PERFORMANCE WORK STATEMENT

View the file

Other files for this federal contract opportunity

Other files attached to BROADBAND LAN, newest first.
File Type Posted
Solicitation_Question-Answer_13September2018.pdf PDF
Attachment_3-Submission_Instructions__Evaluation_Criteria.pdf PDF
Attachment_1_-_Pricing_Schedule.xlsx XLSX spreadsheet
Solicitation_Doc.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

Network Cable Installations and Maintenance Services for the Tobyhanna Army Depot

(TYAD) Broadband Local Area Network (BBLAN)

1. Scope. This Performance Work Statement (PWS) defines the requirements to maintain, repair, engineer, furnish, install, extend, cutover, test and perform all work necessary for the Broadband Dual Coaxial Cable Local Area Network (LAN), located at Tobyhanna Army Depot (TYAD), Tobyhanna Pa. 18466, to support multimedia functions, (e.g., two-way data communications, audio visual media) so that the entire LAN may operate as one system while conforming to the specifications herein.

The BBLAN is comprised of, but not limited to, the following types of components: Coax Cable (inside and out) approximately 31 miles, Head-End equipment, Amplifiers, Line Extenders, Power Supplies including backup, Remote Pilot Generators, Equalizers, Node Taps, Filters, Drops, Splitters, Couplers, Connectors, Pole Line Equipment and miscellaneous components.

All work performed by the contractor shall provide minimal disruption to Government owned systems and personnel. The contractor shall provide the required services at the agreed upon pricing IAW Attachment 1- Pricing Table. Installation shall be directed by the COR or his designee. Contractor shall notify the COR upon completion of the install.

2. Government Provided Material, Equipment and Accommodations

2.1 Government Furnished Material (GFM) and Government Furnished equipment

(GFE)

2.2 The Government shall provide GFM & GFE as all Category 5E, 6, and 6 LAN cable, connectors, installation hardware, ladders, lift equipment, and any other miscellaneous installation related items.

2.2.1 Except for the GFM/GFE identified above. the Contractor shall provide all plant, labor, equipment, parts, vehicles, tools, materials, supervision, and services necessary to perform all operations in connection with inspection, recertification, connections of, removal, repair, maintenance (remedial and preventive), part replacements, and tests to ensure proper operation of the LAN located at TYAD as one system.

2.3 SITE PROVISIONS FURNISHED BY THE GOVERNMENT. The Government shall provide to the Contractor as applicable to this contract: desk, chair and storage space for tools, test equipment, and repair parts.

2.4 SYSTEM EQUIPMENT. The Broadband Local Area Network (BBLAN) dual coax cable system located on Tobyhanna Army Depot. It consists of the entire cable system, all of its components. The LAN is comprised of, but not limited to, the following types of components: Coax Cable (inside and out) approximately 31 miles, C-COR model ASM- 2909 Head-End Equipment, Amplifiers, Line Extenders, Power Supplies including backup, Remote Pilot Generators, Equalizers, Node Taps, Filters, Drops, Splitters, Couplers, Connectors, Pole Line Equipment, and Miscellaneous minor components.

3. General Requirements.

3.1 Place of performance. All within the scope of this effort are located on the Tobyhanna Army Depot. The Tobyhanna Army Depot (TYAD) is located in the Pocono Northeast region of Pennsylvania.

3.2 Period of performance. The period of performance shall be for a base period of one

(1) year from date of award with the option to extend the term of the contract for two (2) additional years.

3.3 The contractor shall install LAN cabling, in accordance with (IAW) industry standards, i.e. ANSI/TIA-568.0-D, Generic Telecommunications Cabling for Customer Premises, 2015, ANSI/TIA-568.1-D, Commercial Building Telecommunications Infrastructure Standard, 2015,ANSI/TIA-568-C.2, Balanced Twisted-Pair Telecommunication Cabling and Components Standard, published 2009, in buildings as required by the Government. The Contractor shall use GFE pull box cable, mark cables using 3M cable mark kit and pull cable above 15 foot suspended ceilings to areas designated by drawings that shall be provided. All cable will be suspended using a bridle ring attached to a beam clamp or best industry standards approved by the COR.

