REPAIRS TO TANK SYSTEMPRICE WORKSHEET
CW2 KERRY P. HEIN USARC
NY058 CSS6292
SHOREHAM, NY 11786-2104
IDSortTypeQuantityUnit MeasureMaterial
Total HrsCity Cost IndexCostCity Cost IndexBare Material CostTotal
Remove sludge, water and remaining product from tank bottom with vacuum truck - tank 13 -3000 to 5000 gal tank1.00Ea152.7%100.30%
Transfer liquids - Tank 13 to Tanks 15 & 15 - 25% capacity500.00Gal152.7%100.30%
Dispose of sludge off site - 10% tank capacity (est)200.00Gal152.7%100.30%
Valve, Ball, brnze/brass 3/4" threaded (for 1" hole)3.00Ea152.7%100.30%
Clear brush by hand40.00SY152.7%100.30%
Prep for paint, existing exterior metal surface1,200.00SF152.7%100.30%
Exterior epoxy primer1,200.00SF152.7%100.30%
Exterior Epoxy intermediate and top coat2,400.00SF152.7%100.30%
Valve, ball, bronze/brass 2"2.00Ea152.7%100.30%
Remote tank monitoring system - head unit & magnorestrictive level probes per tank2.00Ea152.7%100.30%
Manhole, prescast with iron racks and pulling irons, c.i. frame 4'x6'x7' deep1.00Ea152.7%100.30%
Excavating - bulk bank measure13.00BCY152.7%100.30%
Excavating - minimum labor/equipment charge1.00Job152.7%100.30%
General Purpose Laborer - Average3.00WK152.7%100.30%
Project Manager - Average1.00WK152.7%100.30%
Cleanup Daily4.00MSF152.7%100.30%
Cleanup Final 1%1.00Job152.7%100.30%
152.7%100.30%
152.7%100.30%
152.7%100.30%
Totals
COST
OVERHEAD
PROFIT
G&A
GRAND TOTAL