Attachment 0013 - QA W15QKN24R0012 2024MAR18.docx
DOCX document 25 KB Posted
- Solicitation number
- W15QKN24R0012
About this file
This document is a set of Questions and Answers (Q&A) related to Solicitation W15QKN24R0012 for Armor Hardware, Turret Systems, and Platform Integration Kits. The solicitation is a 100% small business set-aside seeking proposals for armor hardware, such as Gunner Protection Kits, turret systems, and platform integration kits, including spare parts and special tooling. The government will make up to two awards with five one-year ordering periods. The Q&A addresses details about the evaluated quantities, proposal requirements, technical data package (TDP) contents, packaging, and availability of alternate suppliers. The government confirmed updates to the TDPs and clarified that disc labeling is not required, as proposals must be submitted electronically through the PIEE system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 0016 ATPD-2352 - PURCHASE DESCRIPTION TRANSPARENT ARMOR - REV T.pdf | ||
| Attachment 0015 QA W15QKN24R0012 2024APR12.docx | DOCX document | |
| W15QKN24R0012 Amendment 0004.pdf | ||
| W15QKNR0012 Amendment 0003.pdf | ||
| Attachment 0014 - QA W15QKN24R0012 2024APR01.docx | DOCX document | |
| Attachment 0009 - Technical Data Packages 20240328.docx | DOCX document | |
| Amendment W15QKN24R0012 00002.pdf | ||
| Attachment 0009 - Technical Data Packages 20240318.docx | DOCX document | |
| Attachment 0009 - Technical Data Packages 2024FEB27.docx | DOCX document | |
| Amendment W15QKN24R0012-0001.pdf | ||
| Attachment 0012 - QA W15QKN24R0012 2024MAR06.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers W15QKN24R0012
2024MAR18
Note: Original submitted questions have been reworded and revised to not divulge any potential proprietary information.
Question 1:
Will the Government publish the evaluated quantities for each CLIN and Ordering Period, and the formulae for how the weightings of the unit prices will be calculated?
Response: The evaluated quantities for each CLIN and ordering period will not be provided to industry.
Question 2:
Will the Government confirm that a proposal must respond to the actual CLIN items listed in the TDP packages, as compared to the list of items mentioned in the early description of the solicitation?
Context:
· A.1 Indicates that Offerors must “fulfill Government requirements for Armor Hardware, Turret Systems, and Platform Integration Kits…The turret system consists of hatch assembly, slew bearing and gear ring for tactical vehicles, interfacing with Gunner Protection Kits.”
· L.2.c.(i).(1) Directs offerors to “provide a detailed Manufacturing Plan for the production and testing of the Armor Hardware, Turret Systems, and PIK, (Attachment 009, Technical Data Packages, TDPs) kits, spare items and special tooling.” But the actual contents of Attachment 009 are the TDPs for: Objective Gunner Protection Kit (OGPK), CROWS Boresight KIT(BSK); Vehicle Integration KIT M153A2E1 M1A2; VIK KIT,Stryker ICV, CV, ICVV, CVV; and Javelin Interface Bracket (JIB). The TDPs do not include “Turret Systems” as described in A.1.
Response: Proposal pricing must respond to each CLIN listed in Attachment 0001. All proposals shall be based on the TDPs provided.
Question 3:
Why does the RFP mention the labeling of “each disc” but also state that the proposals must be submitted in electronic copies through PIEE, and that proposals that are mailed or hand-carried will not be evaluated?
Context:
· L.1.a: “Electronic copies of each volume shall be submitted through the Solicitation Module of the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/ . Proposals submitted by mail or hand-carried will not be evaluated…”
· L.2.b: “File Packaging. All of the proposal files shall be compressed (zipped) into one file entitled proposal zip, or as separate uploads in their native format, i.e. doc, xls, ppt, etc. Files shall be in read-only format, using PDF files. All price breakdown information to aide in the cost/price evaluation shall be submitted in Microsoft Office Excel Read/Write format and viewable in Microsoft Excel. Each disc shall be externally labeled with the volume number, date, and the Offerors name…”
Response: All files are to be submitted in accordance with Section L. No DISCs or hard copies will be accepted. Thus, disc labeling language is not required.
Question 4:
Will the Government confirm the revision number to which Offerors must propose the OGPK, transparent armor, part number 13014384?
· Context: The drawing for part number 13014384, Window, Large, shows the latest revision as Rev G. However, one of our transparent armor suppliers has shown us that the latest revision for this part number is Rev H.
Response: W15QKN24R0012 Attachment 0009 TECHNICAL DATA PACKAGES.zip has been updated to incorporate 13014384_RevH. Reference Amendment 0002 for further details. The TDP updates shall be sent out to all offerors who submitted complete TDP package requests. Initial complete TDP requests will automatically receive the updated TDP.
Question 5: Does the USG have an alternate supplier for the LBS-300-A2 Laser Boresight system?
Response: Part number 13043051 references two alternative suppliers in the table for the Laser Boresight System. The Government will not provide additional recommended/approved sources. Other sources of supply may be proposed in accordance with the solicitation requirements.
Question 6: Confirm if there are Special Packaging Instruction (SPI)s associated with CLIN 1000 OGPK, and if so, please clarify the RFP or TDP document where they are specified.
Context: Attachment 0001 Price Matrix, in tab “Production CLINs”, column G, rows (merged) 31-36, indicate a Y for SPIs. However, in reviewing the TDP for OGPK we find no DD Form 2169, JUN 97 Special Packaging Instruction.
Response: Reference Solicitation Amendment 0002. Attachment 0009 TECHNICAL DATA PACKAGES has been updated in incorporate the SPI’s. Updated TDP’s will be sent out to interested parties who have submitted completed TDP request documents.
Question 7: The following drawings are referenced and appear missing from the TDP’s.
Clin 1000 (Top Drawing: 13063370) 57K3214, 13064366, 12367450, 12484847, 12484861, 12484864, 12484848, 12484863, 13015468, 13015469, 13015470, 13015474, 13015477, 13015478, 13015480, 13015481, & 13015476
Clin 1002 (Top Drawing 13079108) 13307286
Response: Clin 1000 (Top Drawing: 13063370) 57K3214 - pg. 50 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13064366 - This is an “Installation Document” and is not relevant for this procurement effort. It is not required to be included with the 13063370 kit and the document will not be shared.
12367450 - pg. 43 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 12484847 - pg. 85 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 12484861 - pg. 93 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 12484864 - pg. 97 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 12484848 - pg. 98 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 12484863 - pg. 98 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015468 - pg. 60 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015469 - pg. 63 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015470 - pg. 64 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015474 - pg. 70 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015477 - pg. 73 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015478 - pg. 74 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015480 - pg. 75 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015481 - pg. 76 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf” 13015476 - pg. 81 of the file “OGPK TDP Binder_FEB-2024_update20240307.pdf”
Clin 1002 (Top Drawing 13079108) 13307286 – This part (from Higher Level Assembly 13072761 (Find Number 2)) is not required to be included with the 13079108 kit and the drawing will not be shared.
Question 8: Will the Government provide the incumbent details, contract value, and insights into the project's key challenges, priorities, and performance metrics.
Response: No additional information will be provided.