Cable will be pulled inside walls or placed in a wire mold that will be attached to the walls. The Contractor shall: terminate all cables using GFE connectors or GFE patch panels; test all cables using a GFE cable scanner; check for correct wiring, opens and shorts in the cables; mark all LAN cable drops using GFE label maker and ensure that remote end cable number matches the patch panel cable number; and clean up at the end of each day. The Contractor shall perform drop installations within one (1) working day from the time of request by the Government unless otherwise specified by the COR.

The Contractor shall follow all Depot security, safety and fire standards.

3.4 Contractor Personnel.

3.4.1 General. The contractor shall provide trained and experienced service technicians with recent and relevant experience in the installation, termination and testing of Category 5E, 6 and 6E Ethernet drops at TYAD and to provide quality services IAW manufacturers’ specifications and industry standards. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

Approval must be obtained from the COR before commencing any work.

3.4.2 Service Contract Labor Standards. FAR 37.107 and 41 USC Chapter 67, Service Contract Labor Standards, provides for minimum wages and fringe benefits as well as other conditions of work under certain types of service contracts. Service Contract Labor Standards are applicable to this acquisition. Prevailing wage rates may be referenced at the following link: https://www.wdol.gov/sca.aspx.

The Wage Determination currently in effect as of January 10, 2018 is WD 15-5798 (Rev.-5) posted on January 16, 2018.

3.4.3 Specific Qualifications.

The Contractor shall be experienced in the repair of all the BB LAN equipment installed on TYAD LAN or its equivalent and on the operation and maintenance of Dual Broadband Coaxial Cable Networks. The Contractor shall have demonstrated experience as a technician or instructor on like equipment or in a similar field in electronics or communications. This experience must have included the use of schematic diagrams, a variety of teste equipment, troubleshooting, installing, maintaining, repairing, or instructing on coaxial cable plants or similar functions.

Experience shall be reflected on the contractor’s resume.

3.4.4 Security clearance/access requirements.

Prior to the commencement of performance under the contract and within seven (7) workdays of contract award, the Contractor shall submit to the Chief, Security Division, TYAD, a roster of all Contractor personnel, inclusive of on-site supervisory or managerial personnel and sub-contractor personnel, that the Contractor anticipates will be performing work on-site. The roster shall indicate which individuals are U.S. citizens and which are resident aliens (immigrants). Due to limited availability of Government personnel, Contractors shall not be permitted to employ non-resident/non-immigrant aliens as part of the Contractor’s on-site workforce. All non-resident/non-immigrant aliens must have approval prior to being permitted access to TYAD. Such approval must be obtained by requesting access through the following: apply at the alien-resident’s embassy; proceed to the U.S. Embassy; proceed to the Department of the Army; proceed to Army Materiel Command; proceed to U.S. Communications- Electronics Command (CECOM); proceed to TYAD. All non-resident/non-immigrant aliens granted access to TYAD or assigned duty location are required to be escorted by Government personnel. One Government escort can accommodate a maximum of two non-resident/non-immigrant aliens. Due to limited availability of Government personnel, visitors requiring escort may not be permitted access, or access may be limited to a certain time and duration. The following documentation shall accompany the roster for each individual named on the roster as a resident alien (immigrant): a) a copy of a verifiable form of identification, such as a driver’s license or a passport; and b) a copy of a valid Department of Justice Immigration and Naturalization Service Form I-551, Alien Registration Receipt Card (“Green Card”). Contractors who fail to identify any and all resident aliens (immigrants) who will be used for onsite performance and who will seek access to TYAD or assigned duty location as a worker for or through the Contractor, https://www.wdol.gov/sca.aspx inclusive of managerial and subcontractor personnel, may be subject to civil and criminal penalties and sanctions as well as contract remedies.

3.4.5 Within five (5) workdays of the submission of the roster and documentation, and ELTY Form 648-C, the Government will have completed the security check and the Contractor will be notified whether all listed personnel will be permitted to work on-site.

However, actual access to TYAD by the roster personnel will remain contingent upon such resident alien (immigrant) individuals presenting two (2) forms of identification as they process into the Depot through the Security building: a valid Form I-551, Alien Registration Receipt Card (“Green Card”) in addition to at least one other verifiable form of identification.

