Contractor Cost Breakdown.xlsx
XLSX spreadsheet 36 KB Posted
- Attached to
- Range Front Gate - Fort Devens, MA
- Solicitation number
- W15QKN-26-Q-A145
About this file
This is a Contractor Cost Breakdown template form designed for federal construction contracting submissions. The spreadsheet provides a standardized framework for contractors to itemize and calculate all costs associated with a construction project, organized by labor, equipment, and materials components.
The template includes columns for detailed line-item descriptions specifying labor (with crew skill sets and manhours), equipment, and material types and grades, each with associated quantities and unit measures. Contractors must populate unit costs, apply city cost indices where applicable, and calculate total labor costs, equipment costs, and material costs for each line item. The form also includes separate line items for general contractor overhead, profit, bonding requirements, and general and administrative (G&A) costs, with a grand total field at the bottom. The template includes instructional notes defining key fields, such as "Unit Cost" representing the cost for one labor hour of a specified crew and "Total Labor Cost" calculated by multiplying unit cost by total hours. This cost breakdown form is referenced as Attachment 0003 in the solicitation for the Range Front Gate construction project at Fort Devens, Massachusetts, and serves as the required pricing submission format for this 100% service-disabled veteran-owned small business set-aside solicitation using lowest price technically acceptable (LPTA) evaluation methodology.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 26-Q-A145 - Solicitation Q_A.xlsx | XLSX spreadsheet | |
| Solicitation Amendment - W15QKN26QA1450001 SF30(Signed).pdf | ||
| DBA_WD_Massachusetts_MA20260001_Mod._No._1_Rev._Date_05.18.26.docx | DOCX document | |
| Solicitation - W15QKN26QA145 (Released).pdf | ||
| Range Control Front Gate Contract SOW (d. 06.30.2026).docx | DOCX document | |
| Range Front Gate Cost Breakout.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet2
| ID | Sort | Type | Description (to include labor,equipment, material type and grade) | Quantity | Unit Measure | Labor in Manhours | Equipment | Material | Total Cost | ||||||||
| Crew (skill set) | Labor Hours | Total Hrs | City Cost Index | Unit Cost* | Total Labor Cost* | Unit Cost | Total Equipment Cost | City Cost Index | Unit Cost | Total Material Cost |
Totals
GENERAL CONTRACTOR
| OVERHEAD | $ - 0 |
| $ - 0 | |
| PROFIT | $ - 0 |
| $ - 0 | |
| BOND | $ - 0 |
G & A $ - 0
GRAND TOTAL $ - 0
| Unit Cost* | Cost for one labor hour of the specified crew |
| Total Labor Cost* | "=Unit Cost x Total Hours" |
File details come from the government source that posted it. Updated .