This document provides details of an industry day for a federal contract opportunity to acquire the Integrated Fires and Mission Command system. The Army Materiel Command Contracting Command Redstone Arsenal will host the industry day on March 3, 2020 in Huntsville, Alabama to provide information on requirements for a Low Rate Initial Production/Full Rate Production contract.
The major supplies and services to be acquired include production and integration of engagement operations centers, an engagement center trailer, a collaborative environment, and integrated fire control network relays. The contract will result from a full and open competition and be a single-award indefinite delivery/indefinite quantity contract. The industry day will include overviews of the integrated fires and mission command program, hardware architecture, and draft acquisition strategy and evaluation criteria. Questions may be submitted during or after the industry day. Companies must pre-register attendees by February 21 with the required forms to the identified points of contact.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| LRIP-FRP Industry Day Questions and Responses v4.xlsx | XLSX spreadsheet | |
| Entrance Criteria - LRIP-FRP Requirement.6.pdf | ||
| Industry Day Attendees.XLSX | XLSX spreadsheet | |
| DRAFT LRIP-FRP SOW-Revision 1.docx | DOCX document | |
| Industry Day Registration Form.XLSX | XLSX spreadsheet | |
| RSA Personnel Identification Badge Request Form.doc | DOC document | |
| DRAFT LRIP-FRP SOW.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROGRAM EXECUTIVE OFFICE
MISSILES AND SPACE
Army Integrated Air and Missile Defense (AIAMD) Hardware Office Industry Day
COL PHILIP G. ROTTENBORN
Project Manager IAMD Battle Command System (IBCS) 3 March 2020
Distribution A: Approved for public release; distribution is unlimited
Any Warfighter - Anywhere - All The Time
FOR OFFICIAL USE ONLY
3/4/2020
Agenda
| Welcome/Ground Rules/Disclaimer | ACC | 0830 - 0845 Introductions | COL Rottenborn | 0845 - 0900 |
| PEO M&S Overview | COL Rottenborn | 0900 - 0915 | ||
| IAMD Overview | COL Rottenborn | 0915 - 0925 | ||
| IBCS Hardware Overview | LTC Forrester | 0925 - 1000 |
End Items Government Furnished Property
| Break | All | 1000-1015 |
| Acquisition Approach | PEO MS & ACC | 1015 - 1025 |
RFP Timeline/Value Contracting Approach
| LRIP/FRP Overview | PEO MS & ACC | 1025 - 1050 |
| Entrance Criteria |
| Q/A Session | PEO MS | 1050 - 1125 |
| Closing Remarks | LTC Forrester | 1125 - 1130 |
| Lunch | All | 1130 - 1300 |
| Equipment Tour (Bldg 3328) | All | 1300 - 1600 |
Admin Notes Evacuation Plan
Only bottled water allowed in auditorium
Break room/vending machines
Restrooms
Questions submission
WiFi (Toftoy_Guest) enter e-mail, click accept
Silence Electronic Devices
Ground Rules
Program briefings are for information only
Recording and cell phone use is not permitted during this brief
This is an unclassified event; classified questions and answers will not be addressed
Submit all questions in writing on provided index cards.
Additional questions after close of Industry Day should be submitted to CPT Marjorie Masias at marjorie.j.masias.mil@mail.mil, NLT close of business 4 March 2020. Subject Line must read LRIP/FRP Industry Day Questions All questions must specify which criteria your question falls within; i.e., SOW, Schedule, Management, Past Performance, Small Business, etc.
All questions/answers will be documented and distributed to all participants via Beta.SAM.gov announcement NLT 16 March 2020.
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Disclaimer This exchange of information, in accordance with Federal Acquisition Regulation 15.201, is to improve the understanding of Government requirements and industry capabilities. This process allows an opportunity for an early exchange of information about the future acquisition and will promote early identification, resolution, and clarification of concerns regarding the program requirements.
