This document is a Performance Work Statement (PWS) for Vertical Transportation Equipment (VTE) Maintenance, Repair, and Inspection Services at Travis Air Force Base, CA.

The PWS outlines the requirements for a full-service maintenance and repair contract for VTE including freight and passenger elevators, wheelchair lifts, and dumbwaiters. Key details include:

  • Contractor shall provide all personnel, equipment, supplies, and services to perform preventive maintenance, repairs, and emergency services on the VTE in accordance with ASME elevator codes and manufacturer requirements.
  • The contractor is required to develop and submit a Maintenance Control Plan, provide monthly service reports, and support annual inspections and testing.
  • The contractor shall respond to routine service calls within 24 hours and emergency calls within 1 hour.
  • Over and above work, such as alterations/modernizations, vandalism repairs, and work over $20,000, requires approval from the Contracting Officer's Representative.
  • The contract period is for 1 base year with 4 option years.

The related federal contract opportunity solicits for these VTE maintenance and repair services at Travis AFB.

View the file

Other files for this federal contract opportunity

Other files attached to Vertical Transportation Equipment (VTE) Maintenance, newest first.
File Type Posted
Elevator Pictures.pdf PDF
Questions and Answers - VTE (current as of 21 June 2024).xlsx XLSX spreadsheet
Questions and Answers - VTE.xlsx XLSX spreadsheet
VTE Combo.pdf PDF
Equipment List 19 Oct 23.pdf PDF
Wage Determination.pdf PDF
Elevator Map 20231212.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

FOR

VERTICAL TRANSPORTATION EQUIPMENT

MAINTENANCE, REPAIR & INSPECTION

SERVICES

TRAVIS AFB, CA

PERFORMANCE WORK STATEMENT (PWS) FOR

VERTICAL TRANSPORTATION EQUIPMENT MAINTENANCE, REPAIR, &

INSPECTION SERVICES

PART 1

This is a non-personal services contract to provide Vertical Transportation Equipment (VTE) Maintenance and Repair Services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn, is responsible to the Government.

1.1. Description of Services/Introduction: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform full- service maintenance and repair services tailored to VTE at Travis Air Force Base (TAFB), CA. This work is defined in this Performance Work Statement (PWS) Part 5 and is to be performed on equipment from various manufacturers and of different age and condition.

Work shall be completed in a manner that will ensure continuous and safe operation of the VTE. The term “VTE” in this PWS includes all equipment listed in Technical Exhibits (TE’s) #1 (e.g., freight and passenger elevators, wheelchair lifts, and dumbwaiters).

1.2. Objectives: The objective of this contract is to provide complete and full preventive maintenance and repair services on VTE at TAFB. Preventive maintenance includes, but is not limited to, regular cleaning, all inspections, testing, routine service, and maintenance in accordance with all American Society of Mechanical Engineers (ASME) elevator codes to include but not limited to A17.1, A17.2, A17.3, A17.5, A17.6, and A18.1, and manufacturer’s recommendations and requirements. All work not specifically mentioned, which is required to ensure that maintenance and repairs are complete and are within the intent of this contract, shall be performed without additional cost. Contractor shall perform, coordinate, and complete the requirements of the contract in cooperation with any other Contractors or trades performing work at TAFB promptly and diligently as required by the standards of this contract.

1.3. Scope: Contractor shall provide required maintenance and servicing of equipment. Routine service shall consist of, but not limited to, examining, adjusting, cleaning, and lubricating the equipment. All lubrication frequencies and types of lubricants will meet manufacturer’s specifications. The Contractor shall prepare and submit a report to the Contracting Officer’s Representative (COR) within five (5) business days of the service(s) performed along with all findings. The report shall identify each unit of equipment, the location, work performed, repairs needed, date of inspection/service, name of technician, and overall condition of the equipment. If repairs require work considered above routine maintenance work, the Contractor shall notify the COR for appropriate decision and action.

1.4. General Information:

1.4.1. Hours of Operation: Normal working hours for routine maintenance and repair is between 07:00-16:00 Monday through Friday. The Contractor shall at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when a Government facility is not closed for the above reasons.

1.4.2. The Contractor shall be available to provide Emergency service and repairs 24 hrs. per day, seven (7) days a week as required by the Government and have at least five (5) satisfactory contracts operating under its’ name. The Contractor shall provide a full-time Certified Competent Conveyance Mechanic (CCCM) with at least 10 years of experience residing within 30 miles of Travis AFB with a service route which includes more than 50% of his/her work within Solano County to ensure availability in emergency situations. In addition, the Contractor shall have a parts inventory warehouse valued at $50,000 or more in accordance with industry standards within 50 miles from Travis AFB where inventory is readily available for emergency elevator repairs.

