This document is Amendment 0001 to Solicitation W50S8527QA001, issued by the W7NF USPFO Activity MIANG 127 on November 19, 2026, with an effective date of November 19, 2026. The amendment is administered by the Air Force Contracting Officer Andrea Senska. The amendment contains two substantive modifications: (1) addition of a deadline for submitting requests for site visits, which must be received via email to tami.mckenney.1@us.af.mil no later than December 2, 2026 at 10:00 a.m. local time, and (2) correction of the period of performance for multiple Contract Line Items (CLINs) 2004 through 5017.

The period of performance corrections reflect a one-year shift in multiple option line items spanning fiscal years 2028 through 2032. Generally, the corrected dates advance each option period backward by one year from the originally specified timeframes. For example, Option Line Items 2004-2017 were corrected from "01 Oct 2029 to 30 Sep 2030" to "01 Oct 2028 to 30 Sep 2029," with Option Line Item 2006 adjusted to "01 Oct 2028 to 30 Sep 2030." Option periods 3001-3017, 4001-4017, and 5001-5017 similarly reflect corresponding one-year retroactive adjustments. Offerors must acknowledge receipt of this amendment prior to the offer submission deadline by one of the prescribed methods: completing and returning the amendment form, acknowledging receipt on each offer copy, or providing written or electronic acknowledgment referencing the solicitation and amendment numbers.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Continuation of Deliveries or Performance

The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:

Option Line Item 2004

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2005

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2006

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2030

Option Line Item 2007

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2008

INFORMATION FROM TO

Period of 01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

W50S8527QA0010001

Performance

Option Line Item 2009

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2010

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2011

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2012

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2013

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2014

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2015

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2016

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 2017

INFORMATION FROM TO

Period of Performance

01 Oct 2029 to 30 Sep 2030 01 Oct 2028 to 30 Sep 2029

Option Line Item 3001

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3002

INFORMATION FROM TO

Period of 01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3003

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3004

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3005

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3006

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3007

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2031

Option Line Item 3008

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3009

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3010

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3011

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3012

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3013

INFORMATION FROM TO

Period of 01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3014

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3015

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3016

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 3017

INFORMATION FROM TO

Period of Performance

01 Oct 2030 to 30 Sep 2031 01 Oct 2029 to 30 Sep 2030

Option Line Item 4001

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4002

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4003

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4004

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4005

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4006

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4007

INFORMATION FROM TO

Period of 01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4008

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4009

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4010

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4011

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4012

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4013

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4014

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4015

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4016

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 4017

INFORMATION FROM TO

Period of Performance

01 Oct 2031 to 30 Sep 2032 01 Oct 2030 to 30 Sep 2031

Option Line Item 5001

INFORMATION FROM TO

Period of 01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5002

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5003

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5004

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5005

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5006

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5007

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5008

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5009

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5010

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5011

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5012

INFORMATION FROM TO

Period of 01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5013

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5014

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5015

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5016

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

Option Line Item 5017

INFORMATION FROM TO

Period of Performance

01 Oct 2032 to 31 Mar 2033 01 Oct 2031 to 31 Mar 2032

IDCode: J
Page: 1
Pages: 14
AmendNo: 0001
EffDate: 19 NOV 2026
ReqNo:
ProjNo:
IssCode: W50S85
AdmCode:
IssuedBy: W7NF USPFO ACTIVITY MIANG 127

KO FOR MIANG DO NOT DELETE, 43200 MAPLE ST BLDG 105

SELFRIDGE ANGB, MI 48045-5213

UNITED STATES

TAMI MCKENNEY, EMAIL: TAMI.MCKENNEY.1@US.AF.MIL TELEPHONE: 586-239-5989

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W50S8527QA001
SolDate: 17 NOV 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE CONTINUATION
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: 1. Adding the deadline for submitting request for site visit, must be received by email to tami.mckenney.1@us.af.mil, no later than 2 December 2026, 10am local time.

2. Corrected the period of performance on CLINs 2004 - 5017.