W50S8Q-21-B-0004.pdf
PDF 605 KB Posted
- Attached to
- Breakroom Plumbing Repair Federal contract opportunity
- Solicitation number
- W50S8Q-21-B-0004
- Issued by
- Department of the Army National Guard
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Openign Sign in W50S8Q-21-B-0004.pdf | ||
| Abstract of Offers W50S8Q-21-B-0004.pdf | ||
| Pics 146 Breakroom.pptx | PPTX presentation | |
| As-Build 1 Squad Ops Plumbing Water.pdf | ||
| As-Build 2 Squad Ops plumbing sanitary.pdf | ||
| Sign-In Building 146 Breakroom Site Walk.pdf | ||
| As-Build 3 Squad Ops Power floor plan.pdf | ||
| Q and A 146 Breakroom Cleanout.pdf | ||
| RFI Format.doc | DOC document | |
| Amendment 02 W50S8Q-21-B-0004.pdf | ||
| Amendment 01 W50S8Q-21-B-0004.pdf | ||
| W50S8Q-21-B-0004 Drawing 1.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F9B7CE1092AW01
Bldg 146 Breakroom Cleanout, Project # WAAR202107, at the National Guard Base in Springfield, OH ANGB.
Requirements consist of:
Install easily accessible cleanout for Building 146 break room sink. Remove and replace necessary cabinetry. Jet and cleanout pipes using new cleanout. Remove and replace rubber f looring, transitions, and w all base.
Project Intent:
To mitigate plumbing issues and restore equipment damaged as a result by providing an easy to access f loor cleanout.
This project is a set aside for Samll Business.
The North American Industry Classif ication (NAICS) Code is 236220
Size Standard is $39,500,000
The disclouse of magnitude is betw een $25,000 and $100,000.
Contractors intending to submit a bid are strongly encouraged to attend the site visit See, Section I All documents for this solicitation w ill be posted at https://beta.sam.gov/. Prospective contractors should check the w ebsite frequently for updates to this solicitation. Aw ard w ill be made to the responsible bidder w hose bid conforms to the invitation for bids and is most advantageous to the Government considering only price and price related factors.
X
TRACIE E. MCCLURE 937-327-2379
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
17-Jun-2021
(RFP)
(IFB)
CALL:
Bldg 146 Breakroom Cleanout
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______14 calendar days and complete it w ithin ________45 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________16 Jul 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USPFO OH 178 MISSION SUPPORT CONTRACTING
5319 REGULA AVE BLDG 118
SPRINGFIELD OH 45502-8782
W50S8Q
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
WAAR202107
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W50S8Q21B0004 59
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W50S8Q21B0004
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Bldg 146 Breakroom Cleanout
FFP
Project WAAR 202107, Bldg 146 Break Room Cleanout: Install easily accessible cleanout for Building 146 break room sink. Remove and replace necessary cabinetry. Jet and cleanout pipes using new cleanout. Remove and replace rubber flooring, transitions, and wall base. See Statement of Work (attached) for further details.
FOB: Destination
MILSTRIP: F9B7CE1092AW0100
PURCHASE REQUEST NUMBER: F9B7CE1092AW01
SIGNAL CODE: A
PSC CD: Y1QA
NET AMT
Section C - Descriptions and Specifications
STATEMENT OF WORK
DEPARTMENT OF THE AIR FORCE
178th WING
CIVIL ENGINEER SQUADRON
SPRINGFIELD, OH
STATEMENT OF WORK
146 Break Room Cleanout
WAAR202107
DEPARTMENT OF THE AIR FORCE
178th CIVIL ENGINEER SQUADRON
SPRINGFILED-BECKLEY AIR NATIONAL GUARD BASE
SPRINGFIELD, OH
REV: 2020217
1. GENERAL INFORMATION
1.1. DEFINITION OF TERMS
1.1.1. GOVERNMENT refers to the United States GOVERNMENT and the United States Air Force as represented by the United States CONTRACTING OFFICER or their designated representative, the CONTRACTING OFFICER’s REPRESENTATIVE (COR) from the 178th Civil Engineer Squadron.
1.1.2. CONTRACTOR refers to the CONTRACTOR, the SUBCONTRACTOR for the CONTRACTOR, any and all CONTRACTOR and SUBCONTRACTOR employees or personnel, the CONTRACTOR’s tools, and the CONTRACTOR’s vehicles and equipment.
