STATEMENT OF WORK
BUILDING 1E PLATING TANK & WASH STATION
TOBYHANNA ARMY DEPOT
March 2018
1. GENERAL
1.1. SUMMARY: This task order will consist of the purchase of a new non-hexavalent aluminum chromate plating tank and rinse tank for the 1E plating shop, as well as construction of the substructure and associated utilities required for the support and functionality of the tanks. The construction services necessary to complete this installation includes providing all licenses, permits, labor, materials, equipment, supervision and management to complete the project and ensure complete functionality of the new equipment. All and any exceptions shall be submitted in writing.
1.2. KEY ELEMENTS:
The work includes but is not limited to:
A. Demolition
a. The contractor shall remove existing wash station, deck plate, floor grate, and necessary steel.
i. The contractor shall save all materials for reuse and place at a location within the same shop per government instruction.
B. Non-Hexavalent Aluminum Chromate Tank
a. The contractor shall purchase and secure aluminum chromate tank in Building 1E Plating shop on newly renovated structure.
i. The tank shall be installed according to manufacturer specifications.
ii. The tank shall be fabricated and constructed to minimum specifications of existing PKG AC-60 tank, or equivalent, in the Building 1E Plating Shop. Specifications are found in paragraph d.
1. The contractor shall be required to verify all measurements, dimensions, and materials during site visit prior to fabrication.
2. The contractor shall submit CAD shop drawings with all dimensions, materials, and construction to the COR for government approval prior to fabrication.
b. The contractor shall deliver tanks to Building 1E Plating Shop.
i. The contractor shall furnish their own lifting equipment to deliver tanks to the shop.
1. The contractor shall use only electric-powered equipment inside all Government buildings.
2. It shall be the responsibility of the Contractor to deliver, off-load, transport, properly position, and place the new tanks at a designated location within Building 1E.
3. The contractor shall be responsible to provide all personnel and equipment necessary to deliver, off-load, transport, properly position, and place the new tanks at a designated location within Building 1E.
4. Delivery date and time shall be coordinated with the COR a minimum of 14 calendar days in advance of delivery to TYAD.
5. The contractor shall be able to provide delivery of the tanks on a Saturday.
6. A partial delivery is not acceptable.
c. The government shall connect tanks to necessary utilities after placement on newly renovated substructure.
d. The tank shall adhere to the following minimum specifications:
i. The Contractor shall use welded construction. Welding shall be per
ANSI/AWS D1.1-98.
ii. The tank shall have inside dimensions of 144 inches long x 54 inches wide x 72 inches deep.
iii. The tank shall be fabricated using ¼ inch thick 316 stainless steel.
iv. The tank encapsulation shall be fabricated from 18 gauge 304 stainless steel.
v. There shall be a 3 inch rim along the entire top of the tank.
vi. The tank shall be fabricated with 10 ea. pipe supports that measure 2 inches x 3 inches x 12 inches long.
vii. The tank shall be fabricated with 5 ea. C-Channel supports spaced evenly along the underside of the tank. The C-Channel supports shall be evenly-spaced and shall be oriented and installed to run the full width of the tank.
viii. The tank shall be constructed with a base angle mounting flange.
ix. The tank insulation shall be 2 inch thick mineral wool.
x. The tank shall be constructed to permit an operating temperature of 90 degrees Fahrenheit, minimum.
xi. The tank shall be equipped with 1 ea. steam coil with all supporting hangers installed.
xii. The tank shall be equipped with 1 ea. steam loop with solenoid. The solenoid shall be pre-wired.
xiii. The tank shall be equipped with 1 ea. condensate loop.
xiv. The tank shall be equipped with a filter pump with disconnect. The disconnect shall be pre-wired for 480VAC and seal tight.
xv. The tank shall be equipped with a pre-wired DI water fill solenoid.
xvi. The tank shall be equipped with a filter chamber, pump piping and eductors.
xvii. The tank shall be equipped with an electrical enclosure that shall house the pump control switches, level controller, and temperature controller.
The enclosure shall be pre-wired to the sensors and solenoids.
xviii. The tank shall be equipped with a temperature sensor and thermostat.
xix. The tank shall be equipped with a level sensor with controls.
xx. The tank shall be equipped with a sparge air header.
C. Rinse Tank
a. The contractor shall purchase and secure new rinse tank in Building 1E Plating Shop on newly renovated structure.
i. The tank shall be installed according to manufacturer specifications.
ii. The tank shall be fabricated and constructed to minimum specifications of existing PKG AC-70 rinse tank, or equivalent, in the Building 1E Plating Shop. Specifications are found in paragraph d.
1. The contractor shall be required to verify all measurements, dimensions, and materials during site visit prior to fabrication.
