This statement of work describes a roof replacement project for two buildings at the Maryland Air National Guard base. The contractor will demolish and remove the existing modified bitumen roof systems and install new thermoplastic polyolefin single-ply membrane roofs totaling approximately 31,907 square feet. The project also includes reinstalling components removed for work, installing new roof insulation, flashing, and sheet metal trim to match existing. The contractor must schedule work to avoid disrupting base operations between 6:30am and 5:00pm Tuesday through Friday and obtain approvals for other hours or days. The performance period is 180 days. The pre-proposal meeting will be held on February 29, 2024 and the question deadline is March 12, 2024, with bid opening on March 20, 2024. The solicitation is set aside for HUBZone small businesses and issued by the Department of the Army Maryland Army National Guard.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR ROOF BLDG 2040 AND 3010
STATEMENT OF WORK
PROJECT NUMBER: PJMS202006
MARYLAND AIR NATIONAL GUARD
MARTIN STATE AIRPORT
NATIONAL GUARD BASE
BALTIMORE, MARYLAND 21220
19 October 2023
1 General Project Information:
1.1 Project Location and Background: This project is located at the Martin State Airport Maryland Air National Guard, Baltimore, MD 21220. Multiple facilities: Operations Facility Bldg. 2040, and Engine Shop Bldg. 3010 require roof repair by replacement. This project entails demolishing each modified bitumen roofing system and insulation, selective demolition and replacement of roof deck panels as needed, removal/replacement of flashing, coping, and gutters, installation of new rigid insulation, cover board and single membrane Thermoplastic Polyolefin (TPO) roofing system. TPO roofing system to include all accessories to seal all vents, electrical and HVAC piping, roof top air handling units and roof top structures, penetrations, etc. Replace all coping/parapet caps, wall metal flashings and through-wall scuppers and downspout assemblies.
1.1.1 The contractor is responsible for providing specifications and field verify all site conditions, dimension and other factors which may affect the work. Contractor will provide all tools, materials, equipment, labor, and items as needed to properly complete the work in accordance with these specifications and the manufacturer’s instructions for TPO roofing systems. The area to be covered is approximately 31,907 sq. ft. (B2040 – 19,267sf and B3010 – 12,640sf) Contractor shall coordinate demolition and installation with the contracting officer representative, project manager and building managers of each building.
1.2 Site Description: This facility always requires security protection. Absolutely no photography of aircraft is permitted. The work areas are shown in the Site Plan submitted. See attached base map.
1.3 Use of Premises: The Contractor shall assume full responsibility for protection and security of materials and equipment stored on site.
1.3.1 Contractor shall move any stored products, under their control, which interfere with operations of the Government.
1.3.2 The contracting officer representative (COR) will determine the equipment, material and other staging locations or work areas available under this contract.
1.4 Government Equipment: Contractor use of Government owned or leased equipment such as: hoists, forklifts, compressors, welding machines, cutting rigs, etc. shall not be permitted on either a reimbursable or non-reimbursable basis. Cost for all equipment required to accomplish the work shall be included in the Contractor’s final bid price.
1.5 Permits and Inspections: Normally no permits or inspections by local building officials are required. All inspections will be performed by COR and roof manufacturer representative unless modified by the Statement of Work. All testing will be performed by the contractor unless modified within the construction documents.
1.5.1 Digging Permit: This permit is obtained from the Work Control Office (Facility 2100) at
(410) 918-6300. The Contractor is responsible for contacting ‘Miss Utility’ to mark the gas and electrical lines. The Contractor is responsible for hiring a private underground utility locating company to mark the water, sanitary sewer, storm sewer, broadband cable, and communication lines.
1.5.2 Burn Permit: Unless otherwise specified in other sections of this specification, the use of burning equipment or open flame welding and cutting shall be allowed only as authorized in writing by the local Fire Inspector (Facility 3150). Once approved by the Fire Inspector, a written AF Form 592 – USAF Welding, Cutting, and Brazing Permit will be issued. The permit will be issued by the fire department within one (1) hour of request and must be renewed daily.
1.6 Hours of Operations: The hours of operations at Martin State Airport for the Air National Guard are 10 hours per day (0630 – 1700) Tuesday – Friday. Coordinate access to premises with COR, for execution of work. Emergency situations, military operations, or other contingencies may cause suspension of work or restrictions on access to the construction site.
1.7 Off-Hours Work: Except as otherwise specified, all work shall be performed during regular work hours (indicated above). If the Contractor desires or is required to work on Mondays, Saturdays, Sundays, Holidays or other hours outside normal work schedule, the Contractor shall be required to seek written approval from the Contracting Officer. The Contractor is not entitled to premium time if the request is approved.