1.1.3. NOTICE TO PROCEED (NTP) provides written notification that the CONTRACTOR has provided adequate design submittals and is approved by the CONTRACTING OFFICER. This shall allow the CONTRACTOR to begin ordering construction materials.
1.1.4. PERIOD OF PERFORMANCE (PoP) begins with the NOTICE TO PROCEED and ends after the final acceptance of the construction.
1.2. ABBREVIATIONS / ACRONYMS
KO: CONTRACTING OFFICER
COR: CONTRACTING OFFICER’s REPRESENTATIVE PoP: Period of Performance OTHERS: Workmen under the employ of Other CONTRACTORS or the GOVERNMENT.
GFE: GOVERNMENT Furnished Equipment NTP: Notice To Proceed provided by the CONTRACTING OFFICER SOW: Statement of Work ECPs Entry Control Points OSHA: Occupational Safety and Health Administration ASTM: American Society for Testing and Materials UFC: Unified Facilities Criteria (Design Manual) UFGS: Unified Facilities Guide Specifications QA/QC: Quality Assurance / Quality Control EM: Environmental Manager MSDS: Material Safety Data Sheet VECP: Value Engineering Contract Proposal DDC: Direct Digital Controls HHW: Heating Hot Water
1.3. INSTALLATION STANDARDS
1.3.1. Repairs, replacements, new installations and re-installations shall conform to the “best practices” for building constructions, renovations and maintenance activities as specified by the installation Standards referenced below. The workmanship shall meet the requirements of these Standards and as normally provided by experienced trades personnel. The CONTRACTING OFFICER or COR must approve the workmanship as provided by representative samples from the CONTRACTOR prior to installation.
1.3.2. CONTRACTOR shall follow standards for electrical installations pertaining to fire protection and personnel safety found in the current US National Electric Code (NEC).
1.3.3. CONTRACTOR shall follow standards for worker safety found in Occupational Safety and Health Administration (OSHA) requirements, EM385-1-1, National Electric Safety Code, and other similar Standards.
1.3.4. CONTRACTOR is responsible for disposal of all solid waste to include non-hazardous and hazardous waste and shall comply with all Federal, State, and Local environmental laws and regulations and coordinate with Base Environmental Management Office (EMO).
1.3.5. CONTRACTOR shall adhere to all United States Air Force Unified Facilities Criteria (UFC) and Unified Facilities Guide Specifications (UFGS). The US National Electric Code (NEC), Plumbing Codes, International Building Code (IBC), and the Ohio Building Code (OBC) shall be the minimum construction standard allowed; however the UFC shall take precedence should conflict arise. A smoke/fire detection system and consideration for egress shall be provided per NFPA. Ohio Air National Guard Base Fire Department at Springfield, OH, requires a Monaco Fire Alarm panel system. Exterior walls, interior bearing walls (and/or columns) and roof assembly shall meet minimum blast and ballistic mitigation criteria as set forth by UFC 4-020-02FA. Finally, all concrete design shall be in accordance with ACI 318 Code Requirements for Structural Concrete.
1.3.6. CONTRACTOR shall perform site preparation as required, in accordance with drawings and specifications included within this Statement of Work (SOW). Questions pertaining to the depth and extent of the site preparation shall be directed to the CONTRACTING OFFICER’s REPRESENTATIVE (COR). Alteration of existing surfaces or facilities, not identified by the GOVERNMENT, shall not occur. CONTRACTOR shall be responsible for any damage to any surfaces, structures or facilities not identified by the GOVERNMENT for alteration and shall be repaired to the COR’s approval at the CONTRACTOR’s expense.
1.3.7. CONTRACTOR shall provide all labor, material, tools, equipment, and supervision and all other items necessary to complete the work in accordance with any portion of the SOW.
CONTRACTOR shall conduct all work in a professional manner, in accordance with traditionally recognized construction practices and techniques.
1.3.8. It is the CONTRACTOR’s responsibility to field verify all conditions and measurements provided in this statement of work. CONTRACTOR assumes full monetary responsibility for any and all additional work, materials, or equipment required to complete the project that was not included in the statement of work that a reasonable site inspection would have revealed.
CONTRACTOR shall not be responsible for conditions that a reasonable site inspection would not have revealed.