2. The contractor shall submit CAD shop drawings with all dimensions, materials, and construction to the COR for government approval prior to fabrication.
b. The contractor shall deliver tanks to Building 1E Plating Shop.
i. The contractor shall furnish their own lifting equipment to deliver tanks to the shop.
1. The contractor shall use only electric-powered equipment inside all Government buildings.
2. It shall be the responsibility of the Contractor to deliver, off-load, transport, properly position, and place the new tanks at a designated location within Building 1E.
3. The contractor shall be responsible to provide all personnel and equipment necessary to deliver, off-load, transport, properly position, and place the new tanks at a designated location within Building 1E.
4. Delivery date and time shall be coordinated with the COR a minimum of 14 calendar days in advance of delivery to TYAD.
5. The contractor shall be able to provide delivery of the tanks on a Saturday.
6. A partial delivery is not acceptable.
c. The government shall connect tanks to any necessary utilities after placement on newly renovated substructure.
d. The rinse tank shall adhere to the following minimum specifications:
i. The Contractor shall use welded construction. Welding shall be per
ANSI/AWS D1.1-98.
ii. The tank shall have inside dimensions of 144 inches long x 51 inches wide x 72 inches deep.
iii. The tank shall be fabricated from 1 inch thick polypropylene.
iv. The tank shall be fabricated with a 3 inch rim along the entire top of the tank.
v. The tank shall be fabricated with 1 ea. 2 inch 150 pound flange fitting with gusset.
vi. The tank shall be equipped with 1 ea. overflow weir.
vii. The tank shall be fabricated with 5 ea. encapsulated girths.
viii. The tank shall be fabricated with 14 ea., 1 inch x 2 inch x 12 inch long, support tabs.
ix. The tank shall be fabricated with 4 ea., 1 inch x 2 inch x 14 inch long, work bar gussets.
x. The tank shall be fabricated with 7 ea. supports on the underside of the tank. The supports shall be evenly-spaced along the entire length of the tank and oriented and installed to run width-wise along the tank underside.
xi. The tank shall be equipped with 1 ea. air sparge header with 24 ea.
installed sparger support clips.
D. Drip Shield
a. The contractor shall fabricate and install a drip shield with any necessary supports between the newly installed tanks.
i. The drip shield shall be constructed to allow dripping chemicals to be caught as assets are moved from the new Aluminum Chromate tank to the rinse tank and drain back into the Aluminum Chromate Tank.
ii. The drip shield shall be constructed with similar materials and construction to surrounding drip shields.
1. The contractor shall submit CAD drawings of drip shield to the COR for approval prior to fabrication.
E. Substructure Work
a. The contractor shall install steel support beam and substructure to support the new plating tank and rinse tank.
i. The contractor shall use materials and installation/construction methods according to manufacturer specifications.
ii. The steel support beam shall match surrounding beams in dimension and material.
1. The steel support beam shall be places equidistant from the surrounding beams.
2. The contractor shall submit a specification sheet for all materials and installation methods to the COR for approval prior to start of construction.
3. The support beams shall be of sufficient material and dimension to support the weight of the newly installed tanks while full of liquid.
b. The contractor shall remove unnecessary piping and cap all pipes removed.
i. The contractor shall confirm which pipes can be removed and capped with COR prior to demolition and construction.
c. The contractor shall relocate existing sprinkler pipe in order to not interfere with new support beam.
i. The contractor shall submit relocation plan to the COR prior to demolition and construction.
F. Warranty
a. The Contractor shall warrant the tanks, all materials and parts, and all workmanship for a period of one (1) calendar year following Final Acceptance by the COR. During this warranty period all parts costs, labor costs, transportation and shipping costs, travel costs, tool costs and per diem for all Contractor personnel shall be the responsibility of the Contractor. The Contractor field repair technician shall arrive on-site within 72 hours after being contacted by TYAD personnel to make warranty repairs during the warranty period. The Contractor shall supply to the COR Contact Telephone Numbers and Points of Contact (POCs) for use by TYAD personnel for warranty calls.
G. Submittals
a. The contractor shall submit a preliminary floor plan, including dimensions of the tanks, with bid submission in order to ensure technical acceptability.
b. The contractor shall supply preliminary sketches of the tank to the COR for approval that include dimensions, parts identifications, material selections, and fabrication methods prior to fabrication.
c. The contractor shall submit all materials and processes for the installation of substructure and all utilities installed or relocated under this task order.
d. The contractor shall supply the COR with any operator or maintenance manuals for the tanks upon completion of project.
