LRIP-FRP Industry Day Questions and Responses v4.xlsx
XLSX spreadsheet 14 KB Posted
- Solicitation number
- W31P4Q-20-R-0015
About this file
This document contains questions and responses from an Industry Day held by the Army regarding the Integrated Fires and Mission Command (IFMC) Low Rate Initial Production/Full Rate Production (LRIP/FRP) requirement. The major supplies and services to be acquired under the IFMC LRIP/FRP requirement include production and integration of the IFMC major end items of Engagement Operations Centers, Engagement Center Trailer, IFMC Collaborative Environment, and Integrated Fire Control Network Relays. Engineering services for IFMC, contractor logistics support, travel and material, as well as foreign military sales support will also be required. The anticipated contract type is a full and open competition resulting in a single award indefinite delivery/indefinite quantity contract.
The Industry Day provided an overview of the IFMC program, hardware architecture, LRIP/FRP requirements, entrance criteria, draft acquisition strategy and evaluation criteria. Questions from industry were addressed in the document pertaining to technical, contractual and programmatic aspects of the requirement. Registration was required by February 21, 2020 to attend the briefing and optional hardware tour being held on March 3, 2020 at Redstone Arsenal in Huntsville, Alabama.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Entrance Criteria - LRIP-FRP Requirement.6.pdf | ||
| IAMD HW Industry Day updated 3-2-20v9.pptx | PPTX presentation | |
| Industry Day Attendees.XLSX | XLSX spreadsheet | |
| DRAFT LRIP-FRP SOW-Revision 1.docx | DOCX document | |
| DRAFT LRIP-FRP SOW.docx | DOCX document | |
| Industry Day Registration Form.XLSX | XLSX spreadsheet | |
| RSA Personnel Identification Badge Request Form.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| AIAMD LRIP/FRP Industry Day Question and Response Document | |||
| Seq | Category | Question | Response |
| 1 | SOW | Reference Paragraph 3 of the Draft SOW. What are the legacy systems major end items that are to be integrated? | Currently, the AIAMD architecture includes components from the Patriot Force and the Sentinel Radar. This includes Sentinel Radar, Patriot Radar, RIU, and M901/M902/M903 launchers. Equipment integrated in the future are pending Government approval and are beyond what is being assessed. |
| 2 | SOW | Reference Paragraph 5.1.b of the Draft SOW. Is there a list of end items that are to be interoperable with all other IBCS SOS? | Currently, the AIAMD architecture includes components from the Patriot Force and the Sentinel Radar. This includes Sentinel Radar, Patriot Radar, RIU, M901, M902 and M903 launchers. Equipment integrated in the future are pending Government approval and are beyond what is being assessed. |
| 3 | SOW | Reference Paragraph 5.1.a of the Draft SOW. Is there an attachment 1&2 to the Draft RFP? | Yes. Attachments will be provided to those vendors that meet the Entrance Criteria. |
| 4 | TDP | When will the IBCS TDP be published? | Upon release of the RFP to those vendors that meet the Entrance Criteria and consistent with the Contracting effort schedule. |
| 5 | GFP | Is there a list of GFE to be published? | Yes. GFE/GFP list will be released as part of the RFP to those vendors that meet the Entrance Criteria and consistent with the Contracting effort schedule. |
| 6 | SOW | Reference paragraph 5.8.8.3 of the Draft SOW. Where is the G-SIL located? | The current Government Simulation and integration Lab (G-SIL) is located on Redstone Arsenal at building 6272. |
| 7 | SOW | Reference paragraph 5.3 (ECT) of the Draft SOW. How has Tobyhanna AD been involved with the program to this point? When will Drawing ALH-215170 be made available? | Tobyhanna Army Depot created the current ECT design and provided the ECT TDP to the AIAMD program. As with the rest of the TDP, it will be released to vendors as a part of the RFP to those vendors that meet the Entrance Criteria and consistent with the Contracting effort schedule. |