1.3.9. CONTRACTOR is encouraged to develop, prepare, and submit Value Engineering Change Proposals (VECP’s) voluntarily. The Contractor shall share in any net acquisition savings realized from accepted VECP’s, in accordance with the incentive sharing rates in paragraph (f) of 52.248-1 in the FAR. If a VECP is accepted, the Contractor shall share in net acquisition savings of between 50 - 75 percent or as negotiated by KO and as described in the FAR.
1.3.10. CONTRACTOR shall pull all required state boiler permits and arrange a State of Ohio boiler inspection at time of completion prior to Pre-Final Inspection. The CONTRACTOR shall include any work required to obtain approval from the state boiler inspector in the cost of this proposal.
1.3.11. The CONTRACTOR shall complete a DD1354 break-out form for the work performed on project. The form must be completed satisfactorily and in a timely manner before the contractor’s invoice is processed for payment. Any questions from the contractor regarding completion of the form should be referred to the real property manager for assistance. Real Property Manager: Jordan Deady Email: jordan.t.deady.nfg@mail.mil phone: (937) 525-2586
1.4. STANDARD PRODUCTS
1.4.1. The CONTRACTING OFFICER or COR must approve all material submittals prior to procurement. Materials substitution after submittal approvals shall not be allowed without approval by KO.
1.4.2. Materials such as sealants, adhesives, water-proofing or fire-proofing must comply with standards set forth by UL, ASTM, and IEC and listed for the specific use intended.
1.4.3. In the event of conflict among the Specifications, Drawings and/or Technical Instructions, the CONTRACTOR shall bring such conflict to the attention of the CONTRACTING OFFICER or COR for resolution before proceeding with the work involved.
1.4.4. Documentation shall be provided for each submittal. As a minimum, the documentation shall include a catalog sheet of the specific product and the product technical information. When required, a sample of the product/equipment or material must accompany the submission.
1.4.5. MSDS (Material Safety Data Sheet) shall be submitted for all chemical materials to be used for this SOW. Upon approval from the COR the CONTRACTOR shall store materials in accordance with Occupational Safety and Health Administration (OSHA) requirements.
1.5. SUBMITTALS
1.5.1. Material submittals are required unless approval from the COR or CONTRACTING OFFICER has been granted otherwise. All Material Submittals, Design Drawings and Specifications are to be submitted to the CONTRACTING OFFICER with an Air Force Form 3000 (attached) for approval. Submittals, Drawings and Specifications shall be reviewed by the KO and approved prior to installing the approved material.
1.5.2. CONTRACTOR shall provide a detailed Project Schedule identifying milestone dates to COR prior to issuance of NTP. A detailed Design and Construction Schedule in a CPM – Gantt style format shall be submitted for approval using Air Force Form 3064 (attached). If a change in the schedule is required, the CONTRACTOR shall resubmit the Progress Schedule for approval in both electronic and hard copy formats to the COR.
1.5.3. CONTRACTOR shall provide Progress Reports submitted weekly to the COR using Air Force Form 3065 (attached). Progress Reports shall track the CONTRACTOR’s progress in relation to the approved Progress Schedule as well as assist in computing partial payments.
1.5.4. CONTRACTOR shall provide a list of names of all contracted personnel performing work on-base to COR using the Base Pass Information Required for Contractors template (attached) prior to issuance of NTP. List shall be submitted digitally in Word Format via email attachment or CD to
COR.
1.5.5. CONTRACTOR shall provide a list of all chemical materials to be used on the project to the EM using Transient Organization Hazardous Material Inventory (attached) 30 days prior to use.
1.5.6. CONTRACTOR shall provide Material Safety Data Sheet (MSDS) with the Transient Organization Hazardous Material Inventory to COR 30 days prior to beginning construction. At the completion of the project, all unused hazardous materials must be removed from the installation by the CONTRACTOR. CONTRACTOR shall submit the total amount of materials used for the project to COR using the Transient Organization Hazardous Material Inventory Form.
1.5.7. CONTRACTOR shall track and report to COR the volume of solid waste (C & D) disposal and recycling costs incurred or fund received, disposal sites, and weigh tickets, using Post-Project Waste Diversion Report (attached) within 30 days from project completion-minimum 50% diversion.
