The document is a Pre-Bid Conference PowerPoint presentation for a U.S. Air Force contract to repair the foundation of Building 859 at Selfridge Air National Guard Base. The project involves repairing structural issues in the northern part of a fire station, including floor slab settlement, masonry wall cracks, and related damage that has occurred since 2001. Key contract details include a small business set-aside with NAICS code 236220, a firm fixed-price contract with a performance period of 480 calendar days, and a project value between $1M-$5M.
The solicitation timeline includes a pre-solicitation notice on 15 April 2025, solicitation posted on 3 July 2025, a pre-bid site visit on 17 July 2025, and bid opening on 5 August 2025 at 12:00 PM EDT. Bidders must submit electronic sealed bids through the Procurement Integrated Enterprise Environment (PIEE) website, with a bid bond/guarantee required at 20% of the total bid price. The contract will be awarded to the most advantageous responsible bidder, considering only price and price-related factors. Bids must include pricing for all Contract Line Item Numbers (CLINs), with two optional CLINs for exterior repair and site work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Selfridge Air National Guard Base Solicitation No.: W50S8525BA006 Project No.: VGLZ 199555 Repair B859 Fire Station Foundation
17 July 2025 2:00 p.m.
PRE-BID CONFERENCE
Integrity – Excellence – Service -Introduce myself -Thanks for coming -My main focus today is to familiarize you with the project so you can make an initial determination if you are interested in/qualified to bid
Agenda Introductions – Contracting Info.
Admin Matters Process for Questions and Answers (Requests for Information) Project Overview Sealed Bid Requirements and procedures for submission of bids Determination of Responsibility Questions
If there are any differences between Pre-Bid conference slides and the solicitation, the information found in the solicitation will prevail.
Introductions Introductions and Contracting POC Information:
Contracting Officer Mr. Jeremy Starrett jeremy.starrett.1@us.af.mil
Contracting Specialist Ms. Anna Randall anna.randall.1@us.af.mil
Contracting Specialist Mr. David Brown david.brown.39@us.af.mil
-Introductions
Administrative Matters Attendance Roster – Site Visit Ensure you sign the attendance roster
The roster and the Pre-Bid presentation will be posted on https://sam.gov.
A site visit will follow this presentation.
Any questions you have during the site visit should be sent in writing for an official response in accordance with the solicitation.
No other site visits will be granted at this time unless required.
Process for Questions and Answers Submit questions (Requests for Information) to both Anna Randall and David Brown. (See Solicitation Instructions.) Do not contact the A-E or any Government Engineering personnel directly.
Questions and official answers will be posted on Sam.gov on a non-attribution basis with solicitation information at https://sam.gov.
Submit questions NLT 3 business days prior to bid opening, (currently scheduled for 5 August 2025, 12:00 pm EDT)*check Sam for updates.
Amendments will only be issued if there is a change in the solicitation, specifications, or plans.
Any answers that clarify or provide an interpretation to the drawings, specifications, etc. will be posted as an RFI response but NOT issued as an amendment.
Project Overview A Firm Fixed Price contract will be awarded Invitation for Bid Procedures Small Business set-aside
NAICS 236220
Performance Period: 480 calendar days after Notice to Proceed is issued.
The Notice to Proceed will be issued after formal approval of payment and performance bonds.
Magnitude of Construction: $1M - $5M Bid Schedule - CLINs: Base (3 CLINs total) One base CLIN and two Option CLIN. Option CLINs – Exterior Repair and Site Work.
-RPA = Remote Piloted Aircraft
| Pre-Solicitation Notice: | 15 April 2025 | |
| Solicitation Posted: | 3 July 2025 | |
| Pre-Bid Site Visit: | 17 July 2025 | |
| Bid Opening Date/Time: | 5 Aug 2025, 12:00 PM EDT | |
| Deadline to submit questions: | 31 July 2025 | |
| Projected award date: | TBD |
-RPA = Remote Piloted Aircraft
Project highlights requirements include:
The floor slab in the northern part of the building has been settling since the completion of construction in 2001 and continues to settle. These settlements have caused cracks to develop in the floor slabs, as well as in the non-load-bearing masonry wall, resulting in numerous problems as follows: uneven and out of level floors; trip hazards at doorways due to differential settlement up to one inch between doorways and the floor slabs; cracks in the non-load-bearing masonry walls and lintels at the doorways, causing misaligned door frames; horizontal and vertical cracks in the non-load-bearing masonry walls; vertical cracks in non-load-bearing walls at their junctions with load-bearing masonry walls; out of alignment and cracking of restroom area tiles; and miscellaneous cracking of drywall partitions. The scope of this project is the repair of the existing system architectural, plumbing, and structural systems and replacement of permanently damaged materials. The south portion of the building, which contains the firefighting apparatus, has not been compromised and will not be included in any repair designs. Finishes will match existing/original finish and material selections in the affected areas, and design or selection of a new color/material palette is not part of the scope.
Brand Name Requirements: N/A
-Base bid & ABIs are loosely organized in line w/these functional areas
Sealed Bid Procedures Overview BIDDERS ARE STRONLY ENCOURAGED TO CAREFULLY READ THE REQUIREMENTS OF THE SOLICIATION AND COMPLY ACCORDINGLY. REFER TO THE SOLICITATION AND FAR 14 FOR DETAILS.
Bidders must submit sealed bids ELECTRONICALLY via the Procurement Integrated Enterprise Environment (PIEE) website at: https://piee.eb.mil See 00 21 00 – Instructions for PIEE User Guide and Video Demonstration websites. Bids will not be accepted through any other transmission (email, fax, USPS, hand carried, etc.)
Receipt of Submissions: Offeror’s proposal must be received by the Government by the date/time specified in the solicitation. *Allow up to 4 hours for delivery. See 00 21 00 for additional information on submission and timestamps.
After bids are opened an award will be made to that responsible bidder whose bid conforming to the IFB will be most advantageous to the Government, considering only price and price related factors.
The bid abstract will be certified and posted on SAM.gov as soon as practicable.
Bid Requirements SF 1442, (Blocks 14-20c)-Do not enter less than 120 days in block 17
Section 00 10 00. Bid Schedule - all CLIN’s must be priced.
Section 00 45 00 Reps and Certs: Bidder must have current and complete data (entered within the past year) in the Online Representatives and Certifications at https://sam.gov
Acknowledge all SF30 issued Amendments On page 2 of SF1442 and/or by providing signed SF 30s with bid
Bid Bond/Guarantee shall be 20% of the complete bid price, issued on the most recent edition of the SF 24 with a complete power of attorney.
Determination of Responsibility
IMPORTANT: REFER TO THE SOLICIATATION AND FAR PART 9 FOR DETAILS
A bidder is determined to be responsible in accordance with FAR 9.104.
To establish its responsibility, the apparent low bidder may be requested by the Government prior to award, to submit a statement regarding their previous experience in performing comparable work, their business and technical organization, financial and bonding resources and plant available to be used in performing the work.
Payment and Performance Bonds will be required based on project magnitude.
Technical Review Site Visit Technical Review
Site Visit
Official questions will not be answered at this site visit. Please ensure that the Request for Information process is utilized via email or Government’s Points of Entry (GPE) image4.png image5.png image6.emf image1.gif image2.jpeg