1.4.3. Place of Performance: The work to be performed under this contract will be performed at the locations listed in TE #1.

1.4.4. Quality Control Program (QCP): The Contractor shall develop and maintain an effective QCP to ensure services are performed in accordance with (IAW) this PWS. The QCP must be forwarded to and accepted by the COR. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of deficiencies. The QCP shall be delivered to the Contracting Officer (CO) and COR by e-mail within ten (10) business days after contract award. Any changes made thereafter shall be submitted to the COR by e-mail within five (5) business days. After acceptance of the initial QCP, the Contractor will receive the COR’s acceptance in writing of any proposed change to the QCP. Upon request, the Contractor shall provide the COR copies of its Quality Control documentation.

1.4.5. Quality Assurance: The Government will evaluate the Contractor's performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP).

1.4.6. Post-Award Conference/Periodic Progress Meetings: The Contractor shall attend all post-award conferences in person when required by the contracting activity or contract administration office IAW Federal Acquisition Regulation (FAR) Subpart 42.5. The CO, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings, the CO will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of any problems. The parties will take appropriate action to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.4.7. Schedule coordination. The contractor shall be responsible for coordinating all phases of his/her operations with the appropriate base personnel through the CO/COR. The facilities shall remain in operation while the Contractor is working, and it is up to the Contractor to coordinate around the normal activities of the facility.

1.5. Security Requirements:

1.5.1. Physical Security: The Contractor shall safeguard all Government equipment, information and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.

1.5.2. Key Control: The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The contractor shall immediately report any occurrences of lost or duplicate keys to the COR.

1.5.2.1. In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the CO or COR, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment(s) due the Contractor.

1.5.2.2. The Contractor shall prohibit the use of Government issued keys by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the CO or COR.

1.6. Environmental control.

1.6.1. The Contractor shall comply, and assure that all subcontractors comply, with all applicable federal, state, and local laws, regulations, ordinances, policies, and all other standards related to environmental matters. Where applicable, the Contractor shall use environmentally safe products to accomplish all project requirements. The Contractor shall maintain, in company vehicle on site, Material Safety Data Sheets (MSDS) for all chemicals. A copy of all MSDS will be provided to the CO/COR. The MSDS data is subject to random checks by the Government. Contractor shall maintain, and provide on demand, an inventory of materials being brought into the Government facilities/installation. The Contractor shall complete, and provide on demand, monthly inventories of hazardous material (HAZMAT) used, including but not limited to solvents, paints, degreasers, Ozone Depleting Substances, Petroliam, Oils, and Lubricants brought on the Government Installation and facilities. Should the Contractor spills or releases any HAZMAT or other substance contained in 40 CFR 302 into the environment, the Contractor shall immediately notify the CO/COR and appropriate emergency responders. The Contractor is responsible for all costs associated with clean-up and restoration, including any applicable Federal, State, and or Local fines and/or penalties. The Contractor shall maintain a spill plan as required by Federal, State, and Local laws and regulations

1.6.2. ASBESTOS. The Contractor shall comply with Section 29 CFR 1910.1001(j) (7) (IV).

VTE may be in facilities that may contain ACM or PACM. The Contractor shall determine if any exposure to ACM may result in performing work under the contract.

PART 2

CONTRACTOR-FURNISHED ITEMS AND SERVICES

2.1. General: The Contractor shall furnish all supplies, equipment, facilities, and services required to perform work under this contract that are not listed under Part 2 of this PWS.

2.2. Materials: The Contractor shall furnish all materials, supplies, and equipment necessary to meet the requirements under this PWS. Materials shall be New and of at least equivalent material, strength, and design, as specified in ASME A17.1. and the equipment manufacturer. The Contractor shall ensure that all parts are New and warranted against defects or failure for a minimum period of one (1) year. The Contractor shall immediately replace any new or replaced part that fails within one (1) year after installation, including labor, at no additional cost to the Government. Should the Contractor not be able to acquire New Parts due to discontinued equipment, the contractor shall receive written approval from CO/COR prior to installing refurbished parts.

2.3. Parts: The Contractor shall notify and coordinate with the COR when parts are not available. The Contractor shall provide the following information: parts required, estimated time of parts arrival, and the estimated completion time of the repair.