The remarks today of Government officials involved in this procurement should not be considered a guarantee of the Government's course of action in proceeding with the program.
The information shared today reflects current Government intentions and is subject to change based on a variety of circumstances including internal and external comments.
The formal solicitation, when issued, is the only document that should be relied upon in determining the Governments requirements.
Distribution A: Approved for public release; distribution is unlimited PEO Missiles and Space Overview
Distribution A: Approved for public release; distribution is unlimited
PEO M&S PORTFOLIO
| Joint Attack Munition Systems | |
| (JAMS) | Cruise Missile |
Defense Systems
| (CMDS) | Counter - Rocket, Artillery, Mortar |
| (C-RAM) | Integrated Air & |
Missile Defense (IAMD) Lower Tier Project Office (LTPO) Precision Fires Rocket and Missile Systems (PFRMS) Close Combat Weapon Systems (CCWS) Missile Defense & Space Systems (MDSS)
JAVELIN
Tube-Launched, Optically-Tracked, Wireless- (TOW) Lethal Miniature Aerial Missile System(LMAMS) Precision Fires Manager
(PFM)
High Mobility Artillery Rocket System
(M142 HIMARS)
Multiple Launch Rocket System
(M270A1 MLRS)
AVIATION FIRES MANEUVER AIR DEFENSE
& SPACE
Army Tactical Missile Systems (ATACMS)
Guided Multiple Launch Rocket Systems
(GMLRS / U / AW)
PATRIOT
Ground Support Equipment PATRIOT Advanced Capability (PAC-3)
PAC-3
Missile Segment Enhancement (MSE)
Lower Tier Air Missile Defense Sensor
(LTAMDS)
Improved Bradley Acquisition Subsystem (IBAS) Containerized Weapon System (CWS)
Air and Missile Defense Planning & Control System (AMDPCS)
C-RAM Intercept
LPWS
AN/TPQ-50
AN/TPQ-53
AN/TPQ-36
Range Radar Replacement Program (RRRP)
AN/TPQ-37
RAM Warn Counter-Unmanned Aircraft Systems
(C-UAS)
IAMD Battle Command System (IBCS) Engagement Operations Center
(EOC)
Integrated Fire Control Network (IFCN) Relay A / B Plug & Fight Interface Kits
Forward Area Air Defense Command & Control (FAAD C2)
Integrated Collaborative Environment (ICE) Precision Strike Missile (PrSM)
Improved Target Acquisition System(ITAS)
Guided & Unguided
HELLFIRE
Launchers and Test Sets
Joint Air-to-Ground Missile (JAGM)
Stinger Avenger
NASAMS
IFPC Inc 2
IM-SHORAD
EMAM
ALPS
PRE-
DECISIONAL
Sentinel
UNCLASSIFIED
Joint Tactical Ground Station (JTAGS) THAAD & AN/TPY-2 Sustainment Management Office (T2SMO) Hypersonics Transition Team
Distribution A: Approved for public release; distribution is unlimited Briefly touch on this slide, but point out that the PMs will discuss their programs in greater detail.
