B16 Switchgear Transformer RFIs Current as of 28Oct26.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
Switchgear Transformer Replacement
Solicitation number
W50S7X27Q0001
Issued by

About this file

This file is a Request for Information (RFI) document containing questions and answers regarding a switchgear transformer replacement project for Building 16. The Department of the Army National Guard, specifically the 184 Wing, is procuring one control power transformer and three transformer fuses to replace the existing indoor switchgear transformer, with installation services included under Solicitation Number W50S7X27Q0001. The existing switchgear enclosure measures 33" W x 90" H x 54" D, and the government prefers the replacement transformer to fit within these existing dimensions to avoid modifications to existing equipment and concrete pads. The current transformer is a GE/Instrument Transformers, Inc. model 3CPTDV5-95-112.5-SD07035 with a rating of 112.5 kVA, 15 kV Class/95 kV BIL, measuring approximately 38" W x 28" D x 56" H and weighing 2,400 pounds.

The RFI confirms that termination requirements will follow the current "Stubs Up" configuration for cost-effectiveness, and the contractor must provide complete installation services including removal, rigging, electrical reconnection, testing, commissioning, and disposal. The awarded vendor is responsible for coordinating electrical shutdowns and restoration with local utilities and the 184 Engineering Team. Equipment delivery timeline will be a factor in the evaluation, though the document does not explicitly state the delivery deadline referenced in the solicitation. A site visit is scheduled for November 10, 2026, at 0900 hours.

View the file

Other files

File Type Posted
Combined Synopsis Solicitation B16 Switchgear Transformer Amend.pdf PDF
B16 Switchgear Transformer RFIs Current as of 6Nov26.xlsx XLSX spreadsheet
LV Termination.jpg JPG image
B16 Transformer Drawings.pdf PDF
Transformer Data Plate.jpg JPG image
HV Termination.jpg JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionsAnswer
1Existing Switchgear Enclosure Dimensions: Could you please provide the dimensions of the existing switchgear enclosure? Is the replacement transformer required to fit within the existing enclosure, or will modifications or a new installation arrangement be acceptable?Existing switchgear enclosure dimensions 33” W x 90” H x 54” D. Prefer replacement transformer to fit within existing enclosure to avoid modification to existing equipment & concrete pad.
2HV and LV Termination Requirements: Are there any specific high-voltage (HV) and low-voltage (LV) termination configurations we must follow? Our supplier can offer the following options:
oStubs up
oBus to ends, with optional ATCs
oCoordinated bus to ends, with optional braided flex
Could you please confirm the required termination configuration or advise whether these options are acceptable?The straightforward and cost-effective option would be the Stubs Up option as that is the current method of termination.
3Please provide the nameplate information for the Building 16 switchgear that houses the control power transformer: manufacturer, model or type, serial number and ratings. A photograph of the nameplate would be sufficient.Picture of date plate attached. Manufacturer: Instrument Transformers, Inc. (GE/ITI)

Model: 3CPTDV5-95-112.5-SD07035 Serial Number: 5200779 Rating: 112.5 kVA, 15 kV Class/ 95 kV BIL

4Please provide the physical dimensions (height, width, depth) and weight of the existing GE ITI 3CPTDV5-95-112.5-SD07035 control power transformer. A photograph of the transformer nameplate or an outline drawing, if available, would also help.Rough physical dimensions 38” W x 28” D x 56” H Weight: 2400
5Does installation include removal, rigging, electrical reconnection, testing, commissioning, and disposal?Yes. It is the intent of the government for the contractor to provide a complete and useable system.
6Who will coordinate and perform the required electrical shutdown and restoration?The awarded vendor will coordinate with the local utilities having jurisdiction and the 184 Engineering Team.
Does the 90-day requirement apply to equipment delivery only or completed installation?Yes/ Equipment delivery timeline will be considered in evaluation
7