3.4.6 The roster which the Contractor submits is amendable. However, up to five (5) workdays will be required to perform a security check on any personnel added to the roster. The Contractor is urged to include contingency or “backup” personnel in the original roster in order to avoid delays due to roster amendment. TYAD will perform security screening of all Contractor employees, inclusive of subcontractor personnel that the Contractor anticipates will be performing work on-site, and for any other representative/employee before a TYAD badge or TYAD site badge is issued. Any Contractor employee(s) already on site who have not been screened or employees who are on site in transition to this contract will be subject to security screening as scheduled by TYAD. This security screening does not relieve the Contractor of the responsibility to conduct thorough pre-employment background checks and drug screening if required.

Applicable forms will be provided to the Contractor for completion by the Contractor and Contract worker. Contractor workers will not be granted access to the worksite until security screening is completed and access is approved. Any workers on site who fail screening will not be permitted further access to TYAD.

3.4.7 Contractors whose personnel are denied entry to TYAD or assigned duty location due to the security requirements are not relieved of their obligation to provide the required contract performance and must do so at no additional cost to the Government.

Any Contractor failing to perform or that fails to perform in a timely manner under such circumstances may be terminated for default or be subject to other contractual remedies as appropriate.

3.4.8 If work requirements dictate that contractor personnel require access to secured locations/buildings, it is the responsibility of the contractor to coordinate with the COR to obtain the escort(s) required and any associated elevated security clearances.

3.5 Hours of Operation. All contractor services shall be performed between the hours of 7:00 AM and 4:30 PM Monday through Friday, excluding federal holidays. The Tobyhanna Army Depot operates on an alternate work schedule allowing for a regular day off (RDO) every other Friday. A depot operating schedule is provided that identifies the hours of operation and hard closure days.

3.6 Management and Supervision of Contractor Personnel. The contractor shall provide all management, quality control, labor, supervision, parts, materials, tools, equipment, supplies, transportation and other services necessary for the inspection, testing, maintenance and repair of the BBLAN at TYAD. The contractor shall, upon COR approval, provide repairs to any malfunctioning portion of the BBLAN. Following repair, the contractor shall ensure the BBLAN is fully operational. The contractor shall, without additional expense to the Government, be responsible for obtaining any and all necessary licenses and permits and shall comply with any applicable safety and health requirements by Federal, State and Local laws, codes or ordinances in connection with performance of this contract.

3.7 Other Considerations.

3.7.1 Environmental. Protecting the environment is a priority at the Tobyhanna Army Depot. In order to ensure that this is accomplished, policies and procedures are in place to cover spills, air quality, hazardous materials, and other environmental areas of concern. Contractors working at the Tobyhanna Army Depot need to be familiar with and comply with the established policies and procedures. Contractors are directed to reference Appendix 1 – Environmental Concerns for Contractors for local guidance.

Specific questions, concerns, and clarifications are to be directed to the COR.

3.7.2 Safety. (Reference Appendix 2 - Contractor Safety Standards for TYAD)

3.7.3 Voluntary Protection Program. TYAD is an Occupational Safety and Health Administration (OSHA) Voluntary Protection Program (VPP) site. Accordingly, TYAD expects and requires full Contractor compliance with all applicable safety regulations and standards. The Contractor is responsible for maintaining, monitoring, and enforcing full compliance.

3.7.4 OSHA Rules and Regulations. Contractors must comply with all Department of Labor and OSHA Rules and Regulations, 29 Code of Federal Regulations (CFRs) 1910 (General Industries), and/or 1926 (Construction), and all applicable sections of the National Fire Protection Association (NFPA) Codes.

3.7.5 OSHA Fall Protection. In regard to OSHA Fall Protection requirements, the following shall be noted. Personnel performing any type of construction (29 CFR 1926) or general industrial work on elevated surfaces or platforms, over 6 feet, must adhere strictly to Occupational Safety and Health Standards, specifically 29 CFRs, Part 1926, Sections 500, 501 and 502.

3.7.6 Standards for Electrical Safety. Particular attention is directed to NFPA 70E, Standard for Electrical Safety Requirements for Employee Workplaces. Contractor shall fully comply with all sections of this standard, including but not limited to; PART I, Chapter 2 - Ground Fault Protection for Personnel on Construction Sites, PART I, Chapter 3-7.1 - Use of Flexible Cords and Cables, PART II, Chapter 2-3 - Working On or Near Electrical Conductors or Circuit Parts, PART II, Chapter 5 - Lockout/Tagout Practices and Devices.

