Q and A - Lift Station 20260820.pdf

PDF 73 KB Posted

Attached to
Repair Lift Station
Solicitation number
W50S8426BA004
Issued by

About this file

This is a Questions and Answers (Q&A) document for a federal lift station replacement contract. The document addresses clarifications on the Statement of Work (SOW), technical specifications, and contractual requirements for the Lift Station Repair project at Building B6954.

Project Scope and Technical Requirements: The contract performance period is 365 calendar days from Notice to Proceed (NTP), encompassing all work including submittals, construction, winter weather, closeout, and site restoration. The existing lift station may be out of service for a maximum of one week with Contracting Officer Representative (COR) coordination. No temporary bypass pumping is required. The contractor must install two submersible, non-clogging grinder pumps rated for a minimum of 75 GPM at 22 feet Total Dynamic Head (TDH), with the contractor responsible for selecting final pump horsepower. Equivalent equipment meeting code and performance requirements is acceptable; no preferred manufacturer list exists. The existing pit is approximately 60 inches wide and 20 feet deep with 4-inch piping. Only the inlet and outlet pipes installed in pit walls will be reused; all other internal piping and components will be replaced. The discharge piping through the pit wall past the check valve will remain; everything inside the pit will be replaced. The control panel must be NEMA 4X stainless steel compatible with 480V 3-phase 4-wire power, including a manual generator transfer switch, 60 AMP main breaker, 15 AMP motor fuse, and NEMA 1 27 AMP 3-phase motor starter with 3.0 AMP thermal overload setting. Existing electrical components may be reused if modifications or replacements are required; such costs should be included in the base bid. Alarms and monitoring devices are standalone and not integrated with any Building Automation System (BAS) or SCADA. Startup and testing will be witnessed by the COR and performed by the contractor, demonstrating all functions working properly.

Site Work and Contractual Terms: Excavation outside the existing lift station pit is not anticipated, and dewatering beyond removal of debris and standing water is not required. Turf restoration requires standard commercial seed mix and contractor-supplied topsoil reuse from excavation, with one initial watering and natural precipitation thereafter; no prolonged maintenance or 60-day establishment period is required. Removed equipment disposition is addressed in SOW sections 1.13 and 1.14. The contractor must obtain required State of Michigan approvals, permits, and licenses; environmental and wastewater permits are covered in the base contract. Performance and Payment bonds are required if the contract award exceeds $150,000 under the Miller Act; below this threshold, payment bond protection is preferred with penal amounts at 100% of contract price. FAR 52.219-14 Limitations on Subcontracting does not apply to this 100% Small Business set-aside. The Government cannot support additional site visits beyond the August 11 pre-bid visit. Visible electrical piping and racking material will be replaced with the control cabinet.

View the file

Other files

File Type Posted
Bid Opening Abstract W50S84-26-B-A004.pdf PDF
Site Visit Minutes_BCANGB.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Question Answer

Lift Station

Period of Performance The SF 1442 and solicitation identify a 365-calendar-day performance period, while the SOW states 180 calendar days from NTP. Please confirm the correct contract performance period.

Confirming total contract PoP is 365 days from NTP, which includes all contract requirements including submittal process, construction, winter weather, project closeout documents, and site restoration. SOW will be updated to correct 365 PoP.

Lift Station Lift Station Shutdown / Continuity of Service Please confirm the maximum allowable duration that the existing lift station may be out of service during demolition and replacement.

1 week, must coordinate downtime with COR

Lift Station

Temporary Bypass Pumping Please confirm whether the Contractor is required to provide temporary sanitary bypass pumping or other temporary wastewater service during lift-station replacement. If required, please provide the anticipated flow rate/design criteria and any required bypass configuration.

No temporary sanitary bypass is needed.