1.5.8. CONTRACTOR shall abide by the Federal acquisition program for Green Procurement as outlined in USEPA Comprehensive Procurement Guideline website. CONTRACTOR shall provide a list of all recovered materials to the COR using Recovered Materials Determination Form & Recovered Materials Procurement Determination (attached) with the material submittals as outlined in 1.4.1.
1.6. PERMITS / CERTIFICATION
1.6.1. CONTRACTOR is responsible for obtaining all required base passes, dig permits, utility locates and all other permits required to complete the work described in this SOW.
1.6.2. CONTRACTOR must submit and obtain an approved dig permit from Ohio Utilities Protection Service (OUPS) prior to start of any site work. Permits request must be made 48 hours in advance by calling OUPS office at 1-800-362-2764. If damage or injury occurs from digging without a dig permit the CONTRACTOR shall be responsible for all repairs at no additional cost to the government. The CONTRACTOR shall keep a copy of approved dig permit on site at all times.
1.6.3. If total disturbed surface area of the project is greater than 1 acre CONTRACTOR must submit a Storm Water Pollution Prevention Plan (SWPPP) for approval by Clark County Engineer (30 day review process). CONTRACTOR shall then submit a Notice of Intent (NOI) to the Ohio Environmental Protection Agency (OEPA) 21 days prior to start of construction and receive the Director’s Authorization before construction begins. CONTRACTOR shall provide a copy of the NOI, Director’s Authorization, SWPPP, and SWPPP inspections to Environmental Management Office (EMO).
1.6.4. The CONTRACTOR shall obtain an Air Quality (EPA) permit from the Regional Air Pollution Control Agency (RAPCA) for Dayton, OH as required.
1.6.5. The CONTRACTOR shall employ and provide a licensed electrician prior to the start of any electrical work knowledgeable of the work, and conforming to the requirements of the National Electrical Code (NEC). The licensed electrician must provide a current valid certification prior to the start of any electrical work.
1.7. QUALITY ASSURANCE / QUALITY CONTROL
1.7.1. The CONTRACTOR shall supply appropriate supervision and QA/QC for each task of the project to ensure the workmanship and product reflect the SOW and drawings. This project is commercial grade and only commercial type equipment and fixtures shall be accepted. The KO or COR may periodically perform QA checks as deemed necessary at any time during the PoP. These checks do not relieve the CONTRACTOR of the obligations under this section to provide a complete and working product.
1.8. PERSONNEL
1.8.1. CONTRACTOR shall identify a full time Superintendent who shall be responsible for all onsite activities. CONTRACTOR shall submit name(s) of Superintendent to COR prior to issuance of NTP. The Superintendent shall have the authority to make in the field decisions (to be approved by COR), which may arise in day-to-day operations without delay that does not affect cost or scope of project.
1.8.2. CONTRACTOR is required to report this contract in the Contract Manpower Reporting Application.
1.8.3. The GOVERNMENT is not liable for any injury incurred by CONTRACTOR, CONTRACTOR personnel or other persons while they are on site. CONTRACTOR shall take full responsibility for the safety of all personnel within the project site.
1.8.4. The CONTRACTOR shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The CONTRACTOR shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services, or local Security Office. The CONTRACTOR shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF, and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.8.5. CONTRACTOR and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation /facility access and local security policies and procedures (provided by government representative).
1.8.6. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities, and Controlled Access areas shall complete AT Level I awareness training within 30 calendar days after contract start date. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT Level I Awareness Training is available at the following website:
http://jko.jten.mil.
1.8.7. Violations of these policies may result in termination of the contract. Compliance with security requirements shall not be a basis for failing to complete work in the required period of performance.
1.8.8. CONTRACTOR shall recover base passes upon job completion and return to Government within five (5) days of Final Inspection.
1.9. ENVIROMENTAL AND SAFETY
1.9.1. CONTRACTOR is responsible for all costs incurred for clean-up, sampling analyses, and disposal of spill debris as a result of Contractor’s actions. CONTRACTOR shall report all spills to EMO. If appropriate, cost incurred for clean-up by the 178th WG for CONTRACTOR’S actions will be reimbursed to the 178th FE from CONTRACTOR.
1.9.2. CONTRACTOR shall ensure that all personnel receive Environmental Management System (EMS) Awareness training and a copy of the Base Environmental Policy. A copy of the training can be obtained from the 178th Base EMO.
