RFI 1 - Repair Base Fire Alarm.pdf

PDF 195 KB Posted

Attached to
183 CES Repair Base Fire Alarm
Solicitation number
W50S7U-26-B-A001
Issued by

About this file

This is a Request for Information (RFI) document for Solicitation/RFQ #W50S7U-26-B-A001/CES Repair Base Fire Alarm, issued on 23 June 2026. The RFI addresses a single question and answer regarding the Period of Performance (PoP) for D-21 fire alarm equipment and installation services at a repair base facility.

The inquiry concerns standard lead times of 360 days from the date of award, which are necessary to accommodate equipment stocking issues and technician mobilization. The government confirmed that the Period of Performance in the contract award may be extended up to 360 calendar days based on the bids received and standard lead time information known. This response clarifies that contractors should anticipate an extended performance schedule to account for procurement and mobilization requirements associated with the D-21 equipment installation project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/RFQ # W50S7U-26-B-A001/CES Repair Base Fire Alarm

REQUEST FOR INFORMATION (RFI) #1 23 June 2026

Q1. Standard lead time for equipment and installation of D-21 equipment is 360 days from date of award to account for equipment stocking issues and technician mobilization. Can the

Period of Performance (PoP) be extended to reflect these lead times?

A1. Yes, the Period of Performance in the contract award may be up to 360 calendar days based on the bids received and the standard lead time information known.

File details come from the government source that posted it. Updated .