Pre-Bid RFI Log - 212004 Sustain Roofs Basewide3.30.2021.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- 137th SOW Roof Sustainment Project
- Solicitation number
- W50S8T-21-B-0003
- Issued by
-
Department of the Army National Guard
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W50S8T-21-B-0003-0002.pdf | ||
| SOW 212004 Roof Sustainment Amendment 1.pdf | ||
| W50S8T-21-B-0003-0001.pdf | ||
| Pre-Bid RFI Log - 212004 Sustain Roofs Basewide3.30.2021.xlsx | XLSX spreadsheet | |
| W50S8T-21-B-0003.pdf | ||
| Roofs Obase 2.24.2021.pdf | ||
| SOW 212004 Sustain Roofs Basewide.pdf | ||
| 21-2004 Specs Sustain Roofs Basewide.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Pre-Bid RFI Log for W50S8T-21-B-0003 21-2004 Sustain Roofs Basewide
| Date: | RFI No. | RFP Reference (Sect/Para/Page) | QUESTION | GOVERNMENT RESPONSE |
| 3/29/21 | 1 | SOW | Are the manufacturers listed in the spec, are the roofers required to be |
certified in for that product?
- We are certified in a few, Berridge being one of the big ones, but not John Manville. Does this mean we would not qualify to bid on this project?
The manufacturers are listed in the table at the beginning of the SOW.
It is not a requirement from the gov't to be certified for every manufacturer, so long as the warranty will not be voided by performing the repairs, and the repairs are done in accordance with the specs and references in the SOW. This applies to most repairs in the SOW.
There are several repairs in the SOW that will require coordination with the warranty holder, and the warranty holder may require the company to be certified in certain manufacturer repairs. It shall be the responsibility of the general contractor to coordinate with the warranty holder, and secure the appropriate vendor to perform the repairs and/or modifications. The repairs this will possibly apply to include modifications or major repairs to the roof. Anything that would penetrate the roof could possibly void the warranty and will need to be coordinated with the warranty holder unless otherwise directed by the government.
Base Bid
- 1001 Rain Diverter install.
- 1007 railing installation -possibly if penetrations to roof are needed
- 1011 railiing installation- possibly if penetrations to roof are needed
- 1035 railiing installation- possibly if penetrations to roof are needed Option 1
- 1011 Roof anchors Option 2
- 1020 Roof panel replacement Option 4 -1052 Metal wall panel replacement Option 5 -1052 Roof ladder install- possibly if penetration to roof are needed
3/29/21 2 RFP Can we bid on certain buildings or is the bid price a lump sum for all work to be completed?
Bid is inclusive of all buildings as a single job for work to be completed.
| 4/14/21 | 3 | As-Builts | Are structural as-built drawings available for Building 1052? | Any/all as-built drawings can be provided by the Government. Drawings will be placed on a disc and can be received by the requester, in person, at the Engineering office, Civil Engineer Squadron, WRANGB. |
| 4/20/21 | 4 | SOW | B1052 CLIN 0006 is being removed due to a lack of infrastructure to support the installation of ladders. | After looking into it a little farther, we fill like the scope of work and drawings do not provide enough detail and description for the contractors to be able to give us a good price for this work. CLIN 0006 therefore is being removed. |
Sheet4
Sheet2
Sheet3