3.7.7 Safety Video. All Contractors are required to view a Government Furnished Safety Video prior to any work performed on the Depot.

3.7.8 Personal Protective Equipment

All standard Personal Protective Equipment (PPE) required shall be provided by the Contractor at Contractors expense. Standard PPE includes but is not limited to protective eyewear, hearing protection, and safety shoes. Notwithstanding, the Contractor is responsible for determining the adequacy of the identified PPE and for determining the need for any additional PPE.

3.7.9 Accident Reporting. All accidents resulting in injury of any type shall be immediately reported to the COR, Contracting Administrator, and the Contracting Officer.

3.8 Pre-Work Conference. Prior to the initiation of any work under this contract, the contractor shall meet with the Contracting Officer Representative (COR) at a time, date, and location established by the COR for the purpose of coordinating the initiation of work.

4. Performance Requirements.

4.1 LAN DROPS.

4.1.1 ETHERNET DROPS. (KTR shall propose a FFP for this type of drop IAW Attachment 1 – Pricing Table). The contractor shall provide a team of journeyman LAN cable installers to install and terminate category 5E, 6 and 6E LAN twisted pair cable drops as requested by the Contracting Officer’s Representative (COR). The Contractor shall perform drop installations within one (1) working day from the time of request by the Government unless otherwise specified by the COR.

4.1.2 HORIZONTAL INSTALL. (KTR shall propose a FFP for this type of drop IAW Attachment 1- Pricing Table) Upon request by the COR, the contractor shall provide a team of journeyman LAN cable installers to install and terminate Government supplied 48 pair fiber optic or up to 200 pair copper telephone continuous cable either via Government conduit or ariel plant. Fiber terminations shall be accomplished via fusion IAW National Electrical Code (NEC). Installation pricing will be per 50 feet for both fiber optic and copper.

4.1.3 COAXIAL LAN DROPS. (KTR shall propose a FFP for this type of drop IAW Attachment 1- Pricing Table) Upon request by the COR, the contractor shall provide all technical service, hardware, plant, labor, parts and material required to physically, electrically and logically add to the existing Broad Band Cable Plant (BBCP) located at TYAD, up to 100 ea. 100 foot Dual RG 59, or an accepted electrical equivalent, from node taps to a specific demark location as designated by the Government. Work as described above shall be accomplished within two (2) working days of the Government’s request.

The contractor shall perform IAW the terms and conditions of the most current National Electrical Code and UFC 1-200-01 DoD Building Code. Following drop installation, the contractor shall ensure the drop provides adequate signal strength IAW the specifications of TIA/EIA-568-B.1. The contractor shall coordinate with the Contracting Officer’s Representative (COR) to ensure acceptable routing and termination points of cable runs throughout the period of performance.

4.2. REMEDIAL MAINTENANCE (RM):.

(T&M CLIN0002)

4.2.1 The Contractor shall provide RM for the entire LAN at TYAD. Calls for RM will be initiated by the COR. Before performing repairs, a quote must be provided by the Contractor and approval must be obtained from the COR. RM is performed to diagnose and correct LAN system or component malfunctions. It shall be accomplished when equipment failure occurs or when requested by the COR. The BBLAN shall be restored to operational status within eighteen (18) business hours after COR approval of quote or authorization is received.

4.2.2 Defective Component Replacement. In order to maintain the LAN system operational integrity the Contractor shall replace the component(s) immediately or the Contractor may replace malfunctioning equipment with functionally equivalent equipment in good operational condition until the original can be repaired or replaced. If the original part is repaired, it must be returned in a timely manner. In instances where it is necessary to remove an item from TYAD for repair, the Contractor shall coordinate with the COR and sign the component out to ensure accountability. The contractor is responsible for the item from the time it leaves the depot until it is returned in good operational condition. Only new standard parts and components, meeting or exceeding the original manufacturer's specifications (OEM), shall be used in repairs.

4.2.3 Telephonic Response and Assistance. The Contractor shall provide the Government a supervised telephone number during normal business hours (0700 – 1630) for malfunction reporting, discussion, and assistance. A supervised phone number is that which can be reached by a Government representative within thirty (30) minutes of the first attempt with a maximum of three (3) attempts made within the 30-minute period. If, at any time, this supervised telephone number is answered by an answering service or other non-technical personnel, the Contractor, or his designated technical personnel, shall return the call to the Government representative within the thirty (30) minute period from receipt of the call by the Contractor's answering service or non-technical personnel.