| Integrated Fires / Rapid Capabilities | Search, Track, Acquire, | ||
| Radiate, Eliminate | Integrated Fires Mission | ||
| Command | Short & Intermediate Effectors for Layered Defense | Strategic & Operational Rockets & Missiles | Tactical Aviation & Ground Munitions |
Futures Integrations Director Integrated Fires
ALPS
Sentinel
AN/TPQ-50
AN/TPQ-53
AN/TPQ-36
Range Radar Replacement Program (RRRP)
AN/TPQ-37
Engagement Operations Center (EOC)/ Engagement Center Trailer (ECT) Integrated Fire Control Network (IFCN) Relay
Integrated Collaborative Environment (ICE) Legacy PATRIOT Ground Support Equipment
PATRIOT
Advanced Capability (PAC-3)
PAC-3
Missile Segment Enhancement
(MSE)
Lower Tier Air Missile Defense Sensor
(LTAMDS)
High Mobility Artillery Rocket System
(M142 HIMARS)
Multiple Launch Rocket System
(M270A1 MLRS)
Army Tactical Missile Systems (ATACMS)
Guided Multiple Launch Rocket Systems
(GMLRS / U / AW)
Precision Strike Missile (PrSM)
Air and Missile Defense Planning & Control System (AMDPCS)
Forward Area Air Defense Command & Control (FAAD C2) Avenger
NASAMS
IFPC Inc 2
PRE-
DECISIONAL
MLIDS
Counter-Unmanned Aircraft Systems
(C-UAS)
Long Range Hypersonic Weapon
(LRHW)
RAM Warn A / B Plug & Fight Interface Kits Joint Tactical Ground Station (JTAGS)
Stinger
EMAM
IM-SHORAD
PATRIOT
Launcher
ONS
Directed Requirements
JUONS
C-RAM Intercept
LPWS
KuRFS
Program Executive Office M&S Portfolio (Multi-Domain Operations Aligned)
Integrated Air and Missile Defense (IAMD)
Background
AROC approved CDD December 2006 JROC approved CDD December 2009 Program Restructure Approved in February 2012: removed MEADS, SLAMRAAM; incorporated Air Defense Airspace Management (ADAM) Cells, AAMDC & AMD BDE HQs, Indirect Fire Protection Capability (IFPC)/Avenger Battalions Revised acquisition strategy/schedule (revised APB) approved October 2014 AROC approved CPD August 2016 Army directed revision of schedule ATEC assessed IBCS performance at LUT #1 (May 2016) as “Not Effective, Not Suitable, Not Survivable” 2nd LUT required (2020), IOC moved to 2022 ACP update directed ISO of POM 20-24; proposed AAO utilized was 538 Revised CPD returned by ARCIC to HQDA (October 2018) for JROC staffing/approval No changes to KPPs/KSAs Cost & schedule updates Clarification to incremental approach to capability delivery Increment 2 CDD AROC November 2019, pending JROC Q4FY20 Increment 3 CDD draft in development for follow-on (FCOE and AMD CFT)
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
IBCS SW
Plug and Fight Interface Kits To develop, test, and deliver integrated fires capability to the Warfighter in order to provide a decisive battlefield advantage through weapon and sensor integration and a common mission command system across all domains.
Mission Provide common Integrated Fire Control (IFC) across all Army AMD echelons and integrate with Joint architecture Address TRADOC Warfighting Operational Gaps Single Integrated Air Picture (SIAP), IFC, Critical Asset Defense Provide flexibility to respond to evolving threat (sensor, interceptor, Electronic Warfare (EW)) What We Do Development of IBCS Components and Software Integration of Army AMD Component Acquisition Programs into the AIAMD Architecture What We Manage A highly efficient, agile and effective organization responsible for developing a mission command and fire control system that integrates sensors and weapons into a cohesive warfighting capability.
Vision Baseline Components
Engagement Center Trailer (ECT) Integrated Collaborative Environment (ICE) Army Integrated Air And Missile Defense (AIAMD) Engagement Operations Center (EOC) Integrated Fire Control Network (IFCN) V2 Relay
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Acquisition Schedule
LRIP buy supports IBCS fielding to Battalion #2
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
IBCS Hardware End Items and Components
Hardware end items, which were previously referred to as the Integrated Air and Missile Defense (IAMD) Battle Command System (IBCS) will now simply be referred to as Integrated Battle Command System (IBCS).
