B8-W50S7L21B0002 Basewide Fire Suppression Amend 1.pdf

PDF 379 KB Posted

Attached to
Repair Fire Suppression B25/80 Federal contract opportunity
Solicitation number
W50S7L-21-B-0002
Issued by
Department of the Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Repair Fire Suppression B25/80, newest first.
File Type Posted
C4-Abstract - OF1419.pdf PDF
B25 Fire Room.pdf PDF
B8-W50S7L21B0002 Basewide Fire Suppression Amend 2.pdf PDF
B25-80 Floor Plan.pdf PDF
B25 Exterior HVAC pix.pdf PDF
Fire Suppression Questions and Answers.pdf PDF
Updated Drawings Bldg. 25-80 Fire Suppression- Pull Boxes REV 1 7UN21.pdf PDF
B8-W50S7L21B0002 Basewide Fire Suppression.pdf PDF
Updated Drawings Bldg. 25-80 Fire Suppression- Pull Boxes.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W50S7L21B0002

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to update the SOW and the draw ings to inlcude the 6th pull station in Bldg 80 and remove the signage requirement. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Jun-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S7L21B0002

X 9B. DATED (SEE ITEM 11)

20-May-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Jun-2021

CODE

120 BASE CONTRACTING OFFICE

MONTANA AIR NATIONAL GUARD

2800 AIRPORT AVE B

GREAT FALLS MT 59404-5570

W9124V 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been modified:

STATEMENT OF WORK

STATEMENT OF WORK

Repair Fire Suppression, Hangars B25 & B80

JKSE 202404

Revised 10 June 2021

120th Airlift Wing

GREAT FALLS INTERNATIONAL AIRPORT 2 00 AIRPORT

AVE B

GREAT FALLS, MT

10 June 2021

Table of Contents

1. SCOPE OF WORK Page 1

2. AREA OF WORK Page 1

3. DESCRIPTION OF WORK Page 1-9

4. PERIOD OF PERFORMANCE Page 9

5. MATERIALS Page 9

6. MATERIAL SUBMITTALS Page 9

7. GENERAL CONDITIONS Page 9

8. DIFFERING SITE CONDITIONS Page 10

9. GOVERNMENT WORKING HOURS Page 10

10. UTILITIES Page 10

11. DISPOSAL OF MATERIALS AND CLEANUP Page 10

12. MATERIAL & EQUIPMENT ACCOUNTABILITY Page 10

13. SECURITY Page 10

14. ESCORTS Page 10

15. Appendix A Page 11

1. SCOPE OF WORK:

The contractor shall provide all personnel, equipment, tools, materials, supervision, transportation, and other items and services necessary to complete the work as described in this Statement of Work. Work location is at the Montana Air National Guard, GTF International Airport, Great Falls, MT.

2. AREA OF WORK:

Contractor shall work only in the areas designated by Contracting Officer Representative

(COR).

3. DESCRIPTION OF WORK:

The work specified by this section consists of furnishing all labor, equipment, tools, appliances, transportation, materials, and quality control reports required to perform modifications to Hangar Fire Suppression Systems. The work consists of three main items and multiple secondary items. The main items include reprogramming/reconfiguring the foam releasing panel, replacing the manual foam releasing stations and conduits, and installing Surge Protection Devices (SPD) (also referred to as TVSS). The secondary items include replacing heat detectors, providing insulation on the brass trim piping, providing HVAC in the foam rooms, providing required signage, and replacing non-brass trim piping. Not all hangars require all items be performed. See the tables in Appendix A for actual work required in each Hangar.

3.1 All work performed under this SOW shall be conducted in accordance with applicable state and federal laws and regulations, ANG policies and regulations, and this SOW as outlined below.