H. Miscellaneous Requirements
a. All work shall be conducted at the convenience of the government. The contractor shall be willing to work outside of normal business hours or on weekends as required to complete the work without interfering with TYAD Plating Shop Operations. All work schedules and deliveries shall be coordinated with the COR.
i. Normal TYAD business hours are Monday-Friday, 0700-1630.
b. Removal of all construction/demolition debris shall be the sole responsibility of the contractor. The contractor shall dispose of all waste materials according to Tobyhanna Army Depot Recycling Policy.
c. The contractor shall provide a copy of all MSDS sheets for any hazardous materials and their safety plan to the COR prior to the start of construction, as well as keep a copy of each available at the job site or trailer to be presented upon request.
d. The contractor shall submit to the COR weight certificates for all construction/demolition debris removed from the worksite with destination information (recycled/disposed).
e. The contractor shall be responsible for verifying all measurements and site conditions during site visit.
I. Pre-Award Site Visit
a. A site visit will be scheduled by the Government and it is advised that interested Contractors attend. The site visit is for the purpose of interested Contractors to consider the layout and floor space of the project area and to enable the viewing of the delivery, utility and installation sites. The site visit shall be used by the Contractors to identify structures or conditions that may impede, obstruct or prevent completion of the work. It shall be the responsibility of the Contractor to identify obstructions and impediments to the project and to make appropriate accommodations for correction and modification to mitigate the problem. If corrective measures conflict with other requirements listed in the SOW or is outside the work area the Contractor shall identify these issues in the proposal submittal to the Government.
Answers not contained in the SOW to all questions that are raised during the site visit shall be submitted in writing. Should the Contractor fail to identify an obstruction or hindrance to the project that is identifiable from a site visit the Contractor shall provide a solution to the problem that is to the satisfaction of the Government and at no additional cost to the Government. It shall be the responsibility of the Contractor for all dimensioning of the system including all ancillary pieces and material. It shall be the responsibility of the Contractor to supply his personal protective equipment (PPE) for the site visit. At a minimum, the PPE needed is protective eyewear, protective footwear and ear protection.
J. Government Furnished Equipment
a. The government shall provide access to the existing overhead crane in the Building 1E Plating Shop to use for placement of the tanks and materials.
1.3. EXISTING
Existing conditions include:
A. A wash station is currently installed in the location for the new tanks, along with floor grating and supporting steel.
B. Drain pipes and fire suppression sprinkler pipes are below the floor grate.
2. PRODUCTS, MATERIALS AND EXECUTION
2.1. ALL DESIGNS AND INSTALLATIONS SHALL COMPLY THE INTERNATIONAL
BUILDING CODES (IBC) AND UNIFIED FACILITIES GUIDE SPECIFICATION
(UFGS). CODES AND STANDARDS INCLUDE, BUT NOT LIMITED TO, THE
LATEST: NATIONAL ELECTRIC CODE (NEC), NATIONAL FIRE PROTECTION
ASSOCIATION (NFPA), UNDERWRITER’S LABORATORY (UL), AMERICAN
SOCIETY of MECHANICAL ENGINEERS (ASME), AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI), OCCUPATIONAL SAFETY and HEALTH ADMINISTRATION (OSHA), AMERICAN SOCIETY for TESTING and MATERIALS (ASTM), AMERICAN SOCIETY of HEATING, REFRIGERATING, and AIR
CONDITIONING ENGINEERS (ASHRAE), INTERNATIONAL MECHANICAL CODE
(IMC), AND INTERNATIONAL PLUMBING CODE(IPC).
IN ADDITION, ALL DESIGNS AND INSTALLATIONS SHALL COMPLY WITH
TOBYHANNA ARMY DEPOT DESIGN/INSTALLATION GUIDELINES WHICH
ARE SPECIFIC TO THE DEPOT.
IN ANY CONFLICTS BETWEEN SPECIFICATIONS (CODES) AND TYAD
DESIGN/INSTALLATION GUIDELINES, TYAD GUIDELINES SHALL GOVERN
UNLESS WRITTEN APPROVAL BY AHJ IS OBTAINED.
THE FOLLOWING IS A LIST OF TYAD DESIGN / INSTALLATION GUIDELINES
AND SAFETY / FIRE / AND ENVIRONMENTAL REQUIREMENTS AND
REGULATIONS WHICH APPLY WHEN WORKING ON THE DEPOT. THESE
APPENDIXES WILL BE MADE AVAILABLE DURING THE BIDDING PROCESS
AND IT IS SOLELY THE CONTRACTOR’S RESPONSIBILITY TO OBTAIN COPIES
OF THOSE LISTED AS REQUIRED FOR THE PROJECT PRIOR TO SUBMITTING A
BID. FAILURE TO OBTAIN COPIES OF APPENDICES BY THE CONTRACTOR
DOES NOT RELIEVE THE CONTRACTOR OF THE REQUIREMENTS CONTAINED
WITHIN.
TYAD ISD/ENGINEERING OFFICE IS THE “AUTHORITY HAVING
JURISDICTION” (AHJ) AND IS RESPONSIBLE FOR APPROVING EQUIPMENT,
MATERIALS AND INSTALLATION.
