Berm Update RG E_V Contract SOW - DRAFT.docx

DOCX document 40 KB Posted

Attached to
Upgrade Firing Berm at Victor & Echo Ranges - Fort Devens, MA
Solicitation number
W15QKN-25-R-A014
Issued by

About this file

This document is a Draft Statement of Work (SOW) for a Berm Update project at the Devens Reserve Forces Training Area (RFTA) in Massachusetts. The project involves constructing a 7-foot-wide berm extending from existing concrete firing emplacements on the South Post Range Complex Automated Record Firing Ranges (ARFR), addressing safety issues caused by ground erosion. Key requirements include creating a level berm with specific slope restrictions, installing six composite 4x4 posts at varying heights to serve as barricade holders, and performing site preparation, earthwork, hydro seeding, and site restoration.

The project is part of a pre-solicitation opportunity (Solicitation Number W15QKN-25-R-A014) issued by the U.S. Army Contracting Command - New Jersey. The expected period of performance is 365 days from award, with the government potentially setting aside the contract for HUBZone Small Businesses. The project aims to upgrade firing berm positions at Victor and Echo ranges, with a small business size standard of $19,000,000 under NAICS Code 238910. Contractors must submit capabilities statements by 12:00 p.m. EST on 3 April 2025 to the specified contract specialists, demonstrating their ability to complete the required construction services.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Live Fire Range Update

Statement of Work (SOW)

Project Title: Berm Update RG E, V Contract For: Devens RFTA, Massachusetts

1.0 Background: As the major Army Reserve presence in Massachusetts, Devens RFTA provides operational, training and logistic resources to tenant, transient training and stationed units and area customers; provides standardized, effective and efficient services, facilities, infrastructure and quality of life to Soldiers, Family Members, Retirees, and Civilian Employees as applicable to support the training, readiness and operational capability for all components and branches of the joint force accomplished through responsible execution of funds and effective conservation of natural resources.

1.1 Problem Statement: The firing berm emplacements on Devens RFTA South Post Range Complex Automated Record Firing Ranges (ARFR) has a cover over the last iteration of the Army ARFR firing pits. The ground around these covers have eroded away and caused gaps between the platform and the ground ranging from 1 foot to 3 feet. This gap causes a safety issue with soldiers climbing these platforms with weapons and ammunition.

2.0 Scope: This Statement of Work (SOW) requires the procurement of professional services to construct a 7-foot-wide berm extending to the left and right of the current concrete firing emplacements. This berm is to reach a height of the existing concrete to ensure a constant height across of the range. The top of the berm is to be level and have the sides of the berm not to exceed a seventeen (17) degree slope. Six (6) composite 4x4 posts need to be placed into the ground at a depth of four (4) feet with two (2) post extending twenty (20) inches above the berm and one (1) post extending fifty-four (54) inches above the berm and to act as a barricade holder to hold the required barricades on each side of the new berm construction.

3.0 Applicable Documents/References: Training Circular (TC) 25-8 - Ranges, TC 25-1 - Training Land, Department of the Army Pamphlet 385-63 - Range Safety, Army Regulation (AR) 350-19 - The Army Sustainable Range Program, AR 530-1 - Operations Security, Huntsville Corps of Engineer Range Design Manuals, and Devens RFTA Range Development Plan.

4.0 Tasks:

4.1 Task 1: Preconstruction:

4.1.1 Planning:

4.1.1.1 The Contractor shall conduct a site visit to determine the following:

4.1.1.1.1 Determine specific requirements for post/site access by Contractor and equipment.

4.1.1.1.2 Determine distance and accessibility of utilities.

4.1.1.1.3 Determine the required fill materials, amount of seeding required, and the distance of necessary barricade trench work required to cover all the ranges firing points.

4.1.3 The Contractor shall coordinate a site visit and kickoff meeting (Date TBD) within sixty (60) days after award to establish the project communication matrix in preparation for deliveries needed and a cohesive construction schedule to Range Control. This may be accomplished through field inspections, discussions with appropriate personnel, and by checking previous work.

4.1.4 The Contractor shall coordinate for and conduct a predesign meeting as determined during the kickoff meeting. The Contractor shall provide minutes of the site adaption/predesign meeting within seven (7) days after the meeting.

4.1.5 The Contractor shall provide construction schedule twenty-one (21) days prior to commencement of construction.

4.1.6 The Contractor shall coordinate and conduct a Pre-construction meeting NLT ten (10) days prior to the construction start.