1.8 Change Orders: Only the COR or the Contractor may initiate change order requests. Do not proceed with any work until a signed modification or other written authority is received from the Contracting Officer. Only the Contracting Officer may approve a change order.
1.9 Field Changes: No changes in the cost or the scope of the project may be made without processing a change order. Field changes not involving cost or scope may be initiated by the Base Civil Engineer (BCE), COR, Contracting Officer, or the Contractor.
1.10 Daily Report and Sign-In Register: Each day the Contractor is on site to perform any work, the Superintendent/Foreman shall sign in at the Base Engineering Building (Facility 2100), indicating specific Facility/Location and the number of persons who shall be performing work that day.
1.11 Clean up: The work site is an active civilian and military airport. Site cleanliness and Foreign Object Debris (FOD) control is essential. The Contractor will clean up all construction debris and refuse and will remove it from the work site and the Base daily at their own expense.
1.12 Safety: The Contractor is responsible for performing all work In Accordance With (IAW) State and Federal OSHA requirements as well as compliance with the most current USACE EM 385- 1-1.
1.13 Environmental Protection and Waste Disposal: The disposal of all materials, which may include hazardous or toxic liquids that are used to perform the work, shall conform to all Federal, State, and Local environmental regulations. All dumpster service and waste management shall be provided at no additional cost to the Government. All recyclable metal shall be placed into Martin State Airport scrap metal recycling containers. Please contact the Base Environmental Scientist Greg Elmore at (410) 918-6486 for detailed information.
For more information, review “Environmental Protection Plan for Contractors”, which will be provided during the solicitation phase.
1.14 Hazardous Materials: If suspected hazardous materials are discovered, do not disturb, contact the COR.
1.15 Drawings: Drawings furnished by the government to the Contractor may be used for general information only and shall not be relied upon or used as the basis for preparation of contract drawings required by this contract without complete on-site verification by the Contractor.
1.16 Drawings are to be approved by the Base Civil Engineer and COR.
1.17 Description of Work: The Contractor shall describe in his or her proposal how they will manage the project. The Contractor shall identify key staff and their abilities to manage projects of this magnitude, including scheduling methods, reporting and execution.
1.18 Military Real Property Data – DD Form 1354 Worksheet: The Contractor shall furnish real property data to the Government via the DD Form 1354 worksheet, Building Information Checklist for the Transfer and Acceptance of Military Real Property, for each new construction and/or renovation project awarded, unless otherwise notified. The cost and unit of measure of each individual asset must be identified separately. If demolition work is within the scope of the project, demolished assets and demolition costs must also be identified. The Contractor is responsible for accuracy of data, current up to the time of completion. The Contractor should contact the Real Property Office at 410-918-6222 with questions pertaining to the DD Form 1354 worksheet. For construction data assistance, Contractor may contact the 175th Base Civil Engineer’s Office to speak with the COR, or Project Manager assigned to the project. See attachment 3.
1.19 Inspections: Contractor shall have roof manufacturer inspection team inspect the roof. An inspection of the completed work shall be conducted by the Contracting Officer Representative (COR) prior to reoccupation of the work site by Government Personnel.
1.20 Construction Performance Period: The Contractor shall confirm the proposed construction performance period which is 180 days. The proposed performance period will be included in the Cost Proposal.
1.21 Meetings: A Preconstruction Meeting will be required post award and prior to construction.
Weekly progress meetings will also be required.
1.22 Warranty:
1.22.1 Manufacturer’s Warranty: Contractor to install all TPO roofing system and components in a manner prescribed by Manufacturer to result in a minimum, twenty (20) year Certificate of Warranty on materials and workmanship. Contractor shall make all provisions to ensure Manufacturer acceptance and issuance of Manufacturer Written Warranty, including but not limited to, any corrections and or revisions identified by authorized Manufacturer’s Representative.
1.22.2 Contractor (Installer) Warranty: Contractor shall provide Certificate of Warranty for workmanship, including labor and materials per FAR clause 52.246-21.
1.23 Quality Control: The Contractor shall establish and maintain quality control to assure compliance with contract requirements and shall maintain records of his quality control for all construction operations required under this section. A copy of these records, as well as the records of corrective action taken, shall be furnished to the Government.
1.24 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions:
1.24.1 Notify the COR prior to arranging with Baltimore Gas and Electric (BG&E) to shut off and turn on electrical and/or natural gas utilities. Notify the COR not less than 7 days in advance of proposed utility interruptions. The Government will be responsible for all BG&E connection fees. Do not proceed with utility interruptions without the COR’s written permission.
1.24.2 Owner’s Trades personnel will make the necessary disconnects of any / all utilities, and for any RTUs the contractor will need to remove, for roofing installation, and reconnections of the same, upon completion by the contractor. Notify the COR not less than 7 days in advance of proposed utility interruptions.
