W50S8A-24-B-5200 RFI LOG_Final Responses.xlsx

XLSX spreadsheet 26 KB Posted

Attached to
Buildng 254 Roof Repair
Solicitation number
W50S8A24B5200
Issued by

About this file

This notice constitutes an invitation for bids for roof repair services on Building 254 at Pease Air National Guard Base in New Hampshire. The government seeks a single firm fixed price contract to remove and replace three flat roofs totaling 33,250 square feet with an adhered PVC system. Demolition of existing structures and hazardous material abatement are also included. The anticipated contract duration is approximately 270 days. Bids are due by February 29, 2024 and will be publicly opened on that date at 10:00 AM at the Portsmouth Armory. The requirement is set aside as a 100% small business set aside for NAICS code 236220 with a size standard of $45 million. Interested parties should review the specifications, drawings, provisions and clauses attached to the solicitation and attend the pre-bid conference and site visit scheduled for February 8, 2024.

The government agency is the Department of the Army New Hampshire Army National Guard located at 302 Newmarket Street, Newington, NH 03803.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI

RFI TRACKER - W50S8A-24-B-5200
SZCQ212200 Hangar 254 Roof Repair
RFI #TITLEDate ReceivedDate PostedANSWERADDENDUM ISSUED/REQUIRED
1The specifications state the contractor is responsible for asbestos testing. If the test results are positive, will a change order to remove the existing flashings as asbestos containing material be given?14-Feb-2426-Feb-24Mastic on the original wall panels of the 1950's hangar structure underneath the 2" rigid insulation and corrugated metal wall panels is presumed ACM, see Keynote 2 AD001 and Details 5 & 6 AD521. Given age of the shop area addition and previous asbestos testing (see report provided per RFI 8), further ACM is not anticipated. If the contractor identifies additional ACM, an equitable adjustment will be negotiated for any required abatement.N/A
2Not Used
3The drawing show the lightning protection being removed and then reinstalled after the new system is in place. Is the existing lightning protection being reused or is it new? If reused, does it have to be recertified?14-Feb-2426-Feb-24In general, the lightning protection system is new. Refer to Existing Keynotes throughout the drawing set for select components of the existing system that are to remain (Examples: most down conductors, but not all, and some air terminals). Specification section 26 41 00 outlines the testing requirements.N/A
4For bids being submitted by courier, please provide delivery address.15-Feb-2426-Feb-24The address is on page 9 of the SF1442, paragraph 4.3 under the "Instructions to Bidders".N/A
5Is there a staging area available on site to store mechanical equipment, or must all mechanical equipment be moved off-site and stored by the contractor for later reinstallation?16-Feb-2426-Feb-24Outdoor staging areas on the installation, in the vicinity of the project site will be made available to the contractor.N/A
6Will temporary protection be required at entrances? Can entrances to the existing building be closed? Please clarify what entrances must remain open, and what entrances may be closed during construction.16-Feb-2426-Feb-24The main entrance and airfield side entrance must remain usable during construction, provide protection if/when construction activities would create a hazard at these locations. Other entrances are to remain available for emergency egress, but may be closed for routine use when work effects these areas.N/A
7Please confirm if mechanical TAB / commissioning pre and post verifications should be made to existing equipment being removed from the roof, to confirm operation prior to the contractor moving equipment off the roof and to confirm operation following reinstallation of equipment?16-Feb-2426-Feb-24Pre- and Post TAB is required on all equipment that is to be removed and re-installed. If an item is to be demolished it does not need to be TAB'dN/A
8Has a hazardous materials survey been completed for the existing roof? If a survey has been completed, is the report available?16-Feb-2426-Feb-24"Limited Asbestos and Lead Sampling Report - Building 254" dated November 17, 2021 is attached.N/A
9the contract documents do not discuss any phasing requirements specific to the timing of the removal and reinstallation of the rooftop HVAC equipment. Are there any phasing or outage timing requirements for this rooftop equipment?16-Feb-2426-Feb-24Specific phasing is not required. However, interruptions and outages should be minimized to that which is reasonably necessary for the diligent completion of the work. Coordinate with the Government during construction as indicated in the project documents. Note that the majority of the spaces under Roof 1 have been temporarily vacated and present less of a concern for interruption of Government operations than Roof 2 & 3.N/A
10The specifications call for 1/4” per foot tapered insulation with an R-30 base. Our concern is that this will result in an insulation height that exceeds the wall height. Will it be acceptable to use 1/8” tapered insulation in lieu of 1/4” to reduce the overall height of the insulation at the walls?15-Feb-2426-Feb-24Per UFC 3-110-03 section 6-4-4, a 1/4":12 slope is the minimum allowable slope where 1/2":12" slope cannot be achieved. Section C402.2.1.1 of the 2021 IECC allows the R-value calculation to use average thickness of the roof insulation; therefore, an R-30 base would not be required in all areas of the roof. Coordinate with roofing manufacturer for insulation calculations and design.
Th existing roof structure is also sloped. Please see drawings "SZDT001064 ADAL Aircraft Maintenance Hangar 254 - Reference Drawings.pdf" provided with the solicitation.N/A
11What is the square feet of the ceiling removal and reinstallation19-Feb-2426-Feb-24For bidding purposes assume approximately 3,000 square feet of ceiling removal and reinstallation.N/A
12What is the height of the ceiling to be removed salvage and reinstall?19-Feb-2426-Feb-24Heights vary - ceilings range from approximately 8'-0" to 12-0" and spaces open to structure range from approximately 10'-0" to 18'-0".N/A
13Solar Collector – is this system contains Glycol and do we have to remove the complete system including fluid and reinstall or just the tubes?19-Feb-2426-Feb-24The solar collector assembly and support frame on the roof needs to be removed to the extent necessary to replace the roofing. Glycol should be drained and stored for reuse as necessary for removal of the solar collectors to allow the roofing to be replaced. After the roofing is replaced reinstall the collectors and refill with salvaged glycol.N/A
14Please provide mechanical units information that are to be removed and reinstalled (size, weight, manufacturer etc.)19-Feb-2426-Feb-24Specific information about equipment weight, etc. is unavailable. Please see attached photos of mechanical equipment.N/A
15The amount of insulation in the roof is too little compared to the 6 inches required. Shall the contractor install the 6 inches required or reinstall the current amount as seen during the core sampling of the roof?19-Feb-2426-Feb-24As part of the new PVC roof system, insulation must be installed at a thickness that meets or exceeds the R-30 requirement (shown on detail 1/AE521) as determined by the roofing manufacturer. Refer to RFI #10 response regarding tapered insulation.N/A
16Is the are of work considered in a FOD zone?19-Feb-2426-Feb-24YesN/A
17Is the area of work considered in the Red zone?19-Feb-2426-Feb-24NoN/A
18During the process of construction, will construction equipment be within the flight path and require a crane or equipment permit through the FAA?19-Feb-2426-Feb-24Construction equipment will not be within a flight path. Any use of a crane above the profile of the hangar will require an FAA permit.N/A
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175