ISD Engineering Br CONTRACT PACKAGE REQUIREMENTS CHECKLIST
Non‐Hex Plating Tanks ISD POC: Mark Kisel (x5‐7264)
REQUIRED
YES NO
APPENDIX A - TOBYHANNA EXECUTIVE SUMMARY FINAL X
APPENDIX B - ROOM NUMBERING METHODOLOGY DEC 2014 X
APPENDIX C - DESIGN SUBMISSION REQUIREMENTS MANUAL X
APPENDIX D - TYAD CADD STANDARDS MANUAL X
APPENDIX E - STANDARD NEPA SPECIFICATIONS FOR PROJECTS JULY 2015 X
APPENDIX F - ENVIRONMENTAL CONCERNS FOR CONTRACTORS JULY 2015 X
APPENDIX G - ELECTRICAL DESIGN and CONSTRUCTION STANDARDS REV 03-05-17 X
APPENDIX H - MECHANICAL DESIGN JULY 2015 X
APPENDIX I - REQUIREMENTS FOR CONTROLS AND INSTRUMENTS JUL 2015 X
APPENDIX J - FIRE DETECTION & SUPPRESSION 07-21-15 X
APPENDIX K - SAFETY STANDARDS FOR TYAD JANUARY 2018 X
APPENDIX L - SOP FOR EXCAVATION & GROUND PENETRATIONS 07-21-15 X
APPENDIX M - DOOR HARDWARE SPECIFICATION X
APPENDIX N - COMMUNICATION INFORMATION TECHNOLOGY X
3. QUALITY ASSURANCE:
3.1 Rejection of Work: Indication of lack of quality workmanship on the part of the contractor shall be sufficient grounds for the Government to reject installed work and to require its immediate removal and complete reinstallation at no additional cost to the Government.
4. SUBMITTALS (Construction)
4.1 Submit to the ISD Engineering POC (COR) six copies of all submittals, except as noted below. Allow two weeks for Government review. The Contractor shall certify on all submittals that the material being proposed conforms to contract requirements. In the event of any variance, the Contractor shall state specifically which portions vary, and request approval of a substitute. The Contractor shall also certify that all Contractor-furnished equipment can be installed in the allocated spaces. Incomplete submittals and submittals with inadequate data will be rejected. When required, catalog data shall be printed pages or permanent copies of manufacturer's catalogs.
A. Job Specific Safety Plan (Per Appendix K) B. Installation Schedule C. Photometric analysis for lighting plan D. Panel Schedules E. Asbestos Evaluation & Remediation Report F. Air Flow Verification for Exhaust Gas Recovery Systems G. Compressed Air Commissioning Report H. As-Built Record Drawings as per TYAD CADD Standards Manual (Appendix D) I. Operation and Maintenance Manuals for Installed Equipment J. Safety Data Sheets for all hazardous materials proposed for use
5. SECURITY REQUIREMENTS: Contractor personnel working on the Tobyhanna Army Depot must be fully identified. Contractors register with the TYAD Security in Building 20. All employees, staff, and subcontractor personnel, etc., which will require access must present the following to access TYAD:
A. Full name B. Drivers License C. Nationality (if non-U.S. Citizen, alien registration number) D. Completed Form ELTY 648C (Contractor Request for Access to TYAD) E. Completed Form ELTY 648C must be submitted to TYAD prior to date of arrival as required by contract solicitation documentation.
If Contractor vehicles are required for use on TYAD, the following ID is required:
A. Make B. Model C. State Registration D. Insurance
E. License Plate #
Contract personnel are expected to perform work during normal TYAD duty hours (0600-1700).
If work must be performed otherwise, permission must be obtained three working days prior from the Security Office through the ISD Engineering POC (COR). ISD Engineering POC will also coordinate with changes in work schedules with Mission Modernization Branch and Mission Operations as needed to determine impact on production.
Contractor personnel must confine themselves to the work sites specified in their contract.
Visiting other areas is prohibited.
Alcoholic beverages, weapons, cameras, sound recorders, proscribed drugs and explosives are prohibited on Government property.
Use of Government property without prior written approval of the COR is prohibited.
TYAD will arrange for special Contractor parking if required. Contractor personnel must not park in numbered spaces, areas reserved for car pools, grassy areas or other prohibited areas.
Posted speed limits and traffic restrictions must be observed at all times.
Accidents or problems of a security/safety nature must be reported to the Security (570.615.7550) and ISD Engineering POC in Bldg 18 (570.615.8115) immediately. (Safety to contact Security)
Contractor personnel working on station for less than 30 days may be required to log in and out at the Reception Center (Bldg 20) each day and will not be issued an Extended Entry Contractor's Badge. The ISD Engineering POC (COR) will provide information on how to obtain an Extended Entry Contractor's Badge if one is required.
