Questions and Answers HAYW 26-2010 Bldg. 102 110 Flooring.docx
DOCX document 25 KB Posted
- Attached to
- Replace Flooring Bldg 102 & Bldg 110
- Solicitation number
- W50S6T26QA021
- Issued by
-
Department of the Army National Guard
About this file
This is a Questions and Answers document for a federal flooring replacement solicitation (HAYW 26-2010, Solicitation Number W50S6T26QA021) issued by the Department of the Army National Guard for Buildings 102 and 110.
The project requires removing approximately 1,260 square feet of vinyl and carpet flooring and reconditioning approximately 4,825 square feet of existing floors across two buildings, with an estimated contract value between $25,000 and $100,000. Building 102 contains concrete flooring, carpet, and vinyl tile, while Building 110 has concrete flooring with vinyl asbestos tile present only in the restroom (8'6" x 5'). For concrete floor reconditioning, contractors must use Lithium Silicate Densifier, penetrating polyurethane, semi-rigid polyurea joint filler, and micro-aggregate traction additive mixed into the final guard coat, with polishing progressing from initial grit to 400-800 grit (satin/honed finish) per DAFMAN 91-203 specifications. All crack, joint, and spalling repair estimates must be submitted as separate line items in the bid for government approval, as the exact extent of necessary repairs cannot be determined until existing flooring is removed. Updated as-built plans and specifications were to be provided by the Contracting Officer by June 10, and photographs of existing conditions were made available. A mandatory site visit was scheduled for May 27 at 0800 PDT at the west gate parking lot, requiring offerors to complete DBIDS prequalification and submit base access forms five business days prior.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Type
| Number |
| Text |
| Question |
| 1 |
| How do [interested offerors] get plans and specs for this project? |
| Answer |
| 1 |
| CE will provide most updated As-Builts to Contracting by 10 JUN. |
| Q |
| 2 |
| Is there lead or asbestos in the existing flooring? |
| A |
| 2 |
| Asbestos located in the restroom in Building 110. |
| Q |
| 3 |
| What is the existing flooring [material]? |
| A |
| 3 |
| Pg. 2 SOW: Bldg. 102 – Concrete floor, Carpet, Vinyl Tile / Bldg. 110 – Concrete Flooring, Vinyl Asbestos Tile (only in restroom – 8’ 6” x 5’). |
| Q |
| 4 |
| [Does the Government] have pictures? |
| A |
| 4 |
| Will provide to Contracting. |
| Q |
| 5 |
| What material should be used for the polished concrete? |
| A |
| 5 |
| Lithium Silicate Densifier, A Penetrating Polyurethane, Semi-Rigid Polyurea Joint Filler, & Micro-aggregate traction additive mixed into the final guard coat (per DAFMAN 91-203, 7.1.6 Coefficient of Friction for Walking surfaces) |
| Q |
| 6 |
| At what grit level should the polishing process begin and end? |
| A |
| 6 |
| Micro-aggregate traction additive mixed into the final guard coat (400 – 800 grit [satin/honed]) |
| Q |
| 7 |
| Is there a floor plan available that can be provided? |
| A |
| 7 |
| See response to Q1 |
| Q |
| 8 |
| Because the existing flooring covers the concrete substrate, it is difficult to determine the exact extent of necessary crack, joint, and spalling repairs. [Can the Government] please provide a baseline square footage and/or linear footage allowance for these repairs? |
| A |
| 8 |
| Contractor estimates for all repairs shall be included with the bid as a separate line item to be approved by the government. |
Project HAYW 26-2010 Replace B102 & B110 Floor Q&A Final