This sources sought notice requests capability statements from potential sources to provide a paint booth and installation services for the New Hampshire Air National Guard at Pease Air National Guard Base. Interested parties are to provide estimated pricing for the paint booth (CLIN 0001) and installation (CLIN 0002), capability statements, details on providing a commercial off-the-shelf or custom paint booth, lead times, product origin, subcontracting practices, fire suppression system details, and confirmation of sufficient compressed air supply. Responses should include organization information and be emailed to the contracting officer and specialist by the close date. Based on responses received, the requirement may be set aside for small businesses or procured through full and open competition, with potential for multiple awards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX B – SUMMARY OF AVAILABLE UTILITIES WITHIN HANGAR 253

Provided at Rm 129 1 ½ inch gas line @ north wall 1 inch Compressed Air/Tool Lines x 2 at east and west walls Floor Drain located at north/center of room for potential Eye Wash/Shower Electrical service (all located along west wall):

· Panel HP-2 (200A main circuit breaker)

· 15A 480/277V 3Ph/4Wire previously for Blast Booth Claim System (3HP) (Unused)

· 15A 480/277V 3Ph/4Wire previously for Blast Booth Dry Honer (2HP) (Unused)

· Panel HP-4 (150A main circuit breaker)

· 60A 480/277V 3Ph/4Wire previously for Despatch Oven Rm 129 (Unused)

· Additional capacity available in panel

· Panel LP-2 (208/120V)

· Panel LP-2A (208/120V)

Fire sprinkler system w/ drain/test valve located in the southeast corner of Rm 129 (capacity calculation needed for Paint Booth requirement)

· Surrounding Room Fire Suppression/Alarms – HC-2 coverage provided, 0.2GPM/SQFT @ Design Area of 2,500SF

Provided Elsewhere in Bldg 253 Electrical capacity at Panel RDP-1 in the main electrical room of Bldg 253, depicted as Room C on drawing AE-101:

· 70A 480/277V 3Ph/4Wire for Blast Booth Vent (25HP) planned at Rm 120 (Circuit breaker/wiring not installed)

· 60A 480/277V 3Ph/4Wire for Paint Booth Make Up Air Unit (20HP) planned at Rm 120 (Circuit breaker/wiring not installed)

· 60A 480/277V 3Ph/4Wire for Paint Booth Exhaust Fan (20HP) planned at Rm 120 (Circuit breaker/wiring not installed)

Compressed Air-Breathing Air (closest breathing air supply is at CTK Rm 123 or at Mechanical Mezzanine above and west of Room 129)

Domestic water supply (available above ceiling at the restrooms and Mechanical Mezzanine above and west of Room 129)