Pursuant to federal regulations, all personnel and vehicles on Government property are subject to search by authorized personnel at any time.
All Contractors personnel are required to display the TYAD issued identification badge on their person at all times while present at the work site. Access to Government property will not be allowed without this identification badge. The badge is to be displayed on the person outer clothing, above the waist and in full view. Identification badges and vehicle passes issued to Contractor personnel remain the property of the U.S. Government and must be surrendered upon completion of the Contractor at the termination of individual employment, and when requested by the Government. Badges will not be displayed when not on Tobyhanna property.
A list of all personnel working under this contract should be turned in immediately after award in order to allow sufficient time to process security information.
ANTITERRORISM (AT) / OPERATIONS SECURITY (OPSEC) REQUIREMENTS
Antiterrorism (AT) Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date and within 30 days of report date for any additional or new contractor employees, who start after that period. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR within 10 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: https://jkodirect.jten.mil. A Login is not necessary. Non- CAC users select the Non-CAC link for JS-US007: Level I Antiterrorism Awareness Training.
Upon request, the contractor will be provided one copy of the AT level I training slides for use with employees who may not have computer access. TYAD will not be responsible for printing copies of slides for training purposes. TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record, or contractor equivalent. As applicable, contractor employees must complete annual AT awareness training as it pertains the length of the contract.
iWATCH Army Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH Army Program. This will consist of utilizing the tools and media products on the informational iWATCH Army website to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. The iWATCH training is available at the following website: https://myarmyonesource.com select Family Programs and Services, in the drop down boxes select: Go To, iWATCH Army –“See Something, Say Something”. Additional guidance and support can be provided by the TYAD Antiterrorism Officer (ATO) at the contractor’s request. This training shall be completed within 30 calendar days after contract start date and within 30 days of report date for any additional or new contractor employees, who start after that period. The contractor shall notify the COR within 10 calendar days of the completed training for any new employees or subcontractor personnel to assure the ELTY form 583 or contractor equivalent is properly documented. TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record or contractor equivalent.
Operations Security (OPSEC) Training. Per AR 530-1, Operations Security, contractor employees must complete Level I OPSEC training within 30 calendar days after contract start date and within 30 days of report date for any additional or new contractor employees, who start after that period. All contractor employees must also complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR within 10 calendar days after completion of training by all employees and subcontractor personnel. The contractor will be provided a copy of the OPSEC training slides for use with employees who may not have computer access. TYAD will not be responsible for printing copies of slides for training purposes. TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record or contractor equivalent.
Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by TYAD Security Branch. Contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190- 13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by the government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
Common Access Card (CAC) and Information Systems/Network Access by Contractor Workers. Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05. The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.
All contractor employees and associated sub-contractor employees with access to a Government Information System (IS) must be sponsored in Army Knowledge Online (AKO), registered in the ATCTS (Army Training Certification Tracking System) at commencement of services, and must successfully complete the DoD Information Assurance Awareness training prior to issuance of network access to the IS and then annually thereafter.
6. SMOKING RESTRICTIONS: The bearing and use of lighted cigarettes, cigars, pipes, or any tobacco product is prohibited in the following areas:
A. All buildings including private offices, lobbies, and restrooms B. Alleys and passages between buildings C. Stairways and ramps leading to building entries and exits D. Within 50 feet of building entries and exits E. Within 20 feet of heating, ventilation, and air conditioning intake ducts F. Hazardous areas containing flammable liquids, gases, vapors, and all other locations where there is a collection of readily ignitable combustible material
7. STATION PERMITS and WRITTEN APPROVALS:
7.1. Permits are required for, excavation, welding and burning. Contractors must utilize the PA 1 Call system and obtain a permit coordinated with ISD Engineering for excavations in accordance with Appendix L prior to any groundbreaking including digging, drilling and stake driving. Burn/fire permits must be obtained daily from the Fire Department (Appendix K).
7.2 Written approval (Appendix K via e-mail) must be obtained from the Safety Office through the ISD Engineering Branch prior to executing any of the following:
a. Trenching five feet or more in depth (Trench Plan)
b. Entry to a confined space
c. Crane Lift (Lift Plan)
8. STORM PROTECTION: If a warning of gale force winds is issued, take precautions to minimize any danger to persons, and protect the work and any nearby Government property.
Precautions shall include, but not be limited to, closing openings, removing loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work. Close openings even if expected storms are of a lesser intensity but, may still pose a threat to the work site or any nearby Government property.