3.1.1 UFC 3-600-01- Fire Protection Engineering For Facilities

3.1.2 UFC 4-211-01- Aircraft Maintenance Hangars: Type I, Type II and Type III

3.1.3 NFPA 11 – Standard for Low-, Medium-, and High-Expansion Foam

3.1.4 NFPA 16 – Standard for Foam-Water Sprinkler and Foam-Water Spray Systems

3.1.5 NFPA 70 – National Electrical Code

3.1.6 NFPA 72 – National Fire Alarm and Signaling Code

3.1.7 NFPA 409 – Standard on Aircraft Hangars

3.1.8 ANG ETL 01-1-1 Air National Guard Design Policy

3.2 No Aircraft shall be in the hangar bay while this work is performed without prior approval. Prior to performing any work, disable the foam releasing system. Notify the fire department at least 24 hours in advance that the hangar bay fire suppression systems are going to be disabled. All other fire suppression systems should remain active.

3.3 Reprogram/Reconfigure Releasing Panels

a) Hangar bay with multiple foam risers - Verify that the foam releasing panel is not configured to release foam if the pressure switch in one foam riser is activated. If the panel is configured to release foam from a pressure switch activation, reprogram/reconfigure the releasing panel to remove this function. The foam riser pressure switches should cause an alarm but not activate any release solenoids.

b) Test that the activation of a pressure switch or an individual heat detector will not activate the foam system. Test that the activation of cross zoned heat detectors will activate the foam system. System may be tested without actual discharge of water or foam.

c) Reroute conduit such that it does not enter the top of the foam/water releasing panel

3.4 Replace manual foam releasing (start) stations and conduit

a) Demo all existing releasing stations, associated wiring and conduits as required.

b) Install new water tight ¾” conduit and junction boxes from the releasing stations to a height of 15 feet above the finished floor or until the conduit intersects a horizontal run.

Route the conduit into the bottom of the manual foam releasing stations. Provide the low point of this conduit with a drain (See figure 1). Where the conduit is in a hazardously classified area, provide breathers in isolated portions of the conduit (e.g. sealed off from the remaining conduit system). Rate drains and breathers for the electrical (hazard) classification in which they are installed, but not be less than NEMA 250 Type 4. Flexible conduit is not permitted.

c) Install new NEMA 250 Type 4 manual foam releasing stations and signage.

The releasing stations shall be distinctively different from the manual fire alarm pull stations.

Provide tamper cover with colored portions in yellow and lettering on the cover reading "FOAM";

the words "FIRE", "ALARM", or "AGENT" are prohibited to appear on the cover or station.

Provide locking type manual foam releasing stations that when activated require a key to be reset.

Provide a clear plastic tamper cover over the manual foam releasing station that when lifted emits an audible alarm. Exception: Audible alarm is not required where a manual foam releasing station is installed in a hazardous (classified) location.

Provide conventional manual foam releasing stations. Do not locate addressable monitor modules for the manual foam releasing stations in the hangar bay. Approved model is RSG RMS-EX-WP or approved equivalent.

Install manual foam releasing stations within the hangar bay so they are unobstructed, readily accessible, and located within 10 ft. (3.0 m) of each required exit or exit access from the hangar bay. Maintain a minimum separation distance of 5 ft. (1.5 m) between general fire alarm pull stations (if provided) and the manual foam releasing stations. Where possible, install the manual foam releasing stations on the opposite side of the door from the general fire alarm pull stations. If possible locate the releasing station and sign so that a future stop station and sign may be installed per figure 1.

Control valves shall be electrically supervise normally open control valves.

Electrical or mechanical supervision is not required for normally closed control valves, unless opening the valve is detrimental to the system operation. When supervision is required on normally closed valves, provide electrical supervision such as cable type monitoring.

d) Provide the sign for the manual foam releasing station with a yellow or lime-yellow background with "START FOAM SYSTEM" in red lettering not less than 3 inches (76 millimeters) high. The a sign a minimum of 24 inches (610 mm) high by 20 inches (508 mm) wide.