1.9.3. CONTRACTOR shall abide by the Asbestos Notification Requirements as outlined on the OH EPA website. This includes notification of the OH EPA upon the disturbance of more than 260 LF of piping, 160 SF on other facility components, or 35 CF of contaminated material.
1.9.4. CONTRACTOR shall abide by the OH EPA Green Procurement Program as outlined on the USEPA website.
1.9.5. CONTRACTOR shall stop work and contact the 178th Base Environmental Management Office upon unearthing any historical or cultural artifacts during construction.
1.9.6. CONTRACTOR shall obtain all required permits and adhere to and abide by environmental requirements as stipulated by 178th Base EMO. This shall include but is not limited to the following forms:
1. Transient Organization Hazardous Material Inventory
2. Post-Project Waste Diversion Report
3. Recovered Materials Procurement Determination Form
4. Recovered Materials Determination Form
1.9.7. CONTRACTOR shall perform a jobsite cleanup each day and remove all debris and refuse from the site, to the satisfaction of the COR. Unoccupied areas to be broom swept daily. Occupied areas shall be kept free of dust and debris at all times.
1.9.8. CONTRACTOR shall ensure that employees are supplied and use proper safety equipment (i.e. gloves, safety boots) described in OSHA, EM 385 & EM 304 and follow safe work procedures, which protect CONTRACTOR employees and personnel in the vicinity of the job site in accordance with all current OSHA requirements. CONTRACTOR shall assume any liability for any injury incurred by CONTRACTOR personnel while working on site.
1.9.9. CONTRACTOR shall maintain awareness to all NATIONAL DISASTER RESPONSES including Lightning Watch / Lightning Warning / Hazmat Release / Severe Thunder Storm / Tornado Watch / Tornado Warning and shall:
1. Follow all Giant Voice Announcements as directed
2. Discontinue outside / inside work and seek shelter in designated shelter or building as directed
3. Follow directions from Shelter Manager or Senior Military Official 1.9.10. In case of base emergency, CONTRACTOR shall dial 911 then alert Base Security (BDOC) at 937-327-2221.
2. CONTRACT REQUIREMENTS
2.1. GENERAL WORK DESCRIPTION
2.1.1. Install easily accessible cleanout for Building 146 break room sink. Remove and replace necessary cabinetry. Jet and cleanout pipes using new cleanout. Remove and replace rubber flooring, transitions, and wall base.
Project Intent:
To mitigate plumbing issues and restore equipment damaged as a result by providing an easy to access floor cleanout.
2.2. GOVERNMENT FURNISHED EQUIPMENT / PROPERTY 2.2.1. The GOVERNMENT shall provide basic/minimal documents describing the work required in this SOW. Drawings provided are to clearly identify known issues needing addressed. The CONTRACTOR shall be responsible to assess the job.
2.2.2. The GOVERNMENT shall provide the CONTRACTOR access to the site to include all areas of work described in this SOW.
2.2.3. The GOVERNMENT shall provide no other equipment, services, or property.
2.3. PERIOD OF PERFORMANCE 2.3.1. CONTRACTOR shall have a maximum of 45 calendar days from the initial Notice to Proceed (NTP) to complete the project including any design and construction. Any changes or extensions to this time period need prior approval from the
CONTRACTING OFFICER.
2.3.2. CONTRACTOR shall have access to the site from 7:00 am - 4:30 pm Monday - Friday.
CONTRACTOR will not have access to the site on Weekends and Government Holidays unless approved by COR prior.
2.4. COMPLETION 2.4.1. The COR shall certify performance and final completion of this contract.
2.4.2. The CONTRACTOR shall restore any disturbed areas at the direction of the KO and the COR to include grading and reseeding to prior site condition.
2.4.3. The CONTRACTOR shall schedule a Pre-Final Inspection with KO and COR 10 days prior to end of Period of performance. Any Punch List items will be identified and recorded at this time.
2.4.4. CONTRACTOR shall schedule a Final Inspection with KO and COR upon completion of Punch List and within 10 days of the Pre-Final Inspection. This inspection will confirm that all Punch List items have been corrected. Upon completion of the Final Inspection the GOVERNMENT shall take over ownership of the project.
2.5. REQUIRED WARRANTIES 2.5.1. The CONTRACTOR shall provide a 1-year warranty on all material, labor, installed equipment, and work performed in this SOW in addition to any manufacturer’s warranties.
