This document contains questions and answers related to a solicitation for the production of M19, M21, and M23 blasting cap assemblies. The solicitation is seeking proposals for the production, testing, packaging and delivery of the blasting cap assemblies over five ordering periods. Pricing will be evaluated based on the maximum order quantities listed in the solicitation. Foreign companies may be considered as sources for major components. Deviations from packaging requirements will not be permitted. The contractor will not be responsible for costs associated with initial design verification testing.

View the file

Other files

File Type Posted
W15QKN-20-R-0072-Amendment 0007.pdf PDF
W15QKN-20-R-0072-Amendment 0006.pdf PDF
Attachment 0024 Price Matrix updated.xlsx XLSX spreadsheet
Attachment 0025 Questions and Answers Amendment 0006.pdf PDF
W15QKN-20-R-0072 Amendment 0005.pdf PDF
Attachment 0025 Questions and Answers Amendment 0005.pdf PDF
W15QKN-20-R-0072 Amendment 0004.pdf PDF
Attachment 0025 Questions and Answers.pdf PDF
Attachment 0025 Questions and Answers for W15QKN-20-R-0072.pdf PDF
W15QKN-20-R-0072 Amendment 0003.pdf PDF
Attachment 0024 Price Matrix.xlsx XLSX spreadsheet
Attachment 0017 Contract Addendum - Quality Assurance Requirements Updated.docx DOCX document
W15QKN-20-R-0072 Amendment 0002.pdf PDF
W15QKN-20-R-0072 Amendment 0001.pdf PDF
Attachment 0009 Non-Disclosure Agreemnt (NDA) REVISED.pdf PDF
Attachment 0007 DD2345 Military Critical Technical Data Agreement.pdf PDF
Attachment 0011 How to Read DD 1423.pdf PDF
Attachment 0013 Image of Process Map.docx DOCX document
Attachment 0004.PDF PDF
Attachment 0008 AMSTA-AR 1350 Technical Data Questionaire.pdf PDF
Attachment 0023 OPSEC Plan Template.doc DOC document
Attachment 0017 Additional Solicitation and Contract Requirements.docx DOCX document
Attachment 0015 Small Business List.docx DOCX document
Exhibit A.zip ZIP file
Attachment 0016 SFAE-AMO Form 3002 Clearance of Techncial Information for Public Release.pdf PDF
Attachment 0017 CONTRACT ADDENDUM - Quality Assurance Requirements.docx DOCX document
Attachment 0012 Past Performance Questionnaire.docx DOCX document
Attachment 0010 Disclosure of Lobbying Activities No Restriction.pdf PDF
Attachment 0009 Non-Disclosure Agreement M19 M21 M23.pdf PDF
Attachment 0018 CDRL Distribution List.docx DOCX document
Attachment 0022 DoDM 5200.01 - Volume 4 (with Change 1).pdf PDF
Attachment 0020 DoDD 5230.25 (with Change 2).pdf PDF
W15QKN-20-R-0072.pdf PDF
Attachment 0021 DoDM 5100.76 (with Change 1).pdf PDF
Attachment 0014 Small Business Participation.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# Question Answer

Q&As added per Amendment 0003 1 In Section L-22.1.1.6, the solicitation asks for a description of required personnel training and certifications including x-ray skills.

From the performance specifications, there does not appear to be a reference to any x-ray requirements for these items. Please clarify if we need to include personnel training and certification related to x-ray skills.

Personnel training and certification related to x-ray is not required. However, offerors are encouraged to have x-ray skills available in case of any failures and their subsequent investigations.

2 I-109 (b), 52.209-3 FIRST ARTICLE APPROVAL -- CONTRACTOR TESTING (p.55). What is the correct due date for the first article test report? This paragraph states “30 calendar days from the date of this contract”. Section A, Supplemental Information, states “FAT Delivery – 360 days after contract award”.

The First Article Test report is due 360 days after contract award. I-109 (b) will be updated.

3 L-22.2.2 (3) Section 3 Subcontracts (p.104). Please clarify what information is required in Past Performance Volume II, Section 3 Subcontracts. The data specified does not appear to align with past performance data

As stated in the solicitation “The information provided for the prime Offeror and each proposed major subcontractor must include the entire company name, company address, CAGE Code, DUNS Number and type of work to be performed by citing the applicable solicitation requirement.”

4 L-22.4.2 (p.105). Please confirm that the calculation of the total contract price (for small business participation) is correct. Per the instructions, “the total contract price is determined by adding the unit price for a single M19, M21, M23, and FAT costs from each ordering period at the max quantity range price, which is the estimated maximum number of assemblies to be purchased on this contract.”

Yes, the calculation of SB Participation is based on the max contract price.

5 M-5.4 (P. 113) – The price computation chart demonstrating how the total evaluated price will be calculated was not included. Can you provide this chart?

A Price Matrix will be added as Attachment 0024.

6 Please clarify what the requirements are for CDRL A025 Management Plan, Process Capability, Control, and Improvement (PCCI). Block 5, Contract Reference, on CDRL A025 specifies “Section J, QA Requirement 31” which we were unable to locate.

There was no reference to PCCI in the scope of work (section C of solicitation W15QKN-20-R-0072) or the Quality Assurance Requirements (Attachment 17 Contract Addendum).

Attachment 0017 will be amended to reflect QA Requirement 31.

Q&As added per Amendment 0004 7 The price matrix provided in Amendment 0003 did not include any weighting or formula showing how this will be calculated. Can you provide the price computation chart that demonstrates how the total evaluated price will be calculated?

Refer to Section M 5.3 of the Solicitation which discusses how pricing will be calculated. Weighting shall not be provided.

8 Can a foreign company be the source for a major component? There are no NTIB restrictions.

Q&As added per Amendment 0005

9 Reference packaging requirements in QAA-1431B Section 5. Is it permissible to deviate from the outer pack and over pack inner dimensions as long as all other packaging requirements are met?

No, it is not permissible to deviate from the outer pack and over pack inner dimensions as long as all other packaging requirements are met.

10 Section 5.1.3.1 of Document QAA1431B and QAA1430H, the US Government calls out the following:

Outer Pack Box requirement of a 2 piece, SFF (Special Full Flap) FTC (Full Telescoping Container), V3C weather resistant corrugated fiberboard conforming to ASTM DM5118.

After recent communications with our experienced, US Government packaging suppliers, it is not typical for a Full Telescoping Container to have flaps (this would be a custom item). Can you confirm that the

This is to confirm that the OUTER PACK BOXES specified in the Solicitation require both SFF and to be

FTC.

required OUTER PACK BOXES for this Solicitation requires both SFF and to be FTC?

Q&As added per Amendment 0006

11 The M21 quantity ranges listed in Section B of the Solicitation contradict what is listed in the ATTACHMENT 24-Pricing Sheet under ordering period 3, 4 and 5. Additionally, the M23 quantity ranges listed in Section B of the Solicitation contradict what is listed in ATTACHMNET 24-Pricing Sheet under ordering period 4 and 5.

Please advise which quantity ranges are applicable for pricing purposes.

The quantities in the Solicitation are applicable for pricing purposes. Attachment 0024 Price Matrix has been revised to match the Solicitation.

Q&As added per Amendment 0007

12 Can you confirm that the Contractor is not responsible for the DVT test costs?

The Contractor will not be responsible for the test costs of the initial Design Verification Test (DVT), on CLIN 0001, CLIN 0006 and CLIN 0011.