Fire Suppression Questions and Answers.pdf

PDF 278 KB Posted

Attached to
Repair Fire Suppression B25/80 Federal contract opportunity
Solicitation number
W50S7L-21-B-0002
Issued by
Department of the Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Repair Fire Suppression B25/80, newest first.
File Type Posted
C4-Abstract - OF1419.pdf PDF
B25 Fire Room.pdf PDF
B8-W50S7L21B0002 Basewide Fire Suppression Amend 2.pdf PDF
B25-80 Floor Plan.pdf PDF
B25 Exterior HVAC pix.pdf PDF
Updated Drawings Bldg. 25-80 Fire Suppression- Pull Boxes REV 1 7UN21.pdf PDF
B8-W50S7L21B0002 Basewide Fire Suppression Amend 1.pdf PDF
B8-W50S7L21B0002 Basewide Fire Suppression.pdf PDF
Updated Drawings Bldg. 25-80 Fire Suppression- Pull Boxes.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fire Suppression Questions and Answers

1. For this job, are we to add abort stations with the associated wiring and programming or remove this function if already integrated?

a. Per CETSC guidance MANG doesn’t need the abort buttons.

2. According to the updated drawings posted on SAM, there appears to be (1) room where there is the foam/ water releasing panel that is for both Blg 80 and Bldg 25.

However, Appendix A of the SOW has a quantity of (1) for para. 3.7 Bldg 25 and quantity of (1) for 3.7 Bldg 80. Is 3.7 a total quantity of (1) for both bldgs or is it two separate AC systems?

a. The HEF systems for Bldg 25 and Bldg 80 are separate and distinct systems.

Bldg 80 has its own foam/water releasing panel and Bldg 25 has its own foam/ water releasing panel not shown on drawing for a total of 2.