9. PCB, HAZARDOUS MATERIALS, ASBESTOS AND LEAD MATERIAL: If material is encountered which may contain PCB’s, hazardous materials, asbestos and or lead and must be disturbed, do not touch the material. Should the discovery of such suspected material affect the Contractor's planned work schedule, the Contractor shall redirect the work crew to other portions of the unaffected work and modify the schedule at no additional cost to the Government. The ISD Engineering POC (COR) shall be notified immediately, in writing, regarding the discovery of the suspected material and of any adverse impact the Contractor may expect to incur due to this situation. Within 10 calendar days, the Environmental, Safety and Occupational Health Branch (ESOH Branch) Representative will have laboratory tests performed to determine if the material is a hazard. If there is not a danger, the ESOH Branch Representative will direct the Contractor to proceed in the identified area without change. If the material is identified as hazardous, before proceeding, discussions will be held between the Contracting Officer's Representative, ISD Engineering POC (COR) and ESOH Branch to determine the most cost-effective means for removal. The hazardous material will be removed, abated or rendered harmless before work commences.
10. SAFETY REQUIREMENTS: (See Appendix K for Safety details)
11. ENVIRONMENTAL PROTECTION REQUIREMENTS: In addition to the following conditions, the contractor shall provide and maintain, during the life of the contract environmental protection. Plan for and provide environmental protective measures during normal construction practice. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Comply with all Federal, State of Pennsylvania, and local environmental regulations pertaining to the environment, including but not limited to, hazardous waste, storm-water discharge, erosion control, water, air, soil, and noise pollution. See Appendix I (Standard Specifications for Projects Under the National Environmental Policy Act).
a. The contractor shall submit MSDSs for all hazardous materials proposed for use including paints, solvents, adhesives, etc. These copies of MSDSs will be provided to the ESOH Branch through the COR prior to material being brought on post.
b. The contractor shall not install any equipment, switches, or devices (including thermostats) that contain mercury, lead, cadmium, chromium, asbestos or PCBs.
c. The contractor shall not pollute streams, lakes, or reservoirs with fuels, oils, bitumens, calcium chloride, acid, construction wastes, or any other harmful materials. All work under this contract shall be performed in such a manner that pollution will not be created in streams, surface waters, or underground water located within, or adjacent to the project area. The contractor shall not spill, emit, dump, or otherwise discharge any hazardous, toxic, harmful, or unauthorized pollutant, substance, or material, including petroleum products, cleaning agents, or paints, onto the ground, into the air, or into any waters or nearby storm drain. The contractor shall execute any preventative measures required to prevent any hazardous, toxic, or harmful material stored, or used on the project site from entering any storm water drain. Nothing shall be allowed to spill, emit, dump, or otherwise discharge any hazardous, toxic, or harmful material or pollutant into any sink, toilet, drain, utility, or receptacle without written permission from the ESOH Branch through the COR. The contractor shall protect streams, lakes, and wetlands from sediment discharges caused by his activities.
d. The Contractor shall comply with the Public Law 42 U.S.C. 6962, Resource Conservation and Recovery Act (RCRA) in the acquisition of materials with recycled content to meet the standards of Executive Order 13423. Specific designated items in this contract for which recycled content standards have been established have been set forth in the specification (e.g., insulation, roofing materials, carpet, carpet pad, paint, floor tiles, shower, and restroom dividers). Recovered Material Certification: As required by the RCRA, the contractor will certify that the percentage of recovered materials to be used in the performance of the contract will be at least the amount required by the applicable contract specifications (see Federal Acquisition Regulation (FAR) Provision 52.223-4, Recovered Material Certification). In contracts exceeding $100,000, prior to application for final payment, the contractor shall provide a report in accordance with FAR Clause 52.223-9, Estimate of Percentage of Recovered Material Content for Environmental Protection Agency (EPA) Designated Products, to the Contracting Office. Compliance with this program does not relieve the contractor from meeting all other specification requirements.
e. The contractor will ensure that no Asbestos-Containing Materials (ACM) are used in the performance of this contract. Unless specified for abatement in the contract, the contractor will not disturb any existing ACM in the performance of this contract. If ACM, or suspect ACM might be disturbed by the work, the contractor shall avoid coming in contact with the material and immediately notify the ISD Engineering POC (COR) and the Contract Administrator in writing (fax or e-mail acceptable) of the possible ACM. The ISD Engineering POC will coordinate with ESOH Branch to obtain laboratory tests to determine if there is ACM. If the material is determined to be ACM, and disturbing it cannot be avoided, the ISD Engineering POC (COR) will notify the Contracting Officer. The Contracting Officer will direct a change pursuant to the contract clauses entitled “Changes” and “Differing Site Conditions.” If ACM, or suspect ACM has been disturbed, the contractor shall immediately notify the ISD Engineering POC and call the ESOH Branch at (570) 615-7098. The contractor will shut down and not move any equipment or supplies near the damaged ACM. The contractor will evacuate all non-contaminated contractor personnel from the immediate vicinity. Any contractor personnel thought to be contaminated with asbestos (e.g., evidence of dust on clothing) should remain in the area, but as far away as possible from the damage, until the ESOH Branch responds. If the damaged material is determined to be ACM and there is potential for further damage, the Contracting Officer will direct a change pursuant to the clauses of the contract clauses entitled “Changes” and “Differing Site Conditions.”