Distribution A: Approved for public release; distribution is unlimited Engagement Operation Center (EOC) S280 Based EOC M1148 Load Handling System (LHS)
Operator Workstations
Distribution A: Approved for public release; distribution is unlimited Rack 1 eMCSU with panel
GMR
Network Shelf
(BPU)
JBC-P Processor
DC PDU
AC UPS
Patch panel
CAU-V
KGV-72
Network Shelf
(IGRM, SCIM, KG-250)
JBC-P display/keyboard
MIDS
DC Power Supply (Wire Ducts not shown) Rack 2
RF-300M-V250
NetGuardian KVM Switch
DC PDU
AC UPS
DC Power Supply Patch panel KVM Console Maintenance Laptop
JTT-SR
IBCS EOC S-280 Rack Layout
Distribution A: Approved for public release; distribution is unlimited IBCS EOC S-280 Rack Layout
Rack 3
Printer
CASS
Media Converter (Black) DC PDU (Red)
AC UPS
DC Power Supply Patch panel
ADSI
Network Mgt Laptop Isolation Router (black) Network Router (Black) Alarm Amp AC PDU (Red) AC PDU (Black)
Network Switch (Red) Firewall (Red) Patch panel Network Router (red) Workstations Isolation Router (red) BS Servers
2X AC
PDU
2X AC
UPS
Fiber Patch Panel Media Converter (red) Cross-Domain Server VM Servers Stand-In Servers
Rack 4
Distribution A: Approved for public release; distribution is unlimited S280 EOC LRUs
| S280 Based EOC | |||
| Part Number | Description | Part Number | Description |
| WS-C3850-48P-E | CISCO 48 PORT SWITCH | 7608AD2012SNHR7 | SMART AC PDU |
| ASA5508-K9 | CISCO ASA 5508-X WITH FIREPOWER | PG3000-UPS-RSD | AC UNINTERRUPTIBLE POWER SUPPLY |
| SERVICES | ETI0003-1086 | SMART DC PDU | |
| ISR4351-AXV/K9 | CISCO 4351 ROUTER | E3E03A#B1H | HP OFFICEJET PRO 6230 PRINTER |
| ISR4321-AXV/K9 | CISCO 4321 ROUTER | 3U-IAMD-NN-NF-CC-ADSI | 3RU CPCI ADSI, CONFORMAL COATED |
| 1221-1-0W-KNG | 10/100TX TO 100FX MEDIA CONVERTER | 4090000-0501 | CASS RECEIVER |
| 1120-0-0W-KNG | 10/100TX TO 100FX MEDIA CONVERTER | ASY45857 | AMPLIFIER/CONTROL MODULE (2U) |
| 1020-1W-KNG | MEDIA CONVERTER CHASSIS | RF-300M-V250 | MULTIBAND RADIO, VEHICULAR MOUNT DUAL |
| CMS-00282 | RS111S13 SERVER | D-PK-NG16A-12012.00001 | NETGUARDIAN 16A, DUAL+24, 16 ANALOG |
| CMS-00597 | CRYSTAL RS114PS18 WORKSTATION | 90-2722-012-B | SLIMLINE LITE II LCD MNTR/KYBD |
| SERVER | B072-016-1 | 16-PORT NETCOMMANDER 1RU KVM SWITCH | |
| CMS-00500 (AC PWR) | RS112 SERVER | 02-2855479-3 | PANASONIC CF-31 LAPTOP |
Distribution A: Approved for public release; distribution is unlimited S280 EOC LRUs (continued)
| S280 Based EOC | |||
| Part Number | Description | Part Number | Description |
| 5459100-001 | TOCNET MCSU | 9800-07090-9007 | DISPLAY UNIT, BFT/FBCB2 |
| 5483500-001 | CAU-V | 9800-07010-9005 | KEYBOARD, BFT/FBCB2 |
| 813HN0500-0100 | GPS MESSAGE ROUTER (GMR) | 9800-13900-0000 & 9800-07060-9030 | DISK DRIVE UNIT & FBCB2 CPU |
| 5810-01-564-3364 | KGV-72 (CCI) | 5821-01-547-7436 | RADIO TERMINAL SET AN/USQ-140 |
