Text version
NY AIR NATIONAL GUARD - 174 ATKW
WAYNE LAWTON
174 CES BPN F9G3CE
6001 E MOLLOY RD
SYRACUSE NY 13211
TEL: 315-233-2450 FAX:
REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
W50S8N20Q0001 08-Oct-2019 5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NOTE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
USPFO NY 174 MISSION SUPPORT CONTRACTING
6001 E MOLLOY RD
SYRACUSE NY 13211-7099
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
12-Oct-2019(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
ADAM D. GAGNE
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
W50S8N20Q0001
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job B610 Furnance Replacement
FFP
to repair (through replacement) the boiler system in Building 610 and all additional work explained in the attached Statement of Work. Quotes are due 12 Oct 2019 by 4:00 PM Eastern. Site visit is scheduled for 10 Oct 2019 at 10:00 AM Eastern.
Location: Hancock Field 6001 E Molloy rd. Syracuse, NY 13211. You will be required to have a state or government issued id at the gate. Please contact Adam Gagne, 315-233-2130, adam.d.gagne.mil@mail.mil or Rick Peirson, 315-233- 2591, richard.m.peirson.mil@mail.mil prior to 12:00 PM (noon) 09 Oct 2019 if planning to attend. Award will be made based on lowest price AND approved technical plan. Wage Determination General Decision Number: NY20190026 dated 16 August 2019. Magnitude of this project is between $100,000-$250,000.
FOB: Destination
MFR PART NR: 1212
SIGNAL CODE: A
PSC CD: Z2NZ
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Job Contractor Manpower Reporting
FFP
Vendors must agree to complete the Contract Management Reporting Application at the end of each fiscal year..
The application may be accessed at: https://cmra.army.mil/Login.aspx.
The CMRA is an online database that automates the Army’s contract management and reporting process for contract management personnel by allowing users to enter their contract information, track contract data, and view reports based on contract data in the application. Its primary function is to support the Contractor Manpower Reporting (CMR) program that was approved on September 13, 2002 by the Business Initiatives Council (BIC) to improve the Army’s visibility of contractor services to planners and programmers. The CMR business process captures information of funding source, contracting vehicle, organization supported, mission and function performed, labor hours, and labor costs for contracted efforts. It enables the Army to:
• Fully understand the total Army workforce
• Provide better oversight of the workforce
• Ensure Army receives full value from contractor workforce
• Better account for total Army workforce FOB: Destination
MFR PART NR: 1212
SIGNAL CODE: A
PSC CD: Z2NZ
NET AMT
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 21-OCT-2019 TO
06-NOV-2019
N/A NY AIR NATIONAL GUARD - 174 ATKW
WAYNE LAWTON
174 CES BPN F9G3CE
6001 E MOLLOY RD
SYRACUSE NY 13211
315-233-2450 FOB: Destination
F9G3CE
0002 N/A N/A N/A N/A
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.203-19 Prohibition on Requiring Certain Internal Confidentiality
Agreements or Statements
JAN 2017
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
OCT 2018
52.204-19 Incorporation by Reference of Representations and Certifications.
DEC 2014
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities.
JUL 2018
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-34 Project Labor Agreement MAY 2010 52.222-50 Combating Trafficking in Persons JAN 2019 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.232-18 Availability Of Funds APR 1984 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-26 Preconstruction Conference FEB 1995 52.242-14 Suspension of Work APR 1984 52.244-6 Subcontracts for Commercial Items AUG 2019 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7006 Billing Instructions OCT 2005 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
OCT 2016
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7002 Qualifying Country Sources As Subcontractors DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.247-7023 Transportation of Supplies by Sea FEB 2019
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 25 days. The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $191.00 for each calendar day of delay until the work is completed or accepted plus a one time modification charge of $300.00.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.213-4 TERMS AND CONDITIONS--SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL
ITEMS) (AUG 2019).
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(ii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).
(iii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2019) (Section 889(a)(1)(A) of Pub. L. 115-232).
(iv) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
(v) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(vi) 52.222-26, Equal Opportunity (SEPT 2016) (E.O. 11246).
(vii) 52.225-13, Restrictions on Certain Foreign Purchases (JUN 2008) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
(viii) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(ix) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78 (19 U.S.C. 3805 note).
(2) Listed below are additional clauses that apply:
(i) 52.232-1, Payments (APR 1984).
(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).
(iii) 52.232-11, Extras (APR 1984).
(iv) 52.232-25, Prompt Payment (JAN 2017).
(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).
(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEC 2013).
(vii) 52.233-1, Disputes (MAY 2014).
(viii) 52.244-6, Subcontracts for Commercial Items (AUG 2019).