PART 3

SPECIFIC

TASKS

3.1 Key Personnel: The Contractor shall provide a Contract Manager who shall be responsible for the performance of the work. The name of this person and an alternate, who shall act for the Contractor when the manager is absent, shall be designated in writing to the CO and the COR. The Contract Manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Contract Manager or alternate shall be available by phone during the hours of operation, as described in PWS paragraph 3.5. The Contractor shall provide the name of the Contract Manager and alternate to the CO and COR via email within five (5) business days of contract start and within five (5) business days as changes to key personnel are made.

3.2 Basic Services.

3.2.1 This full-service maintenance and repair contract signifies that the Contractor takes total service responsibility for the equipment identified in the contract. This work will be performed on equipment from various manufacturers and includes traction, hydraulic, roped hydraulic, and screw drive units. Except those services covered in PWS paragraph 3.3 below, the monthly fixed price includes all maintenance, repairs, replacements, routine and emergency service calls, and monthly firefighters’ emergency operation (FFEO) testing. This contract allows the Government to budget total yearly costs and eliminates concerns relating to individual parts repair or replacement invoicing.

The Contractor assumes all responsibility and determines the amount of service visits and types of service required to keep the VTE operating safely and within the requirements of the applicable ASME A17 codes, manufacturer’s recommendations/requirements.

3.2.2 Work conducted on VTE will be IAW ASME A17.1, Safety Code for Elevators and Escalators (applicable to the code year for each VTE and those sections which retroactively apply with each new code version), ANSI/ASME A17.2, Guide for Inspection of Elevators, Escalators, and Moving Walks (most current edition), A17.3, Safety Code for Existing Elevators and Escalators (most current edition), A17.5, Elevator and Escalator Electrical Equipment (applicable edition), A17.6, Standard for Elevator Suspension, Compensation, and Governor Systems (applicable edition), UFC 3-490-06, Elevators (applicable edition), National Fire Protection Association Standards (NFPA) (applicable edition), Unified Facilities Criteria (UFC) 3-600-01, Fire Protection Engineering for Facilities (applicable edition), Occupational Safety and Health Administration (OSHA) Standards, International Building Code (IBC) (applicable edition), and the recommendations/requirements of the original equipment manufacturer (OEM).

3.2.3 Remote communications and/or modem troubleshooting with VTE is NOT allowed.

3.2.4 Any part, component, or assembly unavailable from the manufacturer due to discontinuation, remains the Contractor’s responsibility to obtain an engineered equivalent product from a commercial source with CO and COR approval.

3.3 Excluded Services/Over and Above Work: Repairs shall be treated and billed by the Contractor as full-service maintenance and repair unless otherwise approved by the COR. All Over and Above repairs shall be executed in a timely manner according to specifications and regulations. The following are not considered full-service maintenance and repair and are therefore excluded (i.e., Over and Above) work:

3.3.1 Alterations (a.k.a. modernizations): An alteration on existing VTE is not included under full-service maintenance and repair. Alteration/modernization are considered excluded services. The typical alteration results in a betterment to the safe operation of the equipment. In the case of elevators, when an alteration is made, all affected safety requirements shall be complied with. All work as part of an alteration shall comply with specific requirements of the current ASME A17.1 Code edition. See ASME A17.1 for requirements.

3.3.2 Acts by parties other than the Contractor of vandalism, abuse, negligence, damage resulting from rescue and recovery operations, and acts of God (including damage resulting from emergency power generator power spikes and low quality).

3.3.3 Additional items are: cosmetic, construction, finishing, repairing or replacement of the machine room door and frames, main power breaker(s), hydraulic elevator jack outer housing, buried piping, main communication feeders to controller, security systems, air conditioners, and heaters.

3.3.4 Routine cleaning of the non-mechanical interior of cars and the exterior of the hoistway doors and frames.

3.3.5 Any single repair (one repair per one VTE including all labor and materials) over $20,000 requires coordination with CO/COR and approval by CO/COR.

3.3.6 Replacing missing items and accomplishing repairs as per PWS paragraph 3.4.1, Condition

Assessment.