| 1200-437 | SPECTRACOM SECURESYNC TIMING UNIT DC | WS-C3850-48P-E | CISCO 48 PORT SWITCH |
| PWR | ETA-PD8A | AC POWER DISTRIBUTION UNIT | |
| 1101000 | HAIPE ALTASEC KG-250X RUGGEDIZED IP | PG1500-UPS-V3 | 1U 1500VA Tactical UPS no DC input |
| ENCRYPTOR | CMS-00597 | CRYSTAL RS114PS18 WORKSTATION SERVER | |
| 3158010-104 | BASEBAND PROCESSING UNIT | NRTOC70WUX | 70" DISPLAY AND PROJECTOR SYSTEM |
| 11219-000 REV A1 | STATUS & COORDINATE INPUT MODULE |
Distribution A: Approved for public release; distribution is unlimited IBCS Interactive Collaborative Environment (ICE) HDT Airbeam Medium
Provides the hardware necessary to conduct Engagement Operations (EO) and Force Operations (FO) for long durations Provides Multifunctional Workstations for the Fire Control Element consisting of the Fire Control Officer, Weapons Control Officer, Surveillance Officer and Identification Officer Provides Workstations to support Force Operations of the S1, S2, S3 ,S4 and S6 Replaces makeshift Command Post 2 ½ Tons in the field
Engagement Center Trailer (ECT)
Provides Transport Space for all IBCS Collaborative Environment (ICE) equipment Contains 60 KW’s of Power for the entire Systems Contains an Environmental Control Unit for temperature control of the ICE
Distribution A: Approved for public release; distribution is unlimited Integrated Fire Control Network (IFCN) Relay
Noun: Integrated Fire Control Network (IFCN) Relay Nomenclature: Repeater Set, Radio (AN/TSQ-229) Prime Mover: M1078A1P2 Truck, Cargo Consists of the following hardware components:
Network Enclosure – Baseband Processing Unit (BPU) (radio) KG-250X Encryptor Parvus switch Status & Coordinate Input Module (SCIM) Initialization and GPS Receiver Module (IGRM) Highband RF Unit (HRFU) Antenna B-side processor (Stand-In Server in Transit Case) 5kW Gen Set, MEP1030 Skid Mtd Trailer Flat Bed M1061A1
Distribution A: Approved for public release; distribution is unlimited V2 Relay Components
| B-Kit Component | |
| Network Enclosure | |
| Highband Network Radio (HNR) | Baseband Processing Unit (BPU) |
| Timing Unit | |
| 18 port Switch | |
| Media Converter | |
| KG-250 | |
| Black Router | |
| B-side Processor | RS-112 Stand-In housed in Operational Transit Case |
| Platform Hardware | |
| Trailer | M1061A1 5T Trailer (TACOM Managed) |
| Generator | 5kW TQG (MEP-1030) (PM E2S2 Managed) |
| Battery / Charger | |
| Mast Payload adapter | |
| Guy Reel storage | |
| TFOCA II ( 1km) | |
| Power Regeneration Kit | |
| GPS Antenna |
Distribution A: Approved for public release; distribution is unlimited Government Furnished Property
Government Furnished Software IBCS Application OIV (Firmware) Integrated Fire Control Network (IFCN) Configuration Files
Government Furnished Hardware Routers Generators Trailers Trucks Improved Environmental Control Unit (IECU) Comms Equipment (JBC-P, JTT, MIDS, etc.)
