Questions.docx

DOCX document 13 KB Posted

Attached to
REFUSE AND RECYCLING SERVICES - Rotterdam, NY Federal contract opportunity
Solicitation number
W15QKN-22-Q-5129
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

View the file

Other files for this federal contract opportunity

Other files attached to REFUSE AND RECYCLING SERVICES - Rotterdam, NY, newest first.
File Type Posted
Questions.docx DOCX document
Solicitation Amendment - 22Q5129_0002.pdf PDF
PWS Rev. 1 - Refuse NY059 - Rotterdam - 8-22-2022.docx DOCX document
Solicitation Amendment - 22Q5129_0001.pdf PDF
Questions.docx DOCX document
W15QKN-22-Q-5129.pdf PDF
NY059_Dumpster Location Map.pdf PDF
PWS - Refuse NY059 - Rotterdam.docx DOCX document
WD 15-4143 (Rev. 22) 6-27-2022.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS & ANSWERS

W15QKN-22-Q-5129

Refuse and Recycling Services in Rotterdam, NY

August 12, 2022 Updated: August 15, 2022

Q1: What is the name of the Incumbent?

A1: The name of the incumbent Contractor is New Life Maintenance and Services.

Q2: What is the total Award amount of the Incumbent?

A2: The total Award amount of the incumbent contract is $43,620.00.

Q3: Would a 7 yard dumpster be acceptable?

A3: A 7 yard dumpster would not be acceptable, as the PWS states that an 8 cubic yard is required. This can be found in Section 5.2.1 "The government requires two 8 cubic yard dumpster one for refuse collection and one for Recyclables to be serviced once a week. The contractor shall notify the Government if the size of the containers stated above are inappropriate for the occupancy of the facility based on services provided during the period of performance."

Q4: Would a dumpster without a lid be acceptable?

A4: A dumpster with a lid is required.

Q5: When is the anticipated start date?

A5: The Anticipated Start date for this requirement is within the month of September 2022.

Q6: What will be going inside the (2) 8 cubic yard dumpsters?

A6: The Performance Work Statement, or PWS, can be found within the Solicitation. According to the PWS, Paragraphs 2.15 through 2.20 define the various materials that will be within the dumpsters. Paragraph 5.2.1 states that the two 8 cubic yards will be used separately, one for Refuse and one for Recycling, but both serviced once a week. Paragraph 2.16.1 states that Refuse is: "Is a category of solid waste. Refuse includes all garbage, ashes, debris, rubbish and other similar waste materials. Not included are explosive or incendiary wastes; recyclable materials; hazardous waste; and contaminated waste from medical or radiological processes". Paragraph 2.18 describes Recycling as: "Any material which can be recovered before final disposal, processed and marketed or used to make a new product".

Q7: What size do the 15 rolls offs need to be?

A7: 15 yard containers are needed; four (4) containers of each (metal and wood). The PWS States in Paragraph 5.2.2 "The government requires 15 yard roll off containers as needed for wood and metal disposal. 4 containers of each (metal and wood) per performance year. These containers will be requested by RFOS/COR as needed throughout each performance year”.