This scope of work document outlines the requirements for renovating two bathrooms in Building 1050 at Will Rogers Air National Guard Base. The contractor will demolish existing fixtures, finishes, and partitions before installing new floor and wall tiles, ceilings, plumbing fixtures, lockers, and HVAC equipment. Specific materials called for include porcelain and marble floor tiles, ceramic wall tiles and cove base, solid surface vanity tops, and stainless steel shower partitions. The work also includes options to replace women's lockers, upgrade the ERV unit, and add an ABA-compliant drinking fountain. Bids are due to the contracting officer at the base by the specified date. The Army National Guard facility requires the renovations be completed per the specifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sealed Bid 1419 1050 Bathrooms Page 1 of 2 dt.pdf | ||
| Sealed Bid 1419 1050 Bathrooms Page 2 of 2 dt.pdf | ||
| 1050 Bathrooms Site Visit Attendance Roster.pdf | ||
| Pre-Bid RFI 1050 bathrooms.pdf | ||
| Pre-Bid RFI 1050 bathrooms 29Jul2020.pdf | ||
| BLDG 1050 RESTROOM RERMODEL.pdf | ||
| Compliance Checklist Sealed Bids.pdf | ||
| W50S8T20B0003.pdf | ||
| YZEU172007 Repair Bldg. 1050 Bathrooms Specfications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Bldg. 1050 Bathroom Remodel
Project # YZEU172007
Location: Building 1050 at Will Rogers Air National Guard Base.
All proposals to be submitted to:
Mr. Daniel Tatro Contracting Officer 5901 Air Guard Drive Oklahoma City, OK 73179-1051
Task List:
The work to be accomplished under this contract consists of furnishing all plant, labor, tools, equipment, materials, accessories, incidentals necessary to repair existing locker rooms in building 1050.
1) Demolition
2) New Construction
Value Engineering Statement: Contractors are encouraged to draw on their special ‘know-how’ and experience to propose changes that cut costs while maintaining or enhancing quality, value, and functional performance. You will be required to provide samples of any material(s) you propose as a better value substitute. Otherwise, the specific materials described in this document will be required.
All work is to be accomplished per YZEU172007 Repair Bldg. 1050 Bathrooms Specifications unless specifically superseded below.
See attached drawing for specified areas. Areas shown on drawing are for reference only.
All measurements are approximate and should be field verified.
Base Bid
1) Demolition
a) Remove and dispose of all millwork, fixtures, stall dividers, and hardware in existing bathroom areas per drawings provided.
b) Remove and dispose of floor tile, wall tile, and suspended ceiling in existing bathroom areas as per drawings provided.
c) Remove and dispose of existing wall sections identified on drawings provided. Any electrical or communications rough-in in walls to be removed will be rerouted if possible. If rerouting is not possible, wiring will be terminated at nearest existing junction box. All rerouted or terminated wiring (electrical or communications) must be approved by and authorized by the Government prior to work being accomplished.
d) Existing air return identified on drawings provided will be removed and disposed of. Air return duct work will be rerouted for installation of new air return. Location of new air return will be per drawings provided and verified by the Government prior to installation.
e) Contractor will remove all debris generated from the removal of demolished materials.
2) New Construction
a) Walls
i) All wall construction will be in accordance with section 09260 METAL STUDS AND GYPSUM BOARD SYSTEMS in the YZEU172007 Repair Bldg. 1050 Bathrooms Specifications.
ii) All walls will be patched and prepared for paint.
iii) Infill windows on the south side of the construction area as shown on drawings.
(1) Windows are to be “blacked out” with a vinyl tint so you cannot see inside.
(2) Infill with metal studs and drywall to be flush with existing wall.
iv) Areas receiving wall tile will have ½” cement board behind the wall tile.
(1) Wall tile will be 12” x 24”, Shaw, Casino 500, with accent of American Olean, Refined metals, hammered gloss stainless rm51, or suitable substitutes.
(2) Wall tile will be finished with a bullnose tile or finish trim.
(3) Wall tile grout will be TEC AccuColor #949 Silverado or approved substitute.
v) Any desired deviation to the above listed specification MUST be approved by authorized government personnel prior to work being accomplished.
b) Flooring
i) Provide and install porcelain floor tile and grout in bathroom areas per drawings provided.
(1) Tile will be 24” x 24”, American Olean, Decorum, Dignified gray unpolished or approved substitute.
(2) All floor and wall tile will be installed per manufacturer’s recommendations.
(3) Tile grout will be TEC AccuColor #933 Standard Gray or approved substitute.
ii) Provide and install an Epoxy Coating in bathroom areas per drawings provided and install per the manufacture specifications. Epoxy to be Dur-a-flex, Macro-chip color blend, Glacier or approved substitute.
iii) Provide and install two (2) 2” marble transition strips in locations specified on drawings provided.
iv) All flooring materials and adhesives will be approved via submittal process prior to purchase.
c) Cove Base
i) Contractor is to provide and install ceramic cove base in all areas to receive ceramic or porcelain tile. Specific area will match drawings provided.
ii) Cove base will be American Olean, Decorum, Dignified gray or approved substitute.
iii) Cove base is to be applied with manufacturers recommended adhesive.
iv) All cove base materials and adhesives will be approved via submittal process prior to
d) Doors
i) Refinish existing doors
ii) Reuse existing door hardware to maximum extent.
iii) All new door hardware will be approved via submittal process prior to purchase.
e) Ceiling
i) Contractor is to provide and install new 2’ x 2’ ceiling grid and tile per drawings provided.