3. DETAILED DESCRIPTION OF WORK
3.1. CONSTRUCTION AND SAFETY PRACTICE
3.1.1. The CONTRACTOR will be required to photograph/document the existing site conditions prior to beginning work for record.
3.1.2. CONTRACTOR shall ensure that safe construction practices are used in accordance with current OSHA standards, EPA (RAPCA) requirements and base requirements. The Contractor shall submit a site safety plan prior to start of project. The Contractor shall maintain a clean job site at all times with daily clean-up.
3.1.3. CONTRACTOR shall field verify all measurements prior to execution.
3.1.4. CONTRACTOR shall provide all labor, material, and equipment to complete job as indicated in this Statement of work and Drawings.
3.2. DEMOLI TION
3.2.1. The CONTRACTOR shall remove any demolished and discarded material from base property.
Including all trash and excess material.
3.2.2. The CONTRACTOR shall remove both Corian countertops and wall plates, and prep for re-use.
3.2.3. The CONTRACTOR shall remove all upper and lower cabinets along sink wall as well as both cabinets placed in the island.
3.2.4. The CONTRACTOR shall only demolish and remove concrete flooring and CMU wall necessary to install hard lined cleanout.
3.2.5. The CONTRACTOR shall demolish tile back splash above Corian wall plate.
3.2.6. The CONTRACTOR shall demolish rubber flooring, wall base and transition strips.
3.3. INSTALLATION CONSTRUCTION
3.3.1. The CONTRACTOR shall install new hard lined cleanout to be accessible from the middle of the kitchen floor with chrome cover plate. (The specific location will be shown on provided drawings.)
3.3.2. The CONTRACTOR shall clean out and jet pipes using the newly installed cleanout.
3.3.3. The CONTRACTOR shall install new concrete flooring to match existing structural and physical appearance.
3.3.4. The CONTRACTOR shall replace any CMU wall, if necessary, to physically and structurally match existing.
3.3.5. The CONTRACTOR shall install approximately 18 feet of new Wilsonart Laminate 7054-60, Wild Cherry (or approved equivalent ) upper and lower cabinetry to match pre demolished cabinetry alignment and dimensions as close as possible.
3.3.6. The CONTRACTOR shall install 2 new Wilsonart Laminate 7054-60, Wild Cherry (or approved equivalent) cabinets to replace the removed cabinetry within the island to match the previous dimensions as best possible.
3.3.7. The CONTRACTOR shall install approximately 425 Square foot of Armstrong, Imperial texture, Standard Excelon, 51804 Earthstone Greige, or approved equivalent flooring and transition strip.
3.3.8. The CONTRACTOR shall install approximately 50 feet of new VPI color #40, Sandstone or approved equivalent wall base.
3.3.9. The CONTRACTOR shall patch and paint walls to match existing if needed.
3.3.10. The CONTRACTOR shall replace tile back splash with painted drywall to match existing paint color scheme.
3.4. WARRANTY REQUIREMENTS
3.4.1. The CONTRACTOR shall Supply the GOVERNMENT with a 1 year workmanship warranty from the date of completion
4. BID STRUCTURE
Item:
Item Number Description Quantity Unit Amount
0001 WAAR202107
Bldg 146 Breakroom
Cleanout
1 Job $
5. CONTACT INFORMATION
5.1. POINTS OF CONTACT
5.1.1. Technical Inspector: Shane Ober – (937) 346-2163
5.1.2. Technical Inspector: Ryan Ott – (937) 525-2588
5.1.3. Technical Inspector: Nick Owens – (937) 525-2589
5.1.4. COR: Mike Howard -- (937) 327-2277
5.1.5. KO: LT. McClure -- (937) 327-2379
5.1.6. EM: Maj Dan Worden -- (937) 327-2279
5.1.7. Dig Permit: OUPS Reporting -- 1-800-362-2764
6. ATTATCHMENTS
6.1. DRAWING # 1 - Major Areas of Repair
6.2. AF FORM 3000
6.3. AF FORM 3064
6.4. AF FORM 3065
6.5. Base Pass Information Required for Contractors
6.6. Transient Organization Hazardous Material Inventory
6.7. Construction & Demolition Debris Waste Diversion Worksheet
6.8. Recovered Materials Determination Form
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 45 dys. ANP 1 F9B7CE - 178 WG CES
DANIEL WORDEN
BLDG 151, 1439 F AVENUE, S-B MAP
SPRINGFIELD OH 45502
937-327-2279 FOB: Destination
F9B7CE
Section G - Contract Administration Data
CLAUSES INCORPORATED BY FULL TEXT
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items—
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
(Contracting Officer: Insert either “Invoice 2in1” or the applicable invoice and receiving report document type(s) for fixed price line items for services.)