KG-250X
B-Side Processor Access to IBCS Technical Library Will Be Granted Upon Entrance Criteria Approval
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Break
Acquisition/Contracting Approach
Distribution A: Approved for public release; distribution is unlimited Projected RFP Timeline
| Industry Day (ID) | 03 March 2020 | |||
| Contractor Deliver Entrance Criteria | 10 March 2020 | |||
| Gov’t Approve Contractor Eligible | 17 March 2020 | |||
| Gov’t Provides Technical Library | EOM March | |||
| Issue Draft RFP | March/April | |||
| Contractor Response to Draft | EOM April | |||
| Final RFP | June | |||
| Proposals Due | August |
Projected Award 3QFY21 RFP Timeline is Subject to Change
TBD
TBD
Distribution A: Approved for public release; distribution is unlimited What We Are Buying & Potential Quantities
| Period 1 | Period 2 | Period 3 | Period 4 | Period 5 | Total | |
| 30Jul2021 – 30Jul2022 | 30Jul2022 – 30Jul2023 | 30Jul2023 – 30Jul2024 | 30Jul2024 – 30Jul2025 | 30Jul2025 – 30Jul2026 | ||
| EOC/ECT | 13 | 31 | 40 | 65 | 0 | 149 |
| ICE | 13 | 16 | 28 | 42 | 0 | 99 |
| IFCN Relay | 27 | 27 | 35 | 52 | 0 | 141 |
The quantities above Do Not denote the minimum buy and Do Not include FMS, Engineering Services or Logistic Services Maximum Potential Quantities What We Are Buying A. System HW and System HW Responsibility B. Engineering for Major Mods C. Logistics Services and Support D. Engineering Services E. System Synchronization F. US & FMS Configurations
Distribution A: Approved for public release; distribution is unlimited Contracting Approach Proposed Contract Type: Single Award Indefinite Delivery/Indefinite Quantity (IDIQ), Firm Fixed Price (FFP), Fixed Price Level of Effort (FPLOE), Fixed Price Incentive Fee (FPIF), Cost Reimbursable (CR) using FAR Part 15 Procedures
NAICS Code: 336414 – Guided Missile and Space Vehicle Manufacturing
IDIQ Ceiling: Estimated at $1.8B
Minimum Guarantee: Task Order 0001 estimated at $TBD
Period of Performance: Four Year Ordering Period (June 2021-June 2025); One Year Final Fielding (June 2025-June 2026)
Source Selection Technique: Best Value Trade Off Procedures
Contracting Approach is subject to change
Distribution A: Approved for public release; distribution is unlimited
Hardware LRIP/FRP Entrance & Evaluation Criteria
Distribution A: Approved for public release; distribution is unlimited Entrance Criteria
In order to receive the RFP attachments and SOW attachments for the LRIP/FRP requirement, you are required to have a Secret Integration and Test Facility.
In order to confirm that you have a Secret Integration and Test Facility, you must provide the CAGE code and location of the facility.
Instructions for providing Entrance Criteria will be provided in Beta.sam.gov.
Any attachments related to the LRIP/FRP RFP and SOW will only be provided to those potential bidders who respond with the intent to participate, and have confirmed that they have a Secret Integration and Test Facility.
Entrance Criteria is Subject to Change
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Evaluation Criteria
THIS EVALUATION CRITERIA IS FINAL DRAFT AND IS SUBJECT TO CHANGE
Distribution A: Approved for public release; distribution is unlimited Go/No Go Criteria
Acceptable/Unacceptable
Experience To be assessed as acceptable, the offeror must provide evidence of previous experience in the last 3-5 years:
| Integrating mechanical and electrical components over a type 1 secure network, both wireless and wireline, in a real time safety critical environment; |
| And |
| System engineering, design, qualification and implementation of design changes during manufacturing for major capability upgrades in Command and Control Systems. |
Proposals assessed as unacceptable Experience
ARE NOT ELIGIBLE FOR AWARD
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Evaluation Criteria
ADJECTIVAL RATINGS
Factor 1: Schedule Sub-factor 1: Technical Maturity Sub-factor 2: Production Maturity
Factor 2: Management Sub-factor 1: System Synchronization and Metrics Sub-factor 2: Depot Subcontractor Management
Factor 3: Past Performance Factor 4: Small Business Factor 5: Cost/Price (Evaluated not Rated)
THIS EVALUATION CRITERIA IS FINAL DRAFT AND IS SUBJECT TO CHANGE
| TECHNICAL RATINGS | |||||
| COLOR | Blue | Purple | Green | Yellow | Red |
| RATING | Outstanding | Good | Acceptable | Marginal | Unacceptable |
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Evaluation Criteria
RELATIVE IMPORTANCE
The Schedule Factor is significantly more important than the Management Factor.