3.3.7 If the Contractor encounters an item of work included in PWS paragraph 3.3.1 through 3.3.5, the Contractor shall report the situation to the COR via email within two (2) business days. The report shall include the work location, a detailed scope of the required work, and justification for Contractor determination that the work is not included under full-service maintenance and repair, and an itemized cost estimate. The itemized cost estimate shall include the time to repair, a breakdown of all labor hours and categories, all required parts, and documentation to validate the cost of all required material and parts. No mark- ups are allowed on the cost of the labor or parts. Over and Above work shall not commence until approval from CO/COR is issued for the work. NOTE: Any part, component, or assembly unavailable from the manufacturer due to discontinuation, remains the Contractor’s responsibility to obtain an engineered equivalent product from a commercial source.

3.4 Full-Service Maintenance and Repair.

3.4.1 Condition Assessment. The Contractor, along with the COR, shall determine the working order and condition of all VTE listed in TE’s #1. The Government will either replace non-VTE system related missing items (e.g. , machine room fire extinguisher), repair non-VTE system items not in working order or serviceable condition (e.g. , smoke detector), or issue a Task Order(s) directing the Contractor to replace the missing item(s) and/or accomplish the repair(s). The COR will give instructions for situations where a unit requires a level of repair potentially constituting an alteration as described by PWS paragraph 3.3.1 and ASME A17.1. The Contractor and the COR shall certify their agreement as to the working order of the VTE. If the Government elects to direct the Contractor to perform the work, it will be considered excluded work (as per PWS paragraph 3.3.6. above) and the Government and Contractor will negotiate the additional effort (including the timeframe and effective date) and the CO will issue a Task Order accordingly. All repair work shall be IAW standard commercial practices using only new parts of equal quality, specified by the VTE manufacturer in effecting repairs (substitution of a different component is only permitted where it is equivalent to that which was tested, as determined by the certifying agency and approved by the CO or COR). The condition assessment will be performed at the beginning of the contract to all VTE. All VTE added to the contract after award shall have a condition assessment performed within ten (10) business days after the Contractor is notified of the new VTE.

3.4.2 Maintenance Control Plan (MCP). The Contractor shall develop and submit to the Government an annual written MCP for each unit of VTE. The MCP shall meet the requirements of ASME A17.1, Section 8.6, and shall include an inspection and maintenance service checklist and a schedule showing what months preventive maintenance will be performed. All VTE shall be serviced Monthly a n d i n s p e c t e d I A W ASME A17.1, Section 8.6, the MCP will not be generic in nature, but be unit specific and be based on:

a. Equipment age, condition, and accumulated wear.

b. Design and inherent quality of the equipment.

c. Usage.

d. Environmental conditions.

e. Improved technology.

f. The manufacturer’s recommendations and original equipment certifications for and SIL rated devices or circuits.

g. The manufacturer’s recommendations based on any ASME A17.7 approved components or functions.

The Contractor shall perform inspections and maintenance of all VTE IAW the MCP. The MCP shall ensure compliance with all minimum DoD, ASME, and other code requirements, and be IAW manufacturer specifications of material, procedure, schedule, and documentation. The MCPs shall be submitted to the COR via email and placed in the machine room within 20 business days after start of contract, within ten (10) business days after the start of each contract option period, and within ten (10) business days of changes to orthe addition of VTE. The Contractor shall post the completed MCP report on or near each elevator or in the elevator machine room in a clear document protector or similar item that protects the reports.

3.4.3 The Contractor shall perform maintenance IAW the MCP to ensure reliable and continuous safe operation. The MCP is required to specify appropriate intervals for specific maintenance items.

The Contractor shall perform monthly firefighters’ emergency operation (FFEO) testing IAW ASME A17.1 on all applicable units.

3.4.4 Cleaning of equipment spaces and daily cleanup of job sites in conjunction with maintenance, inspections, testing, and repairs are required. The Contractor shall also be responsible for disposing of hydraulic oil/waste and other waste from maintenance and repair operations.

3.4.5 The Contractor’s maintenance services shall include periodic cleaning and repair of building items such as the hoist-way, pit, car top, machine room walls and floors, painting of all exposed elevator machinery, re- lamping of signal fixtures, position indicators, and car enclosures, sills, emergency telephone equipment, signal fixture faceplates, intercom communication equipment, car and pit light fixtures, cart and pit outlets if any, main power switches, smoke and fire sensors as well as replacement of consumable parts. If during the course of maintenance, a unit is taken out of service, the Contractor shall notify the COR by phone or email within one (1) hour.

