a lockable the buildings (Van Dyke Brown SW 7041). 1each
Page 11 of 12 4/20/2021
27) B1050:
1. Contractor shall install new roof access fixed ladder attached to the building in location shown on the drawings. The ladder shall comply with all OSHA requirements. The ladder shall include an approved fall arrest system even though it may be below the 20’ requirement for OSHA. The ladder shall also have a lockable
Option 2 Contractor shall make the following repairs for the building as identified and listed below.
28) B1020:
b) Replace Metal Roof Panel Section A:
1. Remove cut panel and install new panel using identical profile. The panel replacement will need to be coordinated with the warranty holder for proper installation and to keep the warranty intact. 1 full panel.
Option 3 Contractor shall make the following repair for the building as identified and listed below.
28) B1047:
a) Roof Drain Pipe Repair
1. Contractor shall adjust all drain pipes connected to the roof drain system piping. The current piping is not set up to drain correctly causing some leaks inside the facility.
The contractor shall be responsible for replacing any piping needed to achieve positive gravity drainage. The contractor shall replace any connection points that show signs of leaking between roof drains and other pipes.
Option 4 Contractor shall make the following repairs for the building as identified and listed below.
29) B1052:
a) Replace Metal Wall Panels Sections B & C
1. Contractor shall replace defective metal panels in the parapet walls on the roof.
There are five panels located and identified on the drawings that need to be removed and replaced. The metal wall panels shall be replaced with same material and color to match existing surrounding panels. Coordination with the roof warranty holder may be necessary in order to keep the existing warranty intact. 5 each.
Page 12 of 12 4/20/2021
Permits / Authorizations:
b) AF Form 103 – Civil Engineering Work Clearance Request:
1. To be completed prior to any site excavation or Base Operations stoppages.
2. Contractor responsible for providing Government Construction Inspector with OKIE
Dig number and clearly marked work location 14 days prior to work for internal processing.
3. Contractor to maintain all marking throughout permit duration.
4. Contractor to provide new OKIE number to Government Construction Inspector for revalidation purposes if Work Clearance Request is needed for longer than 30 days.