W50S85-24-B-0011 (T781) RFI LOG as of 2 August.pdf
PDF 140 KB Posted
- Solicitation number
- W50S8524B0011
About this file
This document is a Request for Information (RFI) Log related to the federal contract opportunity W50S85-24-B-0011 (T781) to replace a leaking medium voltage transformer. The RFI Log contains responses to several questions from prospective bidders, including details on the existing cable conduit, transformer oil sample availability, lead time considerations, permitting requirements, and third-party testing standards.
The related federal contract opportunity is for the VGLZ 242003 project to replace the leaking medium voltage transformer T781. It is a 100% Small Business set-aside with a NAICS code of 237130, Power and Communication Line and Related Structures. The period of performance is 180 calendar days after the notice to proceed, with an estimated project magnitude between $100,000 to $250,000. Proposals are due by the date specified in the solicitation, and prospective bidders are encouraged to attend a pre-bid conference and site visit.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Is the existing primary cable conduit encased in concrete?
A. Yes, assume MV feeder conduit is in concrete duct bank.
2. Are there previous transformer oil samples test results available for prospective bidders?
A. Checking with environmental dept.
3. Will an extension be granted if lead times are beyond 180 days for the new switch and new transformer?
A. Submit documentation for deliverables to contracting officer for consideration to extend POP after award to reflect latest market trends, lead times, and to document the lack of alternate but compatible products with better lead time..
4. Is the contractor required to pull an electrical permit for inspection by the local municipality?
A. No. all permitting is local Base requirements quality control is responsibility of contractor, Government will provide assurance inspections.
5. Contract Specifications 1.22: Will a NETA (National Electrical Testing Association) accredited and certified company meet the third-party testing requirements?
A. All testing shall be non-destructive and shall be done in accordance with ANSI/IEEE, UFC, NETA standards and NEC. VLF and Tan delta testing shall be performed.
W50S8524B0011 RFI Log as of 2 August 24