ii) Suspended ceiling system will conform to the base standard of Armstrong Prelude ML 15/16”
Exposed Tee System. (Color: white)
iii) Ceiling tile will be moisture resistant 2’ x 2’ Armstrong Fine Fissured Tegular Medium
Texture. (Color: white)
iv) Ceiling grid is to be installed per section 09511 ACUSTICAL TILE CEILINGS of the
YZEU172007 Repair Bldg. 1050 Bathrooms Specifications.
v) Ceilings in bathroom and shower areas will be hard decked with ½” moisture resistant sheetrock and prepared and painted to match newly painted surrounding walls.
vi) All ceiling material will be approved via submittal process prior to purchase.
f) Millwork
i) Provide and install four (4) vanities per drawings provided. New vanities will be similar in size and design as existing vanities. Contractor is to provide shop drawings of proposed vanities, for approval, prior to construction.
ii) Provide and install four (4) solid surface vanity tops. One in each bathroom area as depicted on the drawings provided. Solid surface will be approved via submittal process prior to purchase. Color will be selected during the submittal process.
iii) Millwork contractor to cut out solid surface tops for sink locations.
g) Paint
i) Contractor is to repair, prep wall surfaces prior to painting.
ii) Wall preparation will meet specifications listed in section 09900 PAINTING in the YZEU172007 Repair Bldg. 1050 Bathrooms Specifications and consist of 1 (one) coat of primer and 2 (two) coats of interior semi-gloss latex paint. Color will be selected during the submittal process
iii) All paint and primer will be approved via submittal process prior to purchase
h) Fixtures & Partitions
i) Provide all materials and labor to install fixtures and partitions in locations specified on drawings provided.
(1) Provide and install seven (7) terrazzo pans, two (2) of which will be ABA compliant as shown on the drawings.
(2) Partitions and installation of partitions will be in accordance with section 10620
OPERABLE PARTITIONS of the YZEU172007 Repair Bldg. 1050 Bathrooms Specifications.
(3) Provide and install wall lockers in men’s restroom as shown on drawings.
(4) Provide and install nine (9) white baked enamel floor mounted water closets. Water closets will be mounted and tied into existing sewer line via new plumbing.
(5) Provide and install four (4) white baked enamel wall mounted urinals. Urinals will be mounted to existing supply and drain lines.
(6) Provide and install nine (9) white baked enamel top mount sinks. Sinks will be attached to sewer line via new plumbing.
(7) Provide and install thirteen (13) maple natural finish locker room benches per drawings provided. Actual bench sizing will be provided by government prior to purchase.
(8) Provide and install fourteen (11) shower curtain rods with curtains in locations per drawings provided.
(9) Provide and install fourteen (21) towel hooks with in locations per drawings provided.
(10) Contractor to provide and install access panels for any valves located in walls or sheet rock fir downs
ii) All materials and fixtures, required within this section, will be approved via submittal process prior to purchase.
i) Electrical
i) Contractor will supply and install all electrical wiring, conduit, and devices and convert existing electrical layout to layout provided on drawings.
ii) All Electrical work will be in accordance with SECTION 16050 - BASIC METHODS AND REQUIREMENTS and Division 16 ELECTRICAL of the YZEU172007 Repair Bldg. 1050 Bathrooms Specifications.
iii) All electrical conduit will be Electrical Metallic Tubing (EMT) or Flexible Metal.
(1) EMT: Use EMT for branch circuit electrical raceway systems where concealed in furred ceilings or in walls, exposed inside where not exposed to physical damage. Use compression type couplings and fittings made-up tight for conduit size 2 inches and smaller. Use setscrew type couplings and fittings for conduit greater than 2". Use watertight couplings and fittings where required. Where cast in concrete and floor slabs, use concrete tight couplings and fittings and terminate conduit in a box cast in concrete, or with rigid steel conduit turn-outs from concrete. Conduit smaller than 1/2-inch diameter will not be permitted.
(2) Flexible Metal: Use flexible metal conduit and fittings for lighting fixture connections and for other electrical equipment connections where subject to movement and vibration.
Use flexible metal conduit from outlet boxes to lighting fixtures in such lengths as required, but not to exceed 6 feet in length. Conduit smaller than 1/2-inch in diameter will not be permitted except that 3/8-inch flexible metallic conduit may be used for lighting fixture "pigtails".
j) Fire Alarm
i) Contractor to reinstall all existing fire alarm and alert devices in the new ceiling tile as shown on drawings.
k) Mechanical
i) Contractor to install new grill, flex duct and diffusers as shown on the drawings.
ii) Contractor to connect flex duct to existing taps.
iii) Contractor to cut in new return drops as shown on drawings.
iv) All equipment, required within this section, will be approved via submittal process prior to purchase.
Option #1
1. Contractor to demo wall lockers in the women’s restroom.
2. Contractor to provide and install new lockers in the women’s restroom.
3. Lockers to match the new lockers in the men’s restroom.
4. All equipment, required within this section, will be approved via submittal process prior to
Option #2
1. Contractor to provide and install new ERU roof top unit.
2. Contractor to right size/upsize the unit to help eliminate the humidity issues.
3. Contractor to will tie in new ERU to existing controls system
4. Contractor to provide and install new curb adapter as necessary for new unit to tie into existing duct work.
5. Contractor to provide and install new electrical disconnect on unit.
6. Contractor to replace circuit breaker with new breaker.
7. Contractor to provide equipment and shop drawings for approval via submittal process prior to purchase of equipment.
Option #3
1. Contractor to provide and install ABA compliant drinking fountain as shown on the drawings.
2. Contractor to demo and patch back necessary sheetrock to gain access to inside of wall and fur down to run domestic water and drain lines.
3. Contractor to provide and install access panel for shut off valve at location specified.
4. All equipment, required within this section, will be approved via submittal process prior to