Lift Station

Pump Design Point / Horsepower The SOW requires two submersible, non-clogging grinder pumps rated for a minimum of 75 GPM at approximately 22 feet discharge head and notes that the existing pumps are 1½ HP, 460V, 3-phase. Please confirm whether 75 GPM at 22 feet TDH is the required pump design point and whether the Contractor is responsible for selecting the final pump horsepower.

Yes, minimum 75 GPM at 22 feet TDH is required. Contractor is responsible for selecting the final pump horsepower.

Lift Station

Pump Manufacturer / Basis of Design Please confirm whether the Government has a required or preferred pump manufacturer, basis-of-design model, or approved manufacturer list. If not, please confirm that equivalent equipment meeting the stated performance requirements is acceptable.

Equivalent equipment meeting code and performance requirments is acceptable.

Lift Station

Existing Wet-Well / Pit Information Please provide the existing wet-well/pit dimensions, depth, piping arrangement, and any available record drawings or equipment data that may assist bidders in selecting and installing the replacement system.

Drawings do not exist for this. Existing equipment specification in SOW is included.

Lift Station Existing Piping / Valves / Fittings Please identify the sizes, materials, and configuration of the existing pit piping, valves, and fittings and clarify which components are to be replaced versus reused.

Piping is 4 inch. No components are to be reused except the inlet and outlet pipes installed in the pit walls

Existing Discharge Piping Please confirm whether the existing discharge piping is intended to remain and be reused. If existing piping is found unsuitable for reconnection, please clarify whether replacement/modification is included in the Base Bid or will be handled as additional work.

The only discharge piping intended on being used in the piping going through the pit wall past the check valve. Everything inside the pit will be replaced.

Lift Station

Control Panel Requirements The SOW requires a NEMA 4X stainless-steel control panel compatible with the existing 480V power supply and generator circuit. Please provide any required short-circuit current rating/SCCR, breaker/fuse requirements, enclosure mounting requirements, and other electrical design criteria not identified in the SOW.

480v 3 Phase 4 Wire. Manual generator transfer switch. 60 AMP main breaker. Motor Fuse 15 AMP. Motor Starter - NEMA 1 27 AMP 3 Phase w/ thermal overload. Thermal overload setting - 3.0

AMP.

Lift Station

Available Fault Current Please provide the available fault current at the lift-station electrical service so the Contractor can properly select the required control-panel and protective-device ratings.

480v 3 Phase 4 Wire. Manual generator transfer switch. 60 AMP main breaker. Motor Fuse 15 AMP. Motor Starter - NEMA 1 27 AMP 3 Phase w/ thermal overload. Thermal overload setting - 3.0

AMP.

Lift Station

Existing Electrical Feeder Please confirm whether the existing feeder, conductors, conduit, and disconnecting means are intended to be reused. If modification or replacement is required to accommodate the new equipment, please clarify whether that work is included in the Base Bid.

Existing electrical and components may be used. If modification or replacement is required they should be included in the bid.

Lift Station

Alarm / Remote Monitoring Integration Please confirm whether the high-water alarm, horn, strobe, or other lift-station controls are required to interface with any existing BAS, SCADA, remote alarm, annunciator, or monitoring system.

Alarms and devices are only at the lift station and not tied to any monitioring system.

Lift Station

Pump Startup / Performance Testing The SOW requires operation of the newly installed lift station before closeout. Please identify the required startup and acceptance testing, including whether flow verification, drawdown testing, pump run testing, lead/lag alternation testing, alarm testing, float testing, and written test reports are required.

Startup and testing should show all the functions working properly.

Lift Station

Manufacturer-Authorized Startup Please confirm whether startup, testing, or commissioning must be performed or witnessed by a factory-authorized representative of the pump/control-panel manufacturer.

Startup, testing, and commissioning will need to be witnessed by the COR and can be performed by the contractor.

Excavation / Dewatering Please confirm whether excavation outside the existing lift-station pit is anticipated and whether bidders should include dewatering beyond removal of debris and standing water from the existing pit.

Excavation outside of the existing lift-station is not anticipated at this time. Dewatering beyond removal of debris and standing water is not anticipated.