Locate the manual foam releasing station with tamper cover on the lower portion of the sign. Provide the word "START" in minimum 1 inch (25.4 mm) high green lettering placed directly above the manual foam releasing station.

e) Install new wire as required. All conductors must be 16 AWG minimum. Pull all conductors splice free; conductors shall be continuous from device to device. The use of wire nuts, crimped connectors, or twisting of conductors is prohibited.

f) Test the system in accordance with the procedures outlined in NFPA 72. The tests shall be witnessed by the Owner's Representative and test results recorded. The required tests for the releasing station circuits are as follows:

(1) Loop Resistance Tests: Measure and record the resistance of each circuit with each pair of conductors in the circuit, short-circuited at the farthest point from the circuit origin.

(2) Verify the absence of unwanted voltages between circuit conductors and ground.

(3) Visually inspect wiring.

(4) Test each release station and circuit for proper operation and response at the control unit and tested in accordance with manufacturer's recommended calibrated test method.

3.5 Install Surge Protection Devices

Install Surge Protection Devices (SPDs) to protect all power supply circuits to the Fire Alarm and Foam releasing panels, including any subpanels (e.g. Autonomous Control Unit, amplifier panels, and Notification Appliance Circuit (NAC) booster panels). Provide SPDs to protect all signaling line circuits, indicating device circuits, or notification appliance circuits that leave or enter a Facility’s exterior enclosure. SPD must be provided at the first location where connections are made that is close to where the circuit enters or leaves the Facility, prior to connection to any other devices when feasible. SPDs are not required for devices connected directly to the Facility exterior when the Facility itself is provided with lightning protection (i.e. an electric bell or speakers mounted on the exterior wall of the Facility.) SPD shall have both a UL 1449 and UL 1283 listing and shall be located in an adjacent terminal box unless the SPD is listed and installed in the control panel by the factory (e.g. Installing SPDs not listed with the panel is prohibited). A typical installation is shown in figure 2. Provide and install SPDs in accordance with UFC 3-520-01 Section 3-4, NFPA 780-28 Section 4.20., and NFPA 70 National Electric Code.

Figure 2

3.6 Repair Trim Piping

a) Brass Trim - Contractor shall replace all non-brass trim on all of the foam/water deluge valves for each system on base. Contractor shall replace the non-brass trim with the manufacture’s standard brass trim package. Install foam pipe insulation on any trim piping which if frozen can cause the deluge valve to open.

b) Tamper Seals & Signage - Mechanically lock or provide tamper seals such as zip-ties on trim valves, that when opened or closed are detrimental to the operation of the foam/water system such as the shutoff for the pressure switch. Provide signage indicating the valve’s normal operating position.

c) Insulate Trim piping –Install polyethylene insulation on all trim piping which if it leaked could cause the deluge valve to open.

3.7 HVAC for Foam Room with Releasing Panel

Contractor shall install a split unit to provide HVAC in each room with a Releasing Panel.

The contractor shall size the equipment based on current loading in each room. The unit shall provide HVAC to provide a temperature range between 60 degrees Fahrenheit and 80 degrees Fahrenheit. Winter operations is required. The relative humidity requirements (RH) of the unit shall provide a maximum RH of 80%.

4. PERIOD OF PERFORMANCE:

Work must be completed in 45 calendar days.

5. MATERIALS:

Construction materials must meet all required NFPA and UL requirements.

6. MATERIAL SUBMITTALS:

The contractor shall submit to the CO for approval all items listed on attached Material Submittal Schedule, AF Form 66 within 10 calendar days of the notice to proceed - or - provide a copy of the AF Form 66 indicating when each material submittal shall be submitted for approval.

Ensure that any disapproved material submittal will not impact the approved project execution schedule, as disapproved submittal shall not be considered grounds for a time extension. Allow for a minimum of 5 calendar days for the Government’s processing of material submittals. The contractor shall not order, deliver or install any materials without CO’s material approval or remove any materials on site, which have not been properly approved.

7. GENERAL CONDITIONS:

Contractor and all personnel shall comply with the Standard codes as required by the State of Montana. All electricians shall be licensed with the State of Montana as a minimum of Journeyman Electrician.