3.4.6 The Government may perform inspections of the VTE with the assistance of the contractor at no additional cost to the Government for purposes of capital asset management and quality assurance. If discrepancies are discovered during these inspections, the Contractor will be notified in writing of any determination and shall be responsible for the corrective actions unless excluded by PWS paragraph 5.3. The Contractor shall also support other TAFB personnel and Contractors who require access to VTE spaces for maintenance/repairs at no additional cost to the Government.

3.4.7 The Contractor shall prepare and submit a service report to the COR via email once per week (Monday). The report shall identify dates and times of maintenance or service calls, the locations of the VTE, the work performed, a list of all materials provided for maintenance and/or repairs, name of the technician(s) performing maintenance and/or repairs, and the overall condition of the VTE.

3.4.8 Annual Fire Alarm Testing.

3.4.8.1 The Contractor shall provide and ensure availability of a technician to provide access to fire alarm equipment located in the hoist-way and machine room during annual fire alarm testing and certification, and to test and reset firefighter recall operations. The Contractor shall provide adequate personnel to ensure that regular maintenance and response to service requests (callbacks) continue during this testing.

3.4.8.2 The Government will provide notice at least two (2) weeks in advance as to when the fire alarm testing will be conducted.

3.4.9 Annual (CAT-1), Three-Year (CAT-3), and Five-Year (CAT-5) Testing.

3.4.9.1 The contractor shall provide personnel and equipment to support a third party (non-company affiliated) ASME QEI-1 certified inspector during the performance of the CAT-1, CAT-3, and CAT-5 safety inspection and/or after major repairs to each elevator. The independent third-party elevator ASME QEI-1 Certified inspector/certifier company shall perform certification inspections and tests as required by all applicable federal guidelines and regulations. The third-party certification/testing company shall have no affiliation to the Prime Maintenance Contractor nor personal ties to the Prime Maintenance Contractor’s management personnel. Should there be a personal tie between the Prime Maintenance Contractor and the third-party certification/testing company, the Prime Maintenance Contract shall notify the CO/COR in writing within ten (10) business days prior to inspection.The Prime Maintenance Contractor shall provide a copy of proof of all maintenance/inspections for the elevator inspector in advance, two (2) business days to the COR in which this document will be kept with the contract file before the start of the annual safety inspection and/or inspections after major repairs to each elevator. Under normal conditions, the governor shall be hand tripped with no load to set the safeties, however, if the hoisting ropes or the governor ropes are replaced after the inspection, a full load safety test shall be required, and the contractor shall provide the test weights and handling personnel. All maintenance deficiencies noted during the safety inspection and test shall be corrected by the contractor prior to certification of the elevators.

3.4.9.2 The Contractor shall provide and ensure availability of support personnel, weights, and all equipment necessary to perform annual (CAT-1, three-year (CAT-3) and five-year (CAT-5) testing, as specified in ASME A17.1, A17.2, and A18.1. The Contractor shall provide adequate personnel to ensure that regular maintenance and response to service requests (callbacks) continue during this testing. The first annual (CAT-1) test shall include the five-year (CAT-5) test regardless of due date. The three-year (CAT-3) test shall be scheduled in conjunction with the annual test two years later (OY2) from the first annual test.

3.5 Service Requests (Callbacks): The Contractor shall provide service requests (routine and emergency) under full-service maintenance and repair at no additional cost to the Government. All repair work shall be done IAW standard commercial practices, manufacturer’s recommendations and ASME A17 requirements. The Contractor shall repair and replace components of the VTE at no additional cost to the Government unless the repair meets the exemptions in paragraph 5.3. When a component in a labeled product is replaced, it must be replaced with an identical component manufactured under the original labeling service (certifying agency) unless previously approved by the CO/COR for upgrade purposes or inability of original parts/components. Substitution of a different component is only permitted where it is equivalent to that which was tested, as determined by the certifying agency. The parts used for replacement are required to comply with all the requirements that the old parts originally complied with.

If when performing a service request a unit is taken out of service, the Contractor shall notify the COR by phone or email within one (1) hour.

3.5.1 Routine Calls: Service calls will be classified as routine when the work or repair does not qualify as an emergency call.

3.5.1.1 The Contractor shall respond in-person to the VTE and begin work on routine service calls during normal duty hours with a response time of 24 hours or less, measured from the time of initial Government- to-Contractor verbal contact until the Contractor arrives at the facility where the VTE is located. Before starting work at any site, the contractor will make the facility manager (FM) or section manager (SM) and the COR aware that the contractor will be working in that building/area. Overtime shall not be authorized for routine service calls. If after troubleshooting, it becomes apparent that the work is considered Over & Above work, the Contractor shall indicate the hours and labor costs of the associated troubleshooting on the VTE report and subsequent proposal for repair. NOTE: Repair work cannot commence until the Contractor is issued a Task Order for this work from the CO or COR. The work is considered complete when the VTE is placed back into service. If the Contractor is unable to gain access to the facility, the assigned technician shall phone the COR and receive further instructions.