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial item financing, submit a commercial item financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC ____
Issue By DoDAAC ____
Admin DoDAAC** ____
Inspect By DoDAAC ____
Ship To Code ____
Ship From Code ____
Mark For Code ____
Service Approver (DoDAAC) ____
Service Acceptor (DoDAAC) ____
Accept at Other DoDAAC ____
LPO DoDAAC ____
DCAA Auditor DoDAAC ____
Other DoDAAC(s) ____
(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert “See Schedule” or “Not applicable.”)
(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
(Contracting Officer: Insert applicable information or “Not applicable.”)
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government JUN 2020 52.203-7 Anti-Kickback Procedures JUN 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-13 Contractor Code of Business Ethics and Conduct JUN 2020 52.204-2 Security Requirements MAR 2021 52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-21 Basic Safeguarding of Covered Contractor Information Systems
JUN 2016
52.208-9 Contractor Use of Mandatory Sources of Supply or Services MAY 2014 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
JUN 2020
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.211-13 Time Extensions SEP 2000 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-26 Audit and Records--Sealed Bidding JUN 2020 52.219-6 Notice Of Total Small Business Set-Aside NOV 2020 52.219-8 Utilization of Small Business Concerns OCT 2018 52.219-14 Limitations On Subcontracting MAR 2020 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards - Overtime
Compensation
MAY 2018
52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work
MAY 2014
52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-35 Equal Opportunity for Veterans JUN 2020 52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020 52.222-40 Notification of Employee Rights Under the National Labor
Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons OCT 2020 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 NOV 2020 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-3 Hazardous Material Identification And Material Safety Data FEB 2021 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-7 Notice Of Radioactive Materials JAN 1997 52.223-9 Estimate of Percentage of Recovered Material Content for
EPA-Designated Items
MAY 2008
52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons.
JUN 2016
52.223-15 Energy Efficiency in Energy-Consuming Products MAY 2020 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
JUN 2020
52.223-21 Foams JUN 2016 52.225-12 Notice of Buy American Requirement - Construction
Materials Under Trade Agreements
MAY 2014
52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.227-1 Authorization and Consent JUN 2020 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
JUN 2020
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-1 Bid Guarantee SEP 1996 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Individual Surety--Pledge of Assets FEB 2021 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-8 Discounts For Prompt Payment FEB 2002 52.232-17 Interest MAY 2014 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-32 Performance-Based Payments APR 2012 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013
52.232-40 Providing Accelerated Payments to Small Business Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-16 Quantity Surveys APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Alt II Specifications and Drawings for Construction (Feb 1997)
Alternate II
APR 1984
52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.243-6 Change Order Accounting APR 1984 52.246-21 Warranty of Construction MAR 1994 52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
APR 2012
52.249-10 Default (Fixed-Price Construction) APR 1984 52.251-1 Government Supply Sources APR 2012 52.252-6 Authorized Deviations In Clauses NOV 2020 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense-
Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General AUG 2019 252.203-7004 Display of Hotline Posters AUG 2019 252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
DEC 2019
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of Terrorism
MAY 2019
252.223-7004 Drug Free Work Force SEP 1988
252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.226-7001 Utilization of Indian Organizations and Indian-Owned
Economic Enterprises, and Native Hawaiian Small Business Concerns
APR 2019
252.227-7033 Rights in Shop Drawings APR 1966 252.231-7000 Supplemental Cost Principles DEC 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7008 Contract Prices-Bidding Schedules DEC 1991 252.236-7013 Requirement for Competition Opportunity for American Steel
Producers, Fabricators, and Manufacturers
JUN 2013
252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012
CLAUSES INCORPORATED BY FULL TEXT
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238220.
(2) The small business size standard is $39,500,000.00.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
( ) Paragraph (d) applies.
( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services--Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations--Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements.