B16 Switchgear Transformer RFIs Current as of 6Nov26.xlsx
XLSX spreadsheet 18 KB Posted
- Attached to
- Switchgear Transformer Replacement
- Solicitation number
- W50S7X27Q0001
- Issued by
-
Department of the Army National Guard
About this file
This file is a Request for Information (RFI) log documenting inquiries and responses related to the Switchgear Transformer Replacement solicitation for Building 16 at the 184 Wing. The RFI document, current as of November 6, 2026, tracks questions submitted by potential offerors regarding the procurement of one Control Power Transformer and three Transformer fuses, along with installation services. The RFIs capture technical clarifications, specification details, and other inquiries necessary for offerors to prepare compliant proposals. This document serves as a historical record of communications between the government and industry to ensure transparency and equal information distribution to all interested parties during the pre-award phase of the solicitation process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combined Synopsis Solicitation B16 Switchgear Transformer Amend.pdf | ||
| LV Termination.jpg | JPG image | |
| B16 Transformer Drawings.pdf | ||
| Transformer Data Plate.jpg | JPG image | |
| B16 Switchgear Transformer RFIs Current as of 28Oct26.xlsx | XLSX spreadsheet | |
| HV Termination.jpg | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Questions | Answer | ||
| 1 | Existing Switchgear Enclosure Dimensions: Could you please provide the dimensions of the existing switchgear enclosure? Is the replacement transformer required to fit within the existing enclosure, or will modifications or a new installation arrangement be acceptable? | Existing switchgear enclosure dimensions 33” W x 90” H x 54” D. Prefer replacement transformer to fit within existing enclosure to avoid modification to existing equipment & concrete pad. | |
| 2 | HV and LV Termination Requirements: Are there any specific high-voltage (HV) and low-voltage (LV) termination configurations we must follow? Our supplier can offer the following options: | ||
| o | Stubs up | ||
| o | Bus to ends, with optional ATCs | ||
| o | Coordinated bus to ends, with optional braided flex | ||
| Could you please confirm the required termination configuration or advise whether these options are acceptable? | The straightforward and cost-effective option would be the Stubs Up option as that is the current method of termination. | ||
| 3 | Please provide the nameplate information for the Building 16 switchgear that houses the control power transformer: manufacturer, model or type, serial number and ratings. A photograph of the nameplate would be sufficient. | Picture of date plate attached. Manufacturer: Instrument Transformers, Inc. (GE/ITI) |
Model: 3CPTDV5-95-112.5-SD07035 Serial Number: 5200779 Rating: 112.5 kVA, 15 kV Class/ 95 kV BIL
| 4 | Please provide the physical dimensions (height, width, depth) and weight of the existing GE ITI 3CPTDV5-95-112.5-SD07035 control power transformer. A photograph of the transformer nameplate or an outline drawing, if available, would also help. | Rough physical dimensions 38” W x 28” D x 56” H Weight: 2400 |
| 5 | Does installation include removal, rigging, electrical reconnection, testing, commissioning, and disposal? | Yes. It is the intent of the government for the contractor to provide a complete and useable system. |
| 6 | Who will coordinate and perform the required electrical shutdown and restoration? | The awarded vendor will coordinate with the local utilities having jurisdiction and the 184 Engineering Team. |
| Does the 90-day requirement apply to equipment delivery only or completed installation? | Yes/ Equipment delivery timeline will be considered in evaluation | |
| 7 | What outage times and maximum downtime are acceptable? | There shouldn’t be a down time from what we are seeing on our and as this just supports the building power not the generators themselves. If they contractor is seeing something different we would ask for at least 2-weeks notice so we can inform all missions. |
| 8 | Is rebuilding the existing transformer an option, or is a new unit required? Would temporary control power be needed during the outage? | New only, the transformer is old and the risk of it happening again is too great. We are already supplying temp power and will keep it that way to help the contractor. |
| 9 | What acceptance testing is required, including any NETA testing after installation? | Yes |
| 10 | Will any preventive maintenance work be needed on the switchgear while it is shut down? | No |
File details come from the government source that posted it. Updated .