4.2 Task 2: Construction: The Contractor shall provide the necessary professional services, all supervision, equipment, labor, tools, and furnish all materials, not provided by the Government, necessary to construct the target trenches and all necessary signage placement.

4.2.1 General Project Requirements: The major components of the project include:

4.2.1.1 Earthwork (clearing and grubbing as required)

4.2.1.2 Fill and aggregate

4.2.1.4 Composite 4x4 posts emplacement

4.2.1.5 Hydro seeding

4.2.1.6 Site restoration

4.2.2 Site Prep: The Contractor shall provide the necessary professional services, all supervision, equipment, labor, tools, and furnish all materials, not provided by the Government, necessary to prepare the site per the Government approved design.

4.2.2.1 Stormwater Pollution Prevention Plan (SWPPP): The Government will provide the Contractor with their Record of Environmental Consideration (REC) at the beginning of the proposal process to enable inclusion of SWPPP requirements. If required by the REC, the Contractor shall develop and implement a SWPPP in accordance with their general construction submittals. Best Management Practices (BMP) shall be applied for Stormwater Management by the Contractor.

4.2.3 Delivery: The Contractor shall notify the Government of the delivery of components constructed off-site ten (10) workdays prior to delivery date. The Government in conjunction with the Contractor shall collaborate on the delivery of the components. All deliveries shall be during normal business hours IAW paragraph 6.0 below.

4.2.4 Installation: The Contractor shall provide the necessary professional services, all supervision, equipment, labor, tools, and furnish all materials, not provided by the Government, necessary to construct the target trenches and all necessary signage placement.

4.2.5 Site Restoration: The Contractor shall provide the necessary professional services, all supervision, equipment, labor, tools, and furnish all materials, not provided by the Government, necessary to restore the construction site to preexisting conditions.

4.4 Task 4: Acceptance Phase:

4.4.1 Upon substantial completion of each range, the Contractor shall coordinate with the COR/OSCOR to schedule a range inspection of the range to ensure that all construction meets the required standards.

4.4.2 The Contractor, when complete shall coordinate with the COR/OSCOR ten (10) days prior and conduct a final acceptance of the range berms. As part of the transfer of responsibility, the Contractor shall assist the Government in completing the DD Form 1354.

5.0 Deliverables and Schedule of Items:

Deliverable/Paragraph Reference
Transmittal Form and Quantity
Schedule
Deliver To
Project Kickoff Meeting Para 4.1.3
Contractor format E-mail
NLT Sixty (60) Days post Task Order Award
COR/OSCOR
Pre-Design Conference Para 4.1.4
Contractor format E-mail
As Determined at Project Kickoff Meeting
COR/OSCOR
Construction Schedule Para 4.1.7
Contractor format E-mail
Twenty-one (21) Days Prior to

Commencement of Construction

COR/OSCOR

Pre-Construction Meeting Para 4.1.8
Contractor format E-mail
NLT Ten (10) Days prior to the

commencement of construction

COR/OSCOR

Meeting Minutes Para 4.1.3 and 4.1.4
Contractor format E-mail
Within seven (7) Days Post Project Kickoff Meeting
COR/OSCOR
Pre-final inspection Para 4.4.1
Contractor format E-mail
Ten (10) days prior to

Completion of Primary Construction

COR/OSCOR

Transfer of Responsibility and DD Form 1354 Completion Para 4.4.2

Contractor format E-mail
Upon Completion and Acceptance
COR/OSCOR

“As-built” Drawings Para 4.4.4

Contractor format E-mail
Forty-five (45) Days Post Government Acceptance
COR/OSCOR
Acceptance Letters Para 17.0
Contractor format E-mail
Upon completion of a SOV task/CLIN. The Government must sign Acceptance Letters within five (5) business days.
COR/OSCOR

6.0 Place of Performance and Hours of Operation:

6.1 Place of Performance. Tasks under this contract shall be performed at Government-owned facilities at Devens RFTA, MA.

6.2 Hours of Operations. The Contractor is permitted to work holidays and non-business hours as coordinated with COR/OSCOR.

7.0 Period of Performance (PoP): The POP shall be one (1) year from date of award.

8.0 Travel: N/A

9.0 Contractor Excluded Responsibilities:

9.1 Environmental Permits, to include a National Pollutant Discharge Elimination System Permit (NPDES), or the State’s equivalent, are not required by the Contractor.