The Government representative shall describe the trouble, the symptoms and type of failure. After discussion with the Contractor's representative, the Government's representative will determine whether the problem requires a response, provide Technical Assistance to remedy the issue remotely through the COR or provide a quote to remedy it physically on-site through Contractor personnel.

4.3 Unpriced but in Scope Requirements

The following services are considered within scope of this requirement and, although not immediately anticipated, they might be deemed by the COR to be necessary during performance of this contract. If deemed necessary during performance, the Government will request a firm-fixed price quote for these services and negotiate accordingly. The Contractor shall not proceed with performance on the following unpriced, but within scope requirements unless authorized by the Contracting Officer through a bi-lateral modification to the contract.

4.3.1 LAN EXTENSIONS. Following award, and throughout the life of this contract, at the option of the Government, the contractor shall provide all that is necessary to increase a minimal specified number of node taps and/or provide new and/or additional LAN service. Charges or credits for additions, deletions and maintenance of equipment shall be negotiated prior to any change, and by contract modification approved by the Contracting Officer (KO).

4.3.2 MOVES. The Government shall have the option, by giving 30 days notice, to have the contractor make moves or relocations of the LAN cable or LAN components IAW specifications of the LAN. Charges for moves or relocations shall be negotiated prior to any change and by contract modification approved by the KO.

4.3.3 CERTIFICATION REPORT: If required by the Government, the Contractor shall provide (2) copies of the Certification Report in an organized legible format that can be fully reproduced by the Government. If a dot matrix printer is used to produce these documents, it shall be done in an enhanced print mode. Documents that can't be reproduced legibly by standard office copying equipment will be rejected. The contractor shall submit the formal report within thirty (30) days of completing the Recertification. The Contractor shall provide two (2) copies of rough draft Certification Report within 10 days of completion of the Recertification.

THE RECERTIFICATION REPORT SHALL CONTAIN, AS A MINIMUM, THE

FOLLOWING:

(1) Inspection date.

(2) Inspectors name.

(3) List of test equipment to be used for the certification and the calibration due date for each piece.

(4) Identify the type of tests, test equipment, test location, and expected readings for each test.

(5) Describe the procedure used for each test performed.

(6) Identify the name and number of the Node to be tested with its location and the reading taken there. When a reading is taken from more than one location, identify each Node the reading is taken from.

(7) Identify the failures or problems encountered and the corrective actions taken.

(8) Identify System Level criteria and Test Frequencies.

(9) Identify Return Trunk test levels and Pilot Generator levels.

(10) Custom site conditions.

NOTE: The use of vendors standard report format is acceptable provided it contains all the information identified in this paragraph.

4.3.4 PREVENTIVE MAINTENANCE (PM): If required by the Government, the Contractor shall provide PM for the LAN. PM is performed to avoid equipment malfunction and to insure the LAN is functioning within design specification and in good operating order. Any malfunctions or discrepancies encountered during PM shall be corrected by the Contractor immediately IAW the provisions of REMEDIAL MAINTENANCE. The Contractor shall provide and use a check-list identifying all the LAN Equipment tested and all the tests performed.

If required by the Government, the Contractor shall perform PM ANNUALLY. The initial PM shall be performed in conjunction with Recertification

4.3.5 PM TESTS: The Contractor shall perform all PM testing. PM tests shall be IAW NCTA practices for measurements on cable TV systems. The Contractor shall perform the following tests as a minimum. All test results shall conform to the specifications/standards of the LAN and this paragraph. All tests shall be conducted semiannually unless otherwise specified. Annual Tests shall be performed in conjunction with Recertification.

TESTING SHALL CONSIST OF, BUT NOT BE LIMITED TO, THE FOLLOWING:

SLOPE AND GAIN. Trunk Amplifiers and Line Extenders shall be tested to insure that the slope and gain are adjusted to meet specified requirements. This shall also include automatic gain control (AGC) and automatic slope control (ASC).

RADIO FREQUENCY. Radio Frequency (RF) continuity and frequency response testing shall be accomplished for every end leg of cable by the contractor. A signal shall be inserted into an inbound port and measured at the corresponding outbound port of a Drop as close to the end of an end leg as possible. The frequency shall be swept from the lowest (40 MHz) to the highest design (400 MHz) frequency at the stated level.