The Management Factor is significantly more important than the Past Performance Factor.
The Past Performance Factor is more important than the Small Business Factor.
The Small Business Factor is the least important factor.
Within the Schedule Factor, the Technical Maturity Sub-factor is more important than the Production Maturity Sub-factor.
Within the Management Factor, the System Synchronization and Metrics Sub-factor is significantly more important as the Depot Subcontracting Sub-factor.
All non-cost factors combined are significantly more important than the Cost/Price Factor.
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Evaluation Criteria
Factor 1: Schedule Sub-factor 1: Technical Maturity The technical maturity will be evaluated using three tasks.
1: Network Enclosure Assembly Design Approach 2: CASS to PDRS Design Approach 3: JTT SR to JTT IBS Design Approach
Sub-factor 2: Production Maturity
Factor 2: Management Sub-factor 1: System Synchronization and Metrics Sub-factor 2: Depot Subcontractor Management
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Factor 1: Schedule
Significantly more important than the Management Factor
Distribution A: Approved for public release; distribution is unlimited Sub-factor 1: Technical Maturity More important than Production Maturity Sub-factor
The technical maturity will be evaluated using three tasks.
1: Network Enclosure Assembly Design Approach The offeror must demonstrate their capability to provide a network enclosure assembly to replace the current network enclosure assembly. The proposed network enclosure assembly must meet all current network enclosure assembly requirements, with exceptions noted with rationale. The proposed network enclosure assembly must include either test data and/or analysis demonstrating how it meets size, weight, power, and environmental requirements as well as how it can support a second IFCS and still meet size, weight, power, and environmental requirements, with exceptions noted with rationale.
2: CASS to PDRS Design Approach The offeror must demonstrate their capability to propose design technical changes to the system for replacing the current obsolete Cooperative Aviation Surveillance System (CASS) with the Passive Detection and Reporting System (PDRS). The proposed technical design changes are limited to form and fit only.
3: JTT SR to JTT IBS Design Approach The offeror must demonstrate their capability to propose design technical changes to the system for replacing the current obsolete Joint Tactical Terminal Senior (JTT SR) with the JTT Integrated Broadcast System (JTT IBS).
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Sub-factor 2: Production Maturity Less important than Technical Maturity Sub-factor
Production Maturity includes the production line, production facilities, production processes, vendor base, workforce, and the ability to sell-off integrated HW and SW classified systems.
The offeror shall provide evidence that the current or proposed production line, production facility, production processes, vendor base, workforce, and classified sell-off are able to support, produce, and deliver IAW the quantity and delivery schedule set forth in the RFP.
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Factor 2: Management
Significantly more important than the Past Performance Factor
Distribution A: Approved for public release; distribution is unlimited Sub-factor 1: System Synchronization and Metrics Significantly more important than the Depot Subcontractor Sub-factor
System Synchronization is the management of IBCS hardware and software integration to ensure consistency in product acceptance, support of fielded systems, implementing new capability growth and support of Government simulation labs. The contractor shall provide an approach for leading system synchronization efforts for IBCS. As a minimum, the approach shall address, membership, frequency of meetings, charter, roles, responsibilities, and authorities, methodology and metrics for tracking hardware and software configuration for IBCS.
All presentation of Metrics will be shown as trends with planned versus actual data points. All metrics will be updated at a minimum, monthly. All metrics required in the SOW shall also be included in the offerors approach. The approach shall have metrics for both production and new development efforts. The approach shall contain sample presentations of all metrics. The approach shall also contain a matrix showing the metric, the source of all data, the owner of the metric, frequency and level of review by the offeror.
Distribution A: Approved for public release; distribution is unlimited
The offeror shall describe their approach and identify work to be allocated as subcontract work to Army depots.