Asbestos abatement required under the contract as originally awarded shall be in accordance with Section 13280, Removal and Disposal of Asbestos Materials, and as otherwise required in the contract. Asbestos abatement not required under the contract as originally awarded, can be incorporated into the existing contract via contract modification, or with the government taking responsibility for the asbestos abatement.
The method of acquiring the abatement is at the discretion of the Government.
f. If a project involves the demolition of any load-bearing structural members, whether or not asbestos is present, twenty (20) days prior to the demolition, the Commonwealth of Pennsylvania, Asbestos Abatement and Demolition/Renovation Notification, Form 2700- FM-AQ0021, revised 8/2005 (or the most recent version), shall be submitted to the proper authorities as specified in Section 13280, Removal and Disposal of Asbestos Materials. The form is available from the ESOH Branch.
g. The contractor is to collect, containerize, recycle, and manage florescent and mercury bearing lamps in accordance with 40 CFR 273. A copy of the manifest/Bill of Lading shall be given to the ESOH Branch five days in advance of shipment by the contractor through the COR so that it can be reviewed for accuracy and completeness.
h. The contractor shall ensure that all hazardous wastes at the work site are properly stored and labeled in a pre-approved location designated by the ESOH Branch. The contractor shall provide copies of any shipping documents for Hazardous Waste/Universal Waste/Toxic Substances Control Act waste. If the depot EPA number is being used for shipping purposes, only ESOH Branch is authorized to sign a manifest and the manifest (or copy) must be supplied prior to the day of shipment for review. The
ESOH Branch will keep originals. If hazardous waste or waste requiring special handling (e.g., asbestos) is being turned over to the government for disposal, the contactor shall notify the ESOH Branch through the ISD Engineering POC (COR) when the waste is ready to be moved.
i. The contractor will not perform any work on the depot potable water system until prior approval is obtained from the ESOH Branch and the D/EL certified operator through the ISD Engineering POC (COR). If a permit is required due to construction or proposed chemical feed changes, it will be the responsibility of the contractor to obtain all permits associated with the project. Any piping or additions added to the depot water system must be disinfected following American Water Works Association (AWWA) circular C601-68 "Disinfecting Water Mains."
j. The contractor shall have a backflow prevention device installed on all contractor equipment that is connected to the depot's water distribution system. The contractor shall have a water meter installed to monitor water consumption of all new buildings constructed.
k. The contractor shall protect streams, lakes, and wetlands from sediment discharges caused by the contractor's activities. The contractor shall also provide (where applicable) an erosion and sedimentation control plan in compliance with state and local laws and regulations, to the COR for approval prior to executing any soil disturbing activities. The contractor shall not disturb any wetlands. The contractor shall submit a storm water permit to PADEP prior to any construction activity that encompasses more than one acre.
l. During the performance of all construction, renovation, and demolition projects, a minimum of 50 percent of all non-hazardous construction demolition debris shall be diverted from the landfill for reuse or recycling. The contractor shall provide written certification to the COR of the type and tonnage of debris reused or recycled from the contract. All refuse and the construction demolition debris not recovered for reuse or recycling shall be disposed of at a PADEP permitted and Monroe County Municipal Waste Management Authority authorized facility. The contractor shall comply with the Monroe County Solid Waste Management Plan and PA Act 90, including all licensing requirements. The contractor shall provide a disposal certificate or landfill weight slip to the ISD Engineering POC (COR) for all solid waste disposed of during the performance of this contract.
m. The contractor shall not bring items containing PCBs onto the depot. Light ballasts that are clearly marked "Contains no PCBs", or that are marked with a manufacture date after 1978 shall be disposed of by the contractor as construction demolition debris. Any light ballast that is not marked as containing no PCBs that has a manufacture date prior to 1978, or that cannot be determined whether it contains PCBs, shall be disposed of by the contractor at an approved and licensed facility.
The contractor shall submit a shipping manifest and certificate of disposal of the PCB-containing items to the ESOH Branch through the ISD Engineering POC (COR).
n. The contractor shall not use paints containing zinc chromate or strontium chromate pigments and paints containing lead in excess of 0.06 percent by weight of the total nonvolatile content (calculated as lead metal).
o. At no time during the execution of this contract shall the contractor provide a food source or harborage for any pests. The contractor shall coordinate all herbicide and pesticide usage and report all usage through the ISD Engineering POC (COR) to the ESOH Branch prior to application. After completion of the contract, the contractor shall ensure there is no passage for pest to enter facilities or structures related to work performed by the contractor.