The level of the lowest and highest frequency will be recorded along with any level that falls outside the design specification. A 55 dBmV signal inserted into the inbound drop port shall produce a signal level of 10 (+ or - 5) dBmV at the associated outbound drop port at any frequency from 40 to 400 MHz.

AMPLIFIER DESIGN LEVELS. All Amplifier Levels shall be within (+ or -) 3 dB of the design levels.

AMPLITUDE RESPONSE. The Amplitude Response within any 6 MHz channel shall be within (+ or -) 1.5 dB

CARRIER TO NOISE. Carrier-to-Noise Ratio (CNR) shall be at least 43 dB in a 4 MHz bandwidth measured at the drop in each branch that is at maximum distance from the head end. The contractor shall take a reading at both the Low and High end of the designed bandwidth. CNR for inbound cable shall be measured at the Headend.

INTERMODULATION. Intermodulation tests shall be conducted at selected drops (those with long runs) using two signals at specified values and levels into an inbound port, and measuring the level difference between the two signals and the sum and differences at the corresponding output port. The frequencies are selected so that all frequencies (source, sum, difference) will be within the designed system bandwidth.

Intermodulation products shall be at least 50 dB below carrier signal levels. Any spurious signals observed shall also be at least 50 dB below the carrier.

RADIATION LEAKAGE. Radiation Leakage tests shall be conducted in accordance with the Federal Communications Commission (FCC) Rules and Regulations, Part 76, Subpart K Technical Standards (76.601-76.617).

AMPLIFIERS AND PILOT GENERATORS. Inspect Amplifiers and Remote Pilot Generators as follows:

(1) Examine the housing for signs of corrosion or mechanical damage.

(2) Inspect the mounting supports, the housing cover bolts, and hinge pins.

(3) All cables shall be held securely by the connectors. The connectors shall be torqued to manufacturer specifications. All unused ports shall have port plugs. All test points shall be securely covered with the dust caps.

(4) (Annual) Open the housing and examine the silicon rubber and wire mesh gaskets.

Inspect interior of the housing for signs of corrosion or damage.

(5) (Annual) Check that all plug-in modules or accessories are firmly seated and secured in their receptacles.

(6) (Annual) Replace any damaged or missing components.

(7) (Annual) Measure internal voltages in accordance with manufacturers specifications and correct as necessary.

(8) Check (Close) the cover to the housing ensuring the gaskets are properly seated and there are no foreign objects obstructing the seal. Hand tighten bolts to secure cover, then follow torqueing sequence recommended by manufacturer to specified torque value.

(9) Perform any other tests recommended by manufacturer.

POWER SUPPLIES. Inspect power supplies as follow:

(1) Inspect the housing, mounting bracket, and cover for damage.

(2) Inspect and correct, as necessary, the secure mounting of the power supply.

(3) Remove the cover and clean all of the accumulated dirt from the interior. Pay special attention to the interior vent screening.

(4) correct all connections of the wires in the terminal block that are not securely fastened by their respective retaining screws.

(5) Inspect all connections for corrosion and clean as necessary.

(6) Inspect batteries for cracks, leaks and excessive corrosion. Repair any damage caused by batteries. Check electrolyte levels if possible. Check operational condition.

Replace if unserviceable or excessively leaking.

(7) Maintain the operating and output voltages are in accordance with manufacturer's standards and as designed for the LAN.

(8) Perform whatever tests are recommended by the manufacturer that will verify the standby power supplies switch to auxiliary power during an AC power failure and return to main power when AC power is restored.

(9) Replace all lights and components that are not functioning properly.

(10) Perform any other task recommended by the manufacturer that will ensure proper performance.

(11) Replace and secure cover.

CABLES. Inspect all trunk cable, messenger cables, mounting and support hardware for any signs of wear and or damage.

5. Invoicing. Two contract lines (CLIN’s) will be used for LAN drops and RM. A firm fixed price (FFP) CLIN will be used for proposal pricing associated with each type of LAN drop. A separate time and material (T&M) CLIN will be used for proposal pricing and invoicing for any authorized RM.

5.1 T&M Invoicing Labor. The contractor shall only invoice at the agreed upon fully loaded T&M labor rate. Travel expenses are not reimbursable under this contract.