1.25 Product Information: Provide all material submittals utilizing AF IMT 3000. Submittals will be reviewed by the Government and sent back. If a submittal is disapproved, vendor will need to resubmit prior to ordering materials. Submit 1 electronic sets of all AF IMT 3000 with attachments. If a hard copy is required, then the vendor shall submit 4 sets; 1 set for BCE, 1 set for Contracting, and 2 sets will be returned to the Contractor.
1.26 Submittals: Prior to start of work, Contractor shall submit the following for review and acceptance by Civil Engineering:
1.26.1 Production Schedule
1.26.2 Safety Plan/AHA
1.26.3 Safety Data Sheets (SDS)
1.26.4 Roofing membrane
1.26.5 Cover board
1.26.6 Insulation
1.26.7 Base flashing
1.26.8 Curb flashing
1.26.9 Sheet metal to include gauge and factory colors available, i.e., coping, flash, drip edge and fascia metals.
1.26.10Tape
1.26.11Adhesives and fasteners
1.26.12Caulking
1.26.13Detail drawing of the roof section
1.26.14Manufacturer Letter of Certification: Documenting that Contractor is qualified to install the Manufacturer’s Roofing System, which will result in Manufacturer’s Warranty, without undue limitations.
1.27 Base Access: The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services, or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.28 Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 10-245, AFI 31-101 and AFMAN 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.29 All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 45 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor, completing the Force Protection computer-based training (CBT) course on Joint Knowledge Online (JKO) at https://jkodirect.jten.mil/Atlas2/ faces/page/login/Login.seam. For those without a CAC, select "Non-CAC" user on the JKO site. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative.
2 Roof Replacement Scope of Work:
2.1 Demolition: Contractor shall do all corresponding work that is necessary to complete the work described in this Statement of Work (SOW) i.e., trapping, select-demo, moving dumpster, etc.
2.1.1 Contractor shall remove and reinstall any components necessary to complete this statement of Work (SOW) i.e., antennas, roof units, ladders, lights, gutters, down spout, etc.
2.1.2 Contractor shall remove existing modified bitumen roof assembly to the roof decking.
2.1.3 Contractor shall remove and repair all areas of the roof that are damaged. Repair shall be in a manner that it is able to except the new TPO roof without any wrinkles or ponding.
2.1.4 Contractor shall remove and reinstall metal insulation wall panel if necessary to install new roof TPO assembly.
2.1.5 Contractor shall clean and prepare roof deck for new TPO roof assembly.
2.1.6 Upon removal of existing roofing system, contractor shall coordinate COR inspection for inspection of hidden damages of structure substrate for acceptance, prior to installation of replacement roofing system.
2.1.7 Contractor shall use whatever method it needs to determine how under lying damage that needs to be repaired before installing the new over lay membrane.
2.2 Installation Building 3010 Engine Shop: All installation and work are to be finished in accordance with manufacture guideline for installation.
2.2.1 Contractor shall un-install and re-install insulated metal panel to install termination bar and TPO membrane.
2.2.2 Contractor shall install new crickets on the upslope side of all mechanical equipment mounted on the roof where applicable.
2.2.3 Contractor shall install .50 aluminum coping and drip edge on along all parapet roof/wall interface. Color to match existing.
2.2.4 Contractor shall furnish and install new, pre-manufactured flashings on all roof penetrations as specified by the roof system manufacturer.
2.2.5 Contractor shall install all new tape and caulk to all seams and roof penetrations.
2.2.6 Contractor shall install a single ply membrane 0.60 mil (white in color) fully adhered membrane roofing system that is fabricated of a Thermoplastic polyolefin (TPO) compound over new roof assembly. New TPO shall be installed over entire roof.
2.2.7 Contractor shall ensure all deck sheets and parapets will be pulled tight and installed as wrinkle-free as possible. Care shall be taken to remove ponding areas and to ensure proper drainage on the roof deck.
2.2.8 Sections 2.3.4 thru 2.3.14 apply to building 3010.
2.3 Installation Building 2040: All installation and work are to be finished in accordance with manufacture guideline for installation.
2.3.1 Any / All Roof top units (RTUs) on the building that need to be lifted from the curbs for roofing contractor to wrap that curb shall be the responsibility of the contractor.
2.3.2 Contractor shall install a single ply membrane 0.60 mil (white in color) fully adhered membrane roofing system that is fabricated of a Thermoplastic polyolefin (TPO) compound over new roof assembly. New TPO shall be installed over entire roof.
2.3.2.1 Contractor shall coordinate with CE for trades personnel to disconnect and reconnect utilities.
2.3.3 Contractor shall ensure all deck sheets and parapets will be pulled tight and installed as wrinkle-free as possible. Care shall be taken to remove ponding areas and to ensure proper drainage on the roof deck.