12. STORAGE OF MATERIALS AND EQUIPMENT: Government furnished storage facilities may not be available to the Contractor in the vicinity of the work site. The Contractor shall provide suitable storage facilities as required, located as approved by the ISD Engineering POC (COR), if he intends to leave materials and equipment in the work area overnight or on weekends. The security of the Contractor's property or his personnel's property shall be the full responsibility of the Contractor. The Government will accept no liability in case of loss due to fire or theft.
13. AVAILABILITY OF UTILITY SERVICES: The Government will furnish water and power in the quantity not to exceed the amount necessary for the normal prosecution of the work, at the nearest available outlet. The Contractor shall make all piping and wiring connections thereto and shall extend the services to the site of the work. On completion of the work, the Contractor shall remove all such temporary connections and any removed or damaged portions of the Government services at the points of connection shall be repaired or replaced.
A. Other Utilities: The Contractor shall make arrangements to obtain all utilities not furnished by the Government, at his/her own expense.
B. The Government will not provide refuse facilities. The Contractor will be required to dispose of all garbage and other waste materials generated by his work at a licensed off-site landfill.
14. ORAL MODIFICATION: No oral statement of any person other than the Contracting Officer or as delegated by the Contracting Officer as provided in the Basic Contract shall in any manner or degree modify or otherwise affect the terms of this Contract.
15. TIME FOR COMPLETION: All work and services under the base bid shall be completed within 90 calendar days after award of the task order.
16. WORK SCHEDULE: Normal working hours are between 0600 and 1700, Monday through Friday, except (a) federal holidays, or (b) other days so designated by the Contracting Officer's Representative/ISD Engineering POC. Any work other than these hours or weekend work will be permitted only when advance written approval has been issued by the ISD Engineering POC (COR) three working days in advance. The contractor may be required to work outside of these hours, as determined by the COR. All work associated with the pre-engineered enclosure affecting road closure, or restricted traffic flow shall be performed after normal working hours unless approved in advance as part of the construction schedule. To work on post at any other times will require a request to the ISD Engineering POC (COR) 48 hours in advance.
17. DELIVERABLES: Upon completion of the construction and prior to final payment, the Contractor will supply the On Site Representative with two (2) copies of the following:
A. As Built Drawings as per TYAD CADD Standards Manual listed in Appendix D:
B. Operation and maintenance manuals. Submit 4 copies. Information shall include:
Safety precautions, Normal operations, Lubrication data, Preventive maintenance plan and schedule, Troubleshooting guides and diagnostic techniques, Wiring diagrams and control diagrams, Maintenance and repair procedures, Removal and replacement instructions, Spare parts and supply list, Parts identification, Warranty information, Test equipment and special tool information, and Contractor information.
C. All new underground utilities within the construction area shall be located and identified on the as-built drawings using the Pennsylvania (North) State Plane coordinate system (North American Datum 1983 Feet (NAD83)) to obtain a NORTHING and EASTING. While vertical surveys will use the North American Vertical Datum (NAVD) 1988 coordinate system for an ELEVATION as detailed in paragraphs 1 through 9 below. Providing survey data is not a substitute for other marking methods. Contractors are responsible for implementing other markings such as tracing wire or tape as required.
1) The actual location, materials and sizes within the construction area shall be measured and provided with a Northing, Easting and Elevation with respect to the proper datum as previously mentioned. These coordinates shall be shown for all change in direction for points such as T’s, Y’s, Elbows, etc. and all surface or underground components such as valves, manholes, drop inlets, clean outs, meters, etc. in order to provide the location of these lines and appurtenances which may be determined in the event the surface openings or indicators become covered over or obscured.
2) The descriptions of exterior utilities shall include the actual quantity, size, and material of the utility lines. The AS-BUILT drawings shall show dimensions to two permanently fixed surface features at the end of each run, including each change in direction. Valves, splice boxes and similar appurtenances shall be located by dimensioning along the utility run from a Northing, Easting, and Elevation point based upon the Pennsylvania (North) State Plane coordinate system (North American Datum 1983 (NAD83)).
3) There will be an allowable tolerance of one foot (1’-0”) in either direction (Vertical or Horizontal) for any and all utilities aforementioned.
4) The location and dimensions of any changes within the building structure.
5) Layout and schematic drawings of electrical circuits and piping.
6) Correct dimensions and details transferred from shop drawings.
7) Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans with a Northing, Easting and Elevation based upon the Pennsylvania (North) State Plane coordinate system (North American Datum 1983 (NAD83)).
8) Actual location of anchors, construction and control joints, etc., in concrete.
9) Changes in location of equipment and architectural features.