The proposed approach must describe its analysis of the capabilities of the Army depots and describe and provide evidence of proven Public/Private Partnerships (PPP) experience with depots.
Identify depot(s) with whom partnership agreement(s) exists; length of time partnership existed; current state of PPP (i.e. completed, in-progress, in dispute etc.); identify capacity in which depot was utilized (i.e. public sector facilities, equipment and employees to perform work for private sector); percentage of work performed by depot for each project/capability.
Sub-factor 2: Depot Subcontractor Management Less important than the System Synchronization and Metrics Sub-factor
Distribution A: Approved for public release; distribution is unlimited
3/4/2020
Factor 3: Past Performance
Distribution A: Approved for public release; distribution is unlimited Past Performance More important than the Small Business Factor Offerors will be evaluated on their record of Recency, Relevancy, and Quality of their federal contracts that are similar to the requirements specified in the solicitation in terms of scope, magnitude (dollar value), and complexity as this solicitation in past performance in the past 3-5 years.
Distribution A: Approved for public release; distribution is unlimited Factor 4: Small Business
Distribution A: Approved for public release; distribution is unlimited Small Business Less important than the Past Performance Factor Small Business Participation and Commitment Proposal
All Offerors (both large and small businesses) will be required to submit a Small Business Participation and Commitment Proposal that will be evaluated on the level of proposed commitment to utilize U.S. small businesses in the performance of acquisition (as small business prime Offerors or small business subcontractors) based on percentage of total contract value (price) and not based on total subcontracting value. The Small Business Factor will be rated using the following definitions.
| TABLE 5. Small Business Participation Factor Rating Definitions | ||
| Color | Rating | Description |
| Blue | Outstanding | Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses. Risk of unsuccessful performance is low. Proposed target goals meet or exceed 20%. |
| Purple | Good | Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low. Proposed target goals are between 10% and 19% |
| Green | Acceptable | Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate. Proposed target goals are between 5% and 9%. |
| Yellow | Marginal | Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high. Proposed target goals are between 1% and 4%. |
Distribution A: Approved for public release; distribution is unlimited Small Business Subcontracting Plan All large business offerors must also submit a Small Business Subcontracting Plan meeting the requirements of FAR 52.219-9 and DFARS 252.219-7003 (DFARS 252.219-7004 for Comprehensive Subcontracting Plans).
Large Businesses must submit an acceptable Subcontracting Plan to be eligible for award.
Distribution A: Approved for public release; distribution is unlimited Factor 5: Cost/Price (Evaluated not Rated)
Questions?
Distribution A: Approved for public release; distribution is unlimited
Closing Remarks
Distribution A: Approved for public release; distribution is unlimited
3/4/2020 image10.png image11.png image12.png image14.png image15.png image16.jpeg image28.jpeg image29.png image30.png image31.png image32.png image33.png image34.png image35.png image36.png image37.png image38.png image39.png image40.png image41.png image42.png image43.jpeg image44.jpeg image45.jpeg image46.png image47.png image21.jpeg image48.png image49.png image50.emf image51.jpeg image52.jpeg image53.png image54.png image55.png image56.png image22.png image57.png image58.png image59.jpeg image60.png image61.png image62.png image63.png image64.png image65.png image66.png image23.png image67.png image68.png image69.png image70.png image71.jpeg image72.png image73.png image74.jpeg image75.png image76.png image24.png image77.png image78.jpeg image25.png image26.jpeg image27.jpeg image79.png image80.png image81.png image82.jpeg image83.png image84.jpeg image85.jpeg image86.png image87.png image88.png image89.png image90.jpeg image91.emf image92.png image93.png image94.png image95.emf image96.jpeg image97.png image98.png image99.png image100.png image101.png image102.png image103.png image104.png image105.jpg image106.png image107.png image1.png image6.jpeg image4.png image5.png image8.png image9.png image2.jpeg image3.png image13.png
File details come from the government source that posted it. Updated .