(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (MAR 2016) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia)).
(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Oct 2018) (Pub. L. 109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at $30,000 or more).
(ii) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (Jan 2018) (E.O. 13126). (Applies to contracts for supplies exceeding the micro-purchase threshold).
(iii) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (MAY 2014) (41 U.S.C. chapter 65) (Applies to supply contracts over $15,000 in the United States, Puerto Rico, or the U.S. Virgin Islands).
(iv) 52.222-35, Equal Opportunity for Veterans (Oct 2015) (38 U.S.C. 4212) (applies to contracts of $150,000 or more).
(v) 52.222-36, Equal Employment for Workers with Disabilities (JUL 2014) (29 U.S.C. 793) (Applies to contracts over $15,000, unless the work is to be performed outside the United States by employees recruited outside the
United States). (For purposes of this clause, ``United States'' includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)
(vi) 52.222-37, Employment Reports on Veterans (Feb 2016) (38 U.S.C. 4212) (Applies to contracts of $150,000 or more).
(vii) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S.
Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).
(viii)(A) 52.222-50, Combating Trafficking in Persons (JAN 2019) (22 U.S.C. chapter 78 and E.O. 13627) (Applies to all solicitations and contracts).
(B) Alternate I (MAR 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).
(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (DEC 2015) (Executive Order 13658) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia)).
(x) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.))
(xi) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2011) (E.O. 13423) (Applies to services performed on Federal facilities).
(xii) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (June, 2016) (E.O. 13693)(applies to contracts for products as prescribed at FAR 23.804(a)(1)).
(xiii) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (June, 2016) (E.O. 13693) (Applies to maintenance, service, repair, or disposal of refrigeration equipment and air conditioners).
(xiv) 52.223-15, Energy Efficiency in Energy-Consuming Products (DEC 2007) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR ® Program or Federal Energy Management Program (FEMP) will be--
(A) Delivered;
(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;
(C) Furnished by the Contractor for use by the Government; or
(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance).
(xv) 52.223-20, Aerosols (June, 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons as a propellant or as a solvent; or contracts for maintenance or repair of electronic or mechanical devices).
(xvi) 52.223-21, Foams (June, 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons as a foam blowing agent;
or contracts for construction of buildings or facilities.
(xvii) 52.225-1, Buy American--Supplies (MAY 2014) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold and the acquisition--
(A) Is set aside for small business concerns; or
(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000).
(xviii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (MAY 2014) (42 U.S.C. 1792) (Applies to contracts greater than $25,000 that provide for the provision, the service, or the sale of food in the United States).
(xix) 52.232-33, Payment by Electronic Funds Transfer--System for Award Management (OCT 2018) (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) as its source of EFT information.)
(xx) 52.232-34, Payment by Electronic Funds Transfer--Other than System for Award Management (JUL 2013) (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information.)
(xxi) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C. App. 1241) (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d).)
(2) Listed below are additional clauses that may apply:
(i) 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (June, 2016) (Applies to contracts when the contractor or a subcontractor at any tier may have Federal contract information residing in or transiting through its information system.
(ii) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Oct 2015) (Applies to contracts over $35,000).
(iii) 52.211-17, Delivery of Excess Quantities (SEP 1989) (Applies to fixed-price supplies).
(iv) 52.247-29, F.o.b. Origin (FEB 2006) (Applies to supplies if delivery is f.o.b. origin).
(v) 52.247-34, F.o.b. Destination (NOV 1991) (Applies to supplies if delivery is f.o.b. destination).
(c) FAR 52.252-2, Clauses Incorporated by Reference (FEB 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.farsite.hill.af.mil
(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its postacceptance rights--
(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate to the satisfaction of the Government, using its standard record keeping system, have resulted from the termination.
The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.
(g) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(h) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. As used in this clause--
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4) such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1 Foreign construction material.... ........... ___ ........ ....... ………. ___ ................ ........ ___ Domestic construction material... ........ ___ ............... .............. ___ .................. ...... ___ Item 2 Foreign construction material.... ......... ___ ............. ........ ……. ___ ............... ......... ___ Domestic construction material... ....... ___ .................. ............. ___ ................. ....... ___ Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
Construction
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items—
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
N/A
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial item financing, submit a commercial item financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC F87700
Issue By DoDAAC W912PQ
Admin DoDAAC** W912PQ
Inspect By DoDAAC F9G3CE
Ship To Code F9G3CE
Ship From Code ____
Mark For Code ____
Service Approver (DoDAAC) ____
Service Acceptor (DoDAAC) F9G3CE
Accept at Other DoDAAC ____
LPO DoDAAC ____
DCAA Auditor DoDAAC ____
Other DoDAAC(s) ____
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.