7.1. Contractor shall field verify all site conditions, quantities, measurements, and project requirements.

7.2. Contractor shall protect and barricade all work areas at all times to protect workers and the public from injury.

7.3. Contractor shall protect all structures, utilities, vegetation, sidewalks and vehicles from damage at all times. Replace all damaged materials with new materials to the satisfaction of the Government, at no additional cost to the Government.

8. DIFFERING SITE CONDITIONS:

Bring any unforeseen project conditions to the attention of the CO immediately. Differing site conditions, which may alter the scope of work, shall be approved by the CO prior to such work being performed.

9. GOVERNMENT WORKING HOURS:

Work hours shall be Monday thru Thursday 0700-1700 hours, with the exception of Federal holidays. Contractor must have prior approval in writing to work outside these guidelines.

10. UTILITIES:

The Government shall provide at no cost to the Contractor reasonable amounts of water and electricity to support the contract. Hook up will be to existing outlets and will be the contractors responsibility.

11. DISPOSAL OF MATERIALS AND CLEANUP:

The contractor shall not use any government disposal bins, dumpsters or trash receptacles for any reason at any time. The contractor shall provide appropriate disposal bins/trash receptacles.

Approval of disposal bins/trash receptacles location(s) shall be coordinated through government project manager. The contractor shall not allow debris to leave the work area due to potential damage to aircraft engines. Contractor shall coordinate with the base Environmental Management Office (EMO) prior to disposing any materials off base. All debris or trash shall be disposed of off base. All demolition debris shall be disposed of at a permitted landfill, with landfill authorization, unless other arrangements have been coordinated through the EMO. Provide proof of landfill disposal from the landfill that accepts the materials. This may be accomplished by providing the government project manager with landfill receipts; waste manifests, or weight tickets from the landfill that accepts the construction debris. Contractor shall clean up after each work period and dispose of all debris at the close of each day.

12. MATERIAL & EQUIPMENT ACCOUNTABILITY:

Notify the government project manager prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the government project manager. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and turned away.

13. SECURITY:

Security Forces shall monitor the incoming and outgoing of work personnel during the duration of the project. All deliveries shall be coordinated with the COR to arrange for their entrance onto Base property. The Contractor shall submit an Entry Authorization List (EAL) to gain access to the base for work.

14. ESCORTS:

Contractors will be escorted when working within the restricted areas of the hangars. A security briefing will be conducted prior to the start of the contract.

All Contractor personnel shall have a minimum of one (1) Form of Photo Identification with them at all times.

EAL

APPENDIX A

(End of Summary of Changes)

BLDG 80 ‐ System

Para. Item Quantity Unit

3.6b Provide tamper seals and signage on foam/water riser trim valve 1 Each

3.6c Install insulation on the foam/water deluge valve piping. 1 LS

3.3c

Reroute the conduit such that it does not enter the top of the foam/water releasing panel

Each

3.3 a & b Reprogramming panel 1 Each

3.7 Provide air conditioning in the room where the foam/water releasing panel is located

LS

3.5 Provide surge protection device to protect the foam/water releasing panel and sub‐panels

3.4 Replace Pull Stations to NEMA 4 Pull Stations 6 Each

3.3b & 3.4f System Testing 1 Each

BLDG 25 ‐ System

Para. Item Quantity Unit

3.6a Replace non‐brass trim on the foam/water deluge valve 2 Each

3.6b Provide tamper seals and signage on foam/water riser trim valve 1 Each

3.6c Install insulation on the foam/water deluge valve piping. 1 LS

3.3c

Reroute the conduit such that it does not enter the top of the foam/water releasing panel

3.3 a & b Reprogramming panel 1 Each

3.7 Provide air conditioning in the room where the foam/water releasing panel is located

LS

3.5 Provide surge protection device to protect the foam/water releasing panel and sub‐panels

3.4 Replace Pull Stations to NEMA 4 Pull Stations 5 Each

3.3b & 3.4f System Testing 1 Each