2.3.4 All replacement flashing and coping shall be factory painted (to match existing Urbane Bronze) and shall be installed so not to allow or create leaks in the TPO roofing system.
2.3.5 Contractor shall install all new flashing on the roofs edge with new .050” thick aluminum flashing. Form sections true to shape, accurate in size, square and free from distortion or defects. Interior walls milled aluminum is allowed.
2.3.6 Contractor shall install new crickets on the upslope side of all mechanical equipment mounted on the roof where applicable.
2.3.7 Contractor shall install .50 aluminum coping and drip edge on along all parapet roof/wall interface and edge. Color to match existing.
2.3.8 Where coping is installed along parapet walls, continuous cleats, or combination of cleats and clips of combatable materials shall be installed, in a manner to provide appropriate expansion / contraction capabilities preventing moisture infiltration.
2.3.9 Where copings are to be painted finish, such finish shall be factory applied. Only minor touch-up paint shall be allowed to be field applied.
2.3.10 Contractor shall install all new taping and caulk to all seams and roof penetrations.
2.3.11 Pre-Molded Accessories: All; Onside corners, outside, curbs wrap, pipe flashing, etc., shall meet criteria for TPO System’ Manufacturer’s warranty.
2.3.12 Mechanical Fasteners and Adhesives: All fasteners and adhesive components shall meet criteria for TPO System Manufacturer’s warranty.
2.3.13 Rigid Roof Insulation: Contractor is to install new 4-inch tapered layer of polyisocyanurate rigid foam insulation with an R-value of at least R30 to the roof deck. Provide for tapered gradual diminution to be able to obtain optimum drainage. Rigid insulation shall meet ASTM Type II standards.
2.3.13.1 Joints: Where multiple layers of rigid insulation are installed, the joints of the insulation boards shall be vertically staggered and offset from the joints in the underlying layer.
2.3.14 Gypsum Roof Board: To be a minimum of 1/4 inch thick insulation board. Insulation board shall be installed over rigid insulation, not against substrate. Note: Unless roofing manufacturer requires the board to be installed against the substrate. Insulation board shall meet ASTM Type II standards.
3 Certifications: Contractor shall provide a copy of the certification to ensure Register Roof Observer (RRO) is certified by the Roof Consulting Institute (RCI) and that the certification is up to date. The RRO shall have a minimum of three years’ experience as an RRO and must provide documentation of relevant experience in the installation monitoring, documentation, and inspection of roofing systems installations. Provide specific details regarding the installation monitoring and inspection of EPDM roofing systems within the RRO experience documentation. RRO must be fluent in English.
4 Standards: CHAPTER VII - STANDARDS FOR NEW ROOFING CONSTRUCTION, RE-
ROOFING CONSTRUCTION, AND ROOFING SYSTEM GUARANTEE
REQUIREMENTS – July2019 (https://dgs.maryland.gov/Documents/ofp/RoofingPolicy.pdf), Unified Facilities Criteria (UFC) 3-110-03 1 May 2012, Change 5, 12 June 2020, ASTM D6878/D6878M-21 Standard Specification for Thermoplastic Polyolefin-Based Sheet Roofing, ASCE 7 - Minimum Design Loads for Buildings and Other Structures, UL 790 Class A for fire resistance, UL 580 Class 90 for wind uplift resistance
5 Codes: National Fire Protection Association, national building code adopted by the local jurisdiction for wind, snow and seismic loads, Underwriters Laboratories and Factory Mutual
6 References: Factory Mutual Standard 4470 - Approval Standard for Class 1 Roof Covers, Underwriters Laboratories (UL) - Roofing Systems and Materials Guide (TGFU R1306), American Society for Testing and Materials (ASTM) - Annual Book of ASTM Standards, Sheet Metal and Air Conditioning Contractors National Association, Inc. (SMACNA) - Architectural Sheet Metal Manual, American Society of Civil Engineers (ASCE)
7 List of attachments:
7.1 Base map (Site Plan)
7.2 Roof Plans
7.3 Roof Details
--------- End Statement of Work ---------
1- OPRATIONS BLDG 2040 TORN SEAM TYP. 2- OPRATIONS LOOKING N.
3- OPRATIONS ROOF DRAINS. 4- OPRATIONS LOOKING E.
5- OPRATIONS LOOKING SE. 6- OPRATIONS LOOKING W
7- ENGINE SHOP BLDG 3010 LOOOKING NE. 8- ENGINE SHOP BLDG 3010 LOOOKING N.
9- ENGINE SHOP ROOF DRAINS. 10- ENGINE SHOP TARES IN MEMBRANE TYP.
11- ENGINE SHOP BUBBLE IN MEMBRANE TYP. 12- ENGINE SHOP UPHEAVE IN MEMBRANE.