Questions and Answers - Dated 16 May 2025.pdf
PDF 133 KB Posted
- Solicitation number
- W50S7L25BA002
- Issued by
-
Department of the Army National Guard
About this file
This document contains Questions and Answers related to Solicitation W50S7L-25-B-A002, dated 16 May 2025, for a construction project at the Montana Air National Guard. The Q&A addresses technical details including concrete mix design requirements, discharge time limits, pavement testing, joint repair, barricades, and grounding rod installation. Key clarifications include: concrete discharge time can be extended to 150 minutes with hydration stabilizers, overcutting is allowed for concrete removal with minimal expansion, no existing pavement testing is required, approximately 5,400 linear feet of joint sealing will be performed, and a free zone will exist with no operational constraints where equipment can be left overnight.
The solicitation is for repair of tiedowns and apron markings, set aside 100% for small businesses, with a project value between $500,000 and $1,000,000. The project will be located at the Montana Air National Guard base in Great Falls, MT, with a contract duration of 59 calendar days. The pre-bid conference is scheduled for 12 May 2025, bid questions are due by 22 May 2025, and the bid opening is planned for 29 May 2025. Contractors must be registered in the System for Award Management (SAM) and cannot subcontract more than 15% of the work to non-similarly situated entities.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS RELATED TO :
SOLICITATION W50S7L-25-B-A002
As of 16 May 2025
Q1. Concrete Mix Design Requirements
The concrete mix design requirements—including detailed proportioning studies and aggregate quality testing. This includes: - Aggregate testing conducted within one year of submittal (1.3.2.1), - 28-day ASR testing and petrographic analysis via ASTM C295 for coarse aggregates (2.3), - Three-point mix design curve (2.13.2). These requirements demand substantial time and financial investment from bidders during the proposal phase.
We respectfully request confirmation that no changes to these requirements will be made post-award.
A1. These specifications are to meet Airfield Concrete requirements, specification is pulled from most recent USGS. Please note first statement in Section 32 13 14.14 Pg 77, 2.1 on existing mix design availability.
Q2. Concrete Discharge Time Limits
This paragraph limits concrete placement to within 90 minutes of cement discharge into the mixer. However, modern hydration stabilizers effectively extend the workable life of concrete. Given that the project involves many small-volume placements, allowing an extended discharge time would: - Improve batching efficiency, - Enhance consistency across placements, - Reduce risk of cold joints. We request approval to extend the allowable discharge time to 150 minutes when hydration stabilizers are used.
A2. Allowable discharge time can be extended to 150 minutes when hydration stabilizers are used. Hydration stabilizers must be in the concrete design if used.
Q3. Clarification on Overcutting
Is overcutting allowed on the 42” x 42” x 9” cutout sections during demolition or replacement? Please clarify if there are dimensional tolerances or constraints on overcutting these concrete removal areas. If overcutting is permitted, are there restrictions on maximum allowable overage or backfill/repair procedures?
Q3. Overcutting is allowed on the cutout sections. Contractor to cut the minimal amount of overcutting to allow for the bottom intersection of concrete to be cleanly cut.
Q4. Existing PCC Pavement Testing Requirements
Are there any Government requirements for coring or testing the existing Portland Cement Concrete (PCC) pavement prior to or during demolition and replacement? Please clarify whether the following are required: - Compressive strength testing - Environmental (e.g., hazardous materials) testing - Thickness verification - Condition assessment (e.g., delamination, cracking, etc.) Additionally, if coring or in-situ testing is required, please specify: - Test frequency, - Acceptable testing methods (e.g., ASTM standards), - Whether government will provide historical test results (if available).
A4. No coring or testing of the existing PCC pavement is required. Testing frequency of new concrete will follow specifications in Section 32 13 14.14. Subsection 3.11
Q5. Joint Repair & Sealing
Please state the unit counts in LF of the joint repair and sealing, and advise if spalling repair is part of this task? If so, what SQ of spalling repair is to be completed?
A5. Joint seal, Detail C-201 #1 has approximately 5,400 linear feet. Spall repair is not a part of this task.
Q6. Barricades & Free Zone
Please advise if this project will have a free zone. If so, what are the operational constraints of the free zone (i.e. can equipment be left overnight).
Please also confirm which barricades are required, who supplies them, and if they are to encompass the entire work area or will be moved in phases (i.e. per parking space).
A6. Montana Air National Guard Free Zone will exist and there will be no operational constraints within freezone. Freezone does not extend into the controlled movement area, which is controlled by the FAA tower. Equipment can be left overnight, however, must be in a stored position and cleaned up to prevent FOD. Barricades are required at connections to the taxiway and operational apron. Additionally, barricades will be required when the taxiway is closed for work within the controlled movement area. Barricades are to be provided by the contractor.
Q7. Deployment Prerequisites
Has an FAA Obstruction Study been initiated? If not, will that be the government’s responsibility or contractors?
Has an airfield waiver been initiated? If not, will that be the government’s responsibility or contractors?
A7. FAA Obstruction Study not required, not constructing any new vertical structure. Airfield notice FAA 7460-1 filed by government.
Q8. Grounding Rods
For installation of the grounding rods, at what depth is the weathered sandstone encountered?
A8. Weathered sandstone at MTANG is approximately 4’ below grade. Historically, to provide adequate depth for the not less than 10 ft long rod, coring with a drill rig was used. Once grounding rod is installed, backfill cored hole with material that provides not more than 10,000 ohms of resistance.