(g) WAWF point of contact.
Adam Gagne 315-233-2130
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
Adam.d.gagne.mil@mail.mil
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
Section J - List of Documents, Exhibits and Other Attachments
STATEMENT OF WORK
STATEMENT OF WORK
Repair Boiler System, Building 610 Project #HAAW 18-2030
174th Attack Wing
Hancock Field ANG Base 6001 East Molloy Road
Syracuse, New York 13211
8 October 2019
TABLE OF CONTENTS
1. SCOPE OF WORK
2. AREA OF WORK
3. DESCRIPTION OF WORK
4. PERIOD OF PERFORMANCE
5. MATERIALS & EQUIPMENT
6. GENERAL CONDITIONS
7. GOVERNMENT WORKING HOURS
8. DIFFERING SITE CONDITIONS
9. UTILITIES
10. DISPOSAL OF MATERIALS AND CLEANUP
11. MATERIAL & EQUIPMENT ACCOUNTABILITY
12. FIRE & SECURITY
13. ENVIRONMENTAL
14. ACRONYMS & ABBREVIATIONS
1. SCOPE OF WORK:
The contractor shall provide all personnel, equipment, tools, materials, supervision, transportation, and other items and services necessary to complete the work as described in this Statement of Work (SOW) and project drawings.
2. AREA OF WORK:
Work location is the 174th Attack Wing (174 ATKW), 6001 East Molloy Road, Syracuse, New York 13211 on Hancock Field Air National Guard Base. Contractor shall work only in the areas designated by Contracting Officer Representative (COR). Work will be primarily located within Building 610, also known as ‘the Main Hangar.’
3. DESCRIPTION OF WORK:
3.1. The work specified by this section consists of furnishing all labor, equipment, tools, appliances, transportation, materials, and quality control reports required to repair (through replacement) the boiler system in Building 610 and all additional work explained in this SOW. All work to be performed in accordance with the DoD Unified Facilities Criteria (UFC).
3.2. All work must be completed without damage to any other government property outside of this work scope.
All work performed under this SOW shall be conducted in accordance with all applicable county, state, and federal laws and regulations.
3.3. Demolition: Remove and dispose of materials specified.
3.3.1. As shown on drawings, demolish existing boiler and associated piping, utilities, and other materials necessary to prepare for installation of new system.
3.3.2. Demolish existing air separator.
3.3.3. Demolish existing boiler venting/breeching as indicated on drawing.
3.3.4. Demolish gas supply pipe from valve (painted blue) to old boiler. Demolish gas vent lines (if not needed for new boilers) and repair exterior wall as appropriate within industry best practices.
3.3.5. If not already removed by government, expansion tank shall be disconnected by government and retained for government use elsewhere.
3.4. Installation. ‘Provide’ shall mean furnish and install. Install according to manufacturer’s instructions unless modified by UFC.
3.4.1. This SOW specifies 2 new boiler units. New materials (including but not limited to gas supply, hot water supply, and hot water return lines) shall be designed for a follow-on project to install 1 additional boiler units (total of 3 boiler units) without service interruption.
3.4.2. Where needed, use black iron for natural gas supply.
3.4.3. Boiler supply shall be 5-inch welded or victaulic style piping with 2-inch sidewall insulation.
Boiler piping will be set up in a primary, secondary, piping manner. Use close ‘tees’ with brass ball valve shut-offs and copper into boilers.
3.4.4. Provide shut-off valves and other materials where appropriate to isolate individual boiler units to allow for uninterrupted operation during future maintenance and repair. Additionally, provide shut-off valve on hot water return to isolate boiler room for future maintenance and repair.
3.4.5. Submit shop drawings for proposed utility layouts for COR approval.
3.4.6. Provide 2 Apex Condensing APX-825C boilers configured for natural gas fuel.
3.4.6.1. Any alternate model must be approved by CO and have the following characteristics:
3.4.6.1.1. Ability to communicate to existing Building Automation System (BAS) [Alerton]
3.4.6.1.2. Ability to communicate to other boiler unit and future boiler units including lead/lag operations
3.4.6.1.3. 95% or greater thermal efficiency
3.4.6.1.4. Full modulation
3.4.6.1.5. At least 5:1 turndown ratio
3.4.6.1.6. Stainless steel heat exchanger
3.4.6.1.7. Outdoor reset for supply temperature
3.4.6.1.8. Connections to PVC venting
3.4.6.1.9. Integral boiler circulator pump
3.4.6.2. Select the Two-Pipe PVC Vent Air System
3.4.6.2.1. Penetrations (for both intake and vent) will be 10 feet above indoor ground level and into south horizontal sidewall.