| 8 | SOW | Reference paragraph 5.8.2.8 in the Draft SOW. What does “allocate subcontract work to the Depot(s) as appropriate mean? | The offeror shall describe their approach and identify work to be allocated as subcontract work to Army depots. The proposed approach must describe its analysis of the capabilities of the Army depots and describe and provide evidence of proven Public/Private Partnerships (PPP) experience with depots. Identify depot(s) with whom partnership agreement (s) exists; length of time partnership existed; current state of PPP (i.e. completed, in-progress, in dispute etc.); identify capacity in which depot was utilized (i.e. public sector facilities, equipment and employees to perform work for private sector); percentage of work performed by depot for each project/capability. |
| 9 | SOW | Will the SOW incorporate scope for NET, Logistics, IETM Support and Sparing? | Yes. |
| 10 | Tech Maturity | Does the USG seek for the 3 components to be redesigned to have the designed/manufactured for cut into manufacturing and fielded with first battalion fielding? | Yes, if cutting in the redesign into the manufacturing process sufficiently supports the required delivery dates and system performance. |
| 11 | Award | Is the final award single source? | Yes. This will be a Single Award IDIQ contract. |
| 12 | Technical | Is the assumption that the three tech changes (i.e., CASS-PDRS & JTT) already be integrated with the IBCS SW correct? Will it have already completed DT with the IBCS SW? | Yes. It is expected that SW will be previously tested and evaluated prior to integration into/onto the EOC. |
| 13 | Award | Are you looking for range pricing? | Yes. |
| 14 | Evaluation Criteria | How many past performances are required? | The quantity will be provided in the RFP. |
| 15 | SOW | Is any of the HW being fielded to the Institution Base? | Yes, Institutional Base HW will be identified and specified IAW a delivery order/task order. |
| 16 | Award | Do you have an RFP estimated release date? | Yes, as identified in the Industry Day Charts, the Draft RFP release is estimated for March/April 2020 and the Final RFP is estimated for June 2020. RFP timeline is subject to change. |
| 17 | Technical | Are the EOC's at the Battery and the Battalion the same? | Yes. |
| 18 | Technical | Are you controlling radios within the shelter from the ICE? | Yes, thru TOCNET Soft CAUs at the workstations. |
| 19 | Evaluation Criteria | Explain the banner on slide 23 "Access to IBCS Tech Library will be granted upon entrance criteria approval". | The Government will only provide the Technical Library to vendors that meet the Entrance Criteria. |
| 20 | Technical | Are the number of launchers that can interface RF wise to an individual Relay limited? | Yes, but the number is limited only by the total nodes within the Task Force at the SoS level IAW the AIAMD System Specification; not the individual launcher quantities per an idividual relay. |
| 21 | SOW | What is the total number of deliveries? | 454 is the Army Aquision Objective, but for this IDIQ award, proposed quantites are reflected in the Industry Day slides. |
| 22 | Technical | Will the SW go thru some testing prior to the delivery to ensure the 3 HW changes proposed in the evaluation will work with the SW version delivered by the Government? | Yes. It is expected that SW will be previously tested and evaluated prior to integration into/onto the EOC and Relay. |
| 23 | SOW | Can the sing-in sheet be distributed to the attendees? | Yes. It will be posted in Beta.sam with the Industry Day Charts. |
| 24 | Award | Will the TDP be frozen? | Yes, during the evaulation period the TDP will be frozen to accommodate a standard basis by which to evaluate vendors. Once the award is made, the TDP will no longer be frozen due to Engineering Change Proposals being anticipated. |
| 25 | Industry Day Charts | The posted brief file from last Tuesday’s Industry Day event and noticed that the original dates for “Contractor Deliver Entrance Criteria” and “Gov’t Approve Contractor Eligible” events are lined out with suspense dates TBD. Can you please confirm that the suspense dates for these events are changing from the original 3/10 & 3/17 respectively? | Yes. The dates have been changed to "to be determined" |