Lift Station

Turf Restoration Limits The SOW requires repair and reseeding of turf damaged during installation. Please confirm the anticipated restoration limits and whether any specific seed mix, topsoil depth, erosion-control material, or establishment requirements apply.

Standard seed mix and topsoil depth should level with the opening and slope away from the pit. Any other disturbed areas should be level with the surrounding ground with top soil and grass seed.

Topsoil Requirements: No imported topsoil is required. The contractor shall reuse and rake the existing excavated soil from the post holes and demolition to fill voids and match adjacent grades.

Approved Seed Mix: A standard, low-cost commercial "contractor’s mix" or local highway-grade seed mix suitable for the region.

Mulch / Erosion Control: A standard application of clean agricultural straw mulch over the seeded areas to prevent immediate wash-out.

Watering Requirements: No temporary irrigation or daily watering is required. The contractor shall perform one initial watering immediately after seeding and mulching. Thereafter, establishment will rely on natural precipitation.

Maintenance & Acceptance: No prolonged maintenance, mowing, or 60-day establishment period is required. Final acceptance of the turf restoration is achieved once the Government Representative verifies the disturbed areas are properly graded, seeded, and mulched prior to demobilization.

Lift Station

Removed Equipment / Recycling Please confirm whether the removed pumps, motors, control panel, piping, valves, copper, and other metallic components are to be turned over to the Government, delivered to the installation recycling point, or removed/disposed of by the Contractor.

See 1.13 and 1.14 of SOW

Permits / State Approvals The SOW requires the Contractor to obtain required State of Michigan approvals, permits, and licenses. Please identify any specific lift-station, plumbing, electrical, environmental, or wastewater permits the Government expects to apply to this project.

State and local laws and licenses required to work on these systems. Environmental and wastewater are covered by the base.

Lift Station

Performance / Payment Protection The solicitation incorporates both FAR 52.228-15 and FAR 52.228-13. Please confirm the specific performance bond and/or payment-protection requirements and required amounts applicable to this contract.

Both Performance and Payment bonds are required if the resultant contract award exceeds $150,000 as required by the Miller Act and RFO FAR 28.102-1(a). RFO FAR 52.228-13, Alternative Payment Protections applies below this threshold and requries a Payment protection only, Payment Bond is preferred. Penal amount for Performance and Payment bonds or alternate payment Protections is 100% of the contract price, as stated in RFO FAR 52.228-13 Alternative Payment Protections and RFO FAR 52.228-15 52.228-15 Performance and Payment Bonds-Construction.

Lift Station Limitations on Subcontracting Please confirm whether FAR/RFO 52.219-14, Limitations on Subcontracting, applies to this 100% Small Business set-aside and, if so, identify the applicable limitation.

RFO FAR 52.219-14 Limitations on Subcontracting is not included in the contract and does not apply.

Lift Station

Project Location / Building Number The SOW and AF Form 66 identify the project as Repair Lift Station at Building 6954, while Attachment 3 is referenced elsewhere as B6854. Please confirm that Building 6954 is the correct project location.

B6954 is the correct location.

Lift Station Could you please provide any available record drawings or other documentation showing the dimensions and configuration of the existing lift station and the proposed replacement?

Estimate is 60in wide and approximately 20ft deep. We do not have currerent drawings or proposed replacement.

Lift Station

We understand that the scheduled pre-bid site visit took place on August 11.

Unfortunately, we were unable to attend the scheduled visit. Would the Government be willing to allow a prospective contractor to conduct a brief site visit at a mutually convenient time? The purpose would simply be to observe the existing lift station and surrounding conditions so that our contractor can accurately evaluate the work and prepare a responsible quotation.

The Government is not able to support a second site visit at this time.

With the replacement of the control’s cabinet is it the intent to replace the visible electrical piping and recking material as well?

Yes

Lift Station What is the pit depth? Approximately 20ft Lift Station What is the discharge size? 4in