3.4.6.2.2. Select Standard Diameter Option
3.4.6.2.3. Select Direct Vent-Sidewall Standard Terminations
3.4.6.2.4. Provide Vent and Combustion Air Equivalent Length Calculations for COR review.
3.4.7. Provide comparable air separator and auto vent.
3.4.8. Provide properly sized expansion tank.
3.4.9. Electrical
3.4.9.1. Provide dedicated circuit for each boiler.
3.4.9.2. Provide service switch for each boiler.
3.4.9.3. Provide emergency power off switch (shunt trip) for each boiler at each door in accordance with National Electric Code.
3.4.10. Provide all other necessary associated piping, utilities, and other materials for proper operation.
3.4.10.1. System must meet NYSDOL safety regulations.
3.4.10.2. Fill system (approximately 600 gallons) with 60/40 water/propylene glycol mixture (requires four to five 55-gallon containers (approximately 240 gallons) for mixture). Government will retain any excess propylene glycol concentrate.
3.4.11. Seal vent/breeching penetration at ceiling and on roof using NRCA best practices.
3.4.11.1. Close interior of exhaust vent with insulation and cap at or below bracing to reduce heat loss.
3.4.11.2. Cut exhaust vent at 2-foot height and demolish excess material; provide stainless steel round cap affixed with stainless steel screws; seal gaps to prevent leaks.
3.4.11.3. Submit roof & ceiling repair plan for COR approval.
3.5. BAS Programming: Provide necessary computer programming services to upgrade BAS to properly monitor and control new boilers including the following feature: Outdoor enable with proof of pump running.
3.6. Testing, Balancing, and Commissioning
3.6.1. Conduct a factory startup as specified by the manufacturer.
3.6.2. Complete Testing, Balancing, and Commissioning as required by UFC 3-410-01.
3.6.3. Provide Commissioning report in accordance with UFC 3-410-01 3-6.15 prior to final acceptance of the system.
3.7. Warranty
3.7.1. Provide a 12 month warranty for parts and labor on the installed equipment and other work completed.
3.7.2. Warranty performance period shall begin upon final acceptance (or ‘beneficial occupancy’) of boiler system.
3.7.3. Contractor shall respond to warranty calls within 48 hours of notification.
4. PERIOD OF PERFORMANCE:
Work must be completed in 25 days to support the duties of 174 ATKW personnel and safety of the mission.
5. MATERIALS & EQUIPMENT:
5.1. Construction materials must meet relevant code specifications and the New York State building code for northern construction.
5.2. SUBMITTALS: The contractor shall submit to the Contracting Officer (CO) for approval all items listed on attached Material Submittal Schedule (AF Form 66) within 7 calendar days of the notice to proceed (NTP). Alternatively, the contractor may, within 7 calendar days of the NTP, provide the CO with a schedule indicating when each material submittal shall be submitted for approval.
5.2.1. Use an AF Form 3000 for transmitting material submittals.
5.2.2. Ensure that any disapproved submittal will not impact the approved project execution schedule, as a disapproved submittal shall not be considered grounds for a time extension.
5.2.3. Allow for a minimum of 4 working days for the Government’s processing of submittals.
5.2.4. The contractor shall not order, deliver, nor install any materials and/or equipment without CO’s approval or remove any materials on site that have not been properly approved.
5.2.5. In addition to model and serial numbers, the contractor shall provide 1 hard copy and 1 digital copy on compact disc of the operations & maintenance (O&M) manual for each installed equipment item unless otherwise specified. Final payment (up to 10% of awarded amount) will be withheld until O&M manuals are received by the COR.
6. GENERAL CONDITIONS:
6.1. Contractor and all personnel shall comply with the Standard Industry of New York State Codes and the Unified Facilities Criteria. Contractor shall work within the time line specified by COR.
6.2. Contractor shall field verify all site conditions, quantities, measurements, and project requirements.
6.3. Contractor shall protect and barricade all work areas at all times to protect workers, base personnel, and the public from injury.
6.4. Contractor shall protect all structures, utilities, vegetation, sidewalks and vehicles from damage at all times. Replace all damaged materials with new materials to the satisfaction of the Government, at no additional cost to the Government.
6.5. SCHEDULE: The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment.
6.5.1. No later than 7 calendar days after the contract award, the contractor shall provide to the COR a Contract Progress Schedule (AF Form 3064 or other format agreed to by COR).