9.2 Testing, handling, and disposal of any hazardous materials.

9.3 Considering the recommendation of the United States Army Engineering and Support Center, Huntsville, this Training Range Facility is exempt from Unified Facilities Criteria (UFC) 4-01001 Depart of Defense Antiterrorism (AT)/Force Protection (FP) requirements. If the Garrison Commander deems this facility requires UFC 4-010-01 AT/FP minimum standards, a modification to this SOW will be required and additional costs applied appropriately.

9.4 If the Garrison Commander and/or Installation Fire Marshal deem fire protection to be a requirement for the facility, a modification to this SOW will be required and additional costs applied appropriately.

10.0 Government Furnished Property (GFP) and Responsibilities: The Government will provide only the facilities, utilities, equipment, parts, supplies, and materials not delineated as furnished in the SOW described herein as GFP. GFP consists of Government-Furnished Facilities (GFF), Government-Furnished Utilities (GFU), Government-Furnished Equipment (GFE), Government-Furnished Materials (GFM), and Government Furnished Information (GFI).

10.1 The Government will not designate a borrow site for fill a material.

10.2 The Government will assist the Contractor with identification and protection of existing utilities.

10.3 The Government will ensure there are no unexploded ordnance (UXO) in the construction area.

10.4 The Government will provide the REC to the DPW environmental section as well as the contractors.

11.0 Reports:

11.1 The Contractor shall provide a Weekly Construction Report after the first day of construction until Government acceptance of the project.

11.2 The Government will review all reports and provide comments as needed within ten (10) calendar days. The Contractor shall incorporate Government comments and provide revised reports within ten (10) calendar days after receiving Government comments.

12.0 Hazardous Information: All areas within the project footprint and adjacent areas are currently active with military personnel. Range Control will deny non-contractor personnel access to the project area during all phases of construction. The Contractor shall remain vigilant with Range Control to work within the construction area to reduce impacts on training exercises. There is no requirement to handle any hazardous material.

13.0 Personnel:

13.1 If an employee is removed from the job site or dismissed from the premises, the Contractor is not relieved of the requirement to provide sufficient personnel to perform the services as required by this SOW. IAW 18 USC 1382 and AR 380-49, the authority of the Installation Commander to control and deny an employee entry to all or part of the installation is absolute. The individual concerned has no right to appeal.

13.2 All personnel must be able to read, write, speak, and comprehend the English language. The Contractor shall provide a workforce possessing the skills, knowledge, and training to satisfactorily perform the services required by this contract. Personnel performing work under this SOW shall not be considered employees of the Government.

14.0 Contracting Officer Representative (COR)/On-Site Contracting Officer Representative (OSCOR):

14.1 COR:

Name: Daniel Sanchez Address: 4260 Jackson Rd, Devens, MA 01434 Office: 978-615-6897 Email: Daniel.j.sanchez76.civ@army.mil

15.0 Security Requirements:

15.1 Employees selected for this SOW must be able to pass all security requirements IAW the Provost Marshall’s Policy to gain access to the installation.

15.2 All Contractors requiring access to Army installations shall complete AT Level I awareness training within thirty (30) calendar days after employee start date. Certificates of completion shall be submitted to the COR or to the KO. AT level I awareness training is available at http://jko.jten.mil/courses/atl1/launch.html.

15.3 All Contractor shall attend iWatch training. This training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within ten (10) calendar days of start of work. The iWatch training: http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx.

15.4 Per AR 530-1, the Contractor shall complete Level I OPSEC Awareness training available at https://securityawareness.usalearning.gov/opsec/. New employees must be trained within thirty (30) calendar days of their reporting for duty and annually thereafter.

16.0 Installation Access:

16.1 The Contractor shall be able to pass all security requirements IAW the Provost Marshall’s Policy to gain access to the installation.

16.2 The Contractor shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.

16.3 The Government will assist the Contractor with installation access however, it is the Contractor’s responsibility to gain lawful access to the installation IAW Provost Marshal’s policies.

17.0 Payment: Provide progress payment invoicing according to the Schedule of Values (SOV) which shall be submitted as indicated in the Purchase Order. The Government will review SOVs with the Contractor before Acceptance Letters are submitted. The Government will sign and return Acceptance Letters within five (5) business days to the Contractor IAW the SOVs and as the Government agrees that the work has been completed.

Devens RFTA, MAPage 1 of 12 Vehicle Recovery Site Bleacher Enclosure SOW
Devens RFTA, MAPage 1 of 12 Vehicle Recovery Site Bleacher Enclosure SOW
Devens RFTA, MAPage 1 of 12 Berm Update RG E, V Contract