5.2 T&M Materials. The contractor shall invoice all material at cost only. No indirect cost and fees on material will be approved. No rental/lease fees for parts or equipment needed that will not be incorporated into the BBLAN system.

5.3 T&M Funding. The T&M CLIN will be incrementally funded, not to exceed the ceiling price established upon award. The contractor exceeds the currently funded amount at their own risk. Contractor shall be solely responsible for all costs incurred above the currently funded amount. The contractor shall notify the COR upon reaching eighty (80) percent of the funded T&M line item amount to allow the Government to consider adding additional funding if available.

6. Deliverables.

6.1 Approved RM. Contractor shall submit a quote for all proposed RM as identified by the contractor, or identified by the COR, during performance. Work shall not commence without approval from the COR.

7. Special Requirements.

7.1 AT OPSEC requirements

7.1.1 ANTITERRORISM/OPSEC Requirements. In performing this contract, the Contractor will have Operations Security (OPSEC) requirements per facility requirements (below) which shall be provided to employees during paid hours.

7.1.2 Antiterrorism (AT) Level I Training. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 10 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: https://Jkodirect.jten.mil/ for CAC holders. Non-CAC-holders may go to: http://jko.jten.mil/courses/atl1/launch.html.

7.1.3 iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 10 calendar days after completion.

7.1.4 Operations Security (OPSEC) Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter. Level I OPSEC training is available at the following website:

http://cdse.edu/catalog/elearning/GS130.html (Duration: 45 minutes).

7.1.5 Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by TYAD Security Branch. Contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by the government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

7.1.6 Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

8.0 PERFORMANCE STANDARDS.

The COR’s Quality Assurance Surveillance Plan (QASP) will be provided to the contractor at time of award.

Task Performance Objective(s) Method of Surveillance

1. Ethernet Drops. 1. As required by the Government the contractor shall provide a team of journeymen LAN cable installers to install and terminate category 5E, 6 and 6E LAN twisted pair cable drops as requested by the COR or his technical representative.

1. Review of contractor installations. TYAD uses an internal service desk tracking system.

1.1 Coaxial Drops.

1.1 Upon request by the COR, the

contractor shall provide all technical service hardware, plant, labor, parts and material required to physically, electrically and logically add to the existing Broad Band Cable Plant (BBCP) located at TYAD, up to 100 ea. 100 foot

1.1 Review of contractor

installations. TYAD uses an internal service desk

Dual RG 59 or an accepted electrical equivalent from node taps designated by the Government to a specific demark location as designated by the Government.

1.2 Horizontal Install

1.2 Upon request by the COR, the contractor shall provide a team of journeyman LAN cable installers to install and terminate Government supplied 48 pair fiber optic or up to 200 pair copper telephone continuous cable either via Government conduit or ariel plant. Fiber terminations shall be accomplished via fusion IAW National Electrical Code (NEC).

Installation pricing will be per 50 feet for both fiber optic and copper.

1.2 Review of contractor

installations. TYAD uses an internal service desk

2 Remedial Maintenance .

1 The contractor shall provide on-site RM within six (6) hours of notification by the government if a major failure occurs.

Major Failures must be corrected within eighteen (18) business hours after authorization for repairs is received.

Ensure BB LAN service is restored.

8.1 The performance standard evaluation ratings are as follows:

PASS

FAIL

8.2 UNACCEPTABLE PERFORMANCE:

There is a 90% acceptance that repairs on equipment are completed within established timeframes and function to OEM specifications. Less than 90% is considered unacceptable.

8.3 Remedies for unacceptability are: at the Contracting Officers discretion the contractor shall arrange for repair by another qualified source at the contractors expense.

8.4 If unacceptable performance occurs, the COR shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication.

8.5 When the COR determines formal written communication is required, the COR shall prepare a Contract Discrepancy Report (CDR), and present it to the contractor's task manager or on-site representative. A CDR template is attached to this QASP.

8.6 The contractor shall acknowledge receipt of the CDR in writing. The CDR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CDR will state how long after receipt the contractor has to present this corrective action plan to the COR. The Government will review the contractor's corrective action plan to determine acceptability.

8.7 CDRs become a part of the supporting documentation for remedies under the contract if deemed necessary by the Contracting Officer.