6.5.2. The contractor shall provide to the COR a Contract Progress Report (AF Form 3065 or other format agreed to by COR) every 2 weeks (or other time period agreed to by COR) after the NTP.
6.5.3. In the event that the CO directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the CO may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
7. DIFFERING SITE CONDITIONS:
Bring any unforeseen project conditions to the attention of the CO immediately. Differing site conditions, which may alter the scope of work, shall be approved by the CO prior to such work being performed.
8. GOVERNMENT WORKING HOURS:
8.1. Work hours shall be Monday thru Friday 0700-1600 hours, with the following exceptions
8.1.1. The contractor may not work during Federal holidays.
8.1.2. On the following Fridays, the Contractor may work only work 0700-1530 hours:
25 October, 8 November, 22 November, and 29 November.
8.1.3. The Contractor may work 0800-1530 on 2 November and 3 November.
8.2. The Contractor must have prior, written CO approval to work outside these hours.
9. UTILITIES:
9.1. The Government shall provide at no cost to the contractor reasonable amounts of water and electricity to support the contract. Hook up will be to existing outlets and will be the contractor’s responsibility.
9.2. Water outlets without a suitable backflow prevention device already installed must have one provided by the contractor prior to use. The backflow prevention device must be submitted to the CO for approval before installation or use. Section 5 submittal instructions apply to backflow prevention device approvals.
10. DISPOSAL OF MATERIALS AND CLEANUP:
10.1. Contractor shall clean up after each work period and dispose of all debris at the close of each day.
10.2. The contractor shall not use any government disposal bins, dumpsters or trash receptacles for any reason at any time unless otherwise specified in this SOW. The contractor shall provide appropriate disposal bins and/or trash receptacles. Approval of disposal bins/trash receptacles location(s) shall be coordinated through the COR.
10.3. The contractor shall not allow debris to leave the work area risking damage to aircraft engines and other government property.
10.4. All debris or trash shall be disposed of off base. All demolition debris shall be disposed of at a permitted landfill, with landfill authorization, unless other arrangements have been coordinated through the Environmental Management Office (EMO). Contractor shall coordinate with the base EMO prior to disposing any materials off base.
10.5. Provide documentation of all disposal and recycling of solid waste, such as landfill receipts; waste manifests, or weight tickets from the landfill that accepts the debris.
11. MATERIAL & EQUIPMENT ACCOUNTABILITY:
Notify the COR prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the COR. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and turned away.
12. FIRE & SECURITY:
12.1. Security Forces shall monitor the incoming and outgoing of work personnel during the duration of the project. All deliveries shall be coordinated with the COR to arrange for their entrance onto the base.
12.2. The contractor’s foreman or project manager shall attend a security briefing prior to the start of work.
12.3. All contractor (and sub-contractor) personnel shall have a minimum of 1 form of government-issued photo identification with them at all times.
12.4. If welding, torching, or any other high-temperature activities are required to complete this project, a burn permit must be obtained first from the Base Fire Department.
13. ENVIRONMENTAL:
13.1. The contractor’s foreman or project manager shall receive an environmental management system briefing at or before the pre-construction meeting.
13.2. HAZARDOUS MATERIALS:
13.2.1. A hazardous material (HM) is any item that is:
13.2.1.1. a health hazard or physical hazard as defined in 29 CFR 1910.1200(c) or
13.2.1.2. regulated in its disposal by the Environmental Protection Agency in 40 CFR or
13.2.1.3. hazardous as defined by Department of Transportation regulation in 49 CFR or
13.2.1.4. hazardous as defined by the Dangerous Goods Regulations of the International Air
Transportation Association
13.2.2. If HM is required to complete this contract, the contractor must create a hazardous materials storage plan and account for HM quantities in accordance with the Hancock Field Hazardous Waste Management Plan. Submit the hazardous materials storage plan following instructions in Section 5.
14. ACRONYMS & ABBREVIATIONS
AF Air Force ANG Air National Guard ATKW Attack Wing BAS Building Automation System CFR Code of Federal Regulations CO Contracting Officer COR Contracting Officer Representative DoD Department of Defense EMO Environmental Management Office HM Hazardous Material NTP Notice to Proceed NRCA National Roofing Contractors Association NYSDOL New York State Department of Labor O&M Operations and Maintenance SOW Statement of Work UFC Unified Facilities Criteria
WAGE DETERMINATION
"General Decision Number: NY20190001 10/04/2019
Superseded General Decision Number: NY20180001
State: New York
Construction Type: Heavy Dredging
Counties: New York Statewide.
STATEWIDE
New York
All dredging, except self-propelled hopper dredges, on the Atlantic Coast and tributary waters emptying into the Atlantic Ocean.
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).