3.5.2 Emergency Calls: Emergency calls are defined as calls made for service when there is an entrapment, a VTE system fails and constitutes a danger to personnel or property, threatens to disrupt major unit activity, operations, or training missions. Emergency calls shall be responded to 24/7 including federal holidays and weekends.

3.5.2.1 The Contractor shall respond in-person to emergency calls within one (1) hour or less, measured from the time of initial Government-to-Contractor verbal contact until the Contractor arrives at the facility where the VTE is located. Before starting work at any site, the contractor will make the facility manager (FM) or section manager (SM) and the COR aware that the contractor will be working in that building. If after troubleshooting, it becomes apparent that the work is considered Over & Above work, the Contractor shall indicate the hours and labor costs of the associated troubleshooting on the VTE report and subsequent proposal for repair. NOTE:

Repair work cannot commence until the Contractor is issued a Task Order for this work from the CO or COR except when the emergency work is to save a live or to prevent further damage to equipment or other facility systems/structure. The work is considered complete when the VTE is placed back into service.

3.6 Schedule Coordination: The Contractor shall be responsible for coordinating all phases of its operations with the appropriate base personnel or through the COR. The facilities shall remain in operation while the Contractor is working, and it is the Contractor’s responsibility to coordinate around the normal activities of the facility.

3.6.1 Before starting work at any site, the contractor will make the facility manager (FM) or section manager (SM) and the COR aware that the contractor will be working in that building/area.

3.6.2 Some facilities will require an escort to enter the building or to access the VTE equipment. The facilities that require prior coordination will be identified at the time of award.

3.7 Reporting: All reports shall meet the specifications provided in the PWS and TE #2- Deliverables List. All reports shall be submitted as Microsoft Office or Adobe compatible. Any identified required revisions shall be corrected within three (3) business days.

3.7.1 Maintenance Control Plan (MCP): The Contractor shall submit an MCP as specified in paragraph 3.4.2.

3.7.2 Service Report: The Contractor shall submit service reports as specified in paragraph 3.4.7.

3.7.3 Condition Assessment Report: The Contractor shall prepare and submit to the COR a written condition assessment report as specified in paragraph 3.4.1.

3.7.4 Over and Above Work Request: The Contractor shall prepare and submit to the COR a written request for Over and Above Work as specified in paragraph 3.3.7.

PART 4

APPLICABLE PUBLICATIONS

4. APPLICABLE PUBLICATIONS (CURRENT EDITIONS): The Contractor shall abide by all applicable regulations, publications, manuals, and local policies and procedures including those listed elsewhere in this PWS and those listed below.

4.1. The Contractor shall abide by all applicable regulations, publications, manuals, and local policies and procedures. Any Contractor-provided publications are to be procured and maintained at the Contractor’s expense. The appropriate edition of each publication shall be used:

a. American Society of Mechanical Engineers (ASME):

(1) ASME A17.1, Safety Code for Elevators and Escalators.

(2) ASME A17.2, Guide for Inspection of Elevators, Escalators, and Moving Walks.

(3) ASME A17.3, Safety Code for Existing Elevators and Escalators.

(4) ASME A17.5, Elevator and Escalator Electrical Equipment.

(5) ASME A17.6, Standard for Elevator Suspension, Compensation, and Governor Systems.

(6) ASME A18.1, Safety Standard for Platform Lifts and Stairway Chairlifts.

(7) ASME QEI-1, Standard for the Qualification of Elevator Inspectors.

b. American Society for Testing and Materials (ASTM):

(1) ASTM A 167, Stainless Heat Resistant Chromium-Stainless Steel Plate, Sheet, and Strip.

(2) ASTM A 366, Steel, Carbon, Cold-Rolled Sheet, Commercial Quality.

c. International Code Council (ICC).

(1) International Building Code (IBC).

(2) International Plumbing Code (IPC).

d. National Fire Protection Association (NFPA).

(1) NFPA 13, Standard for the Installation of Sprinkler Systems.

(2) NFPA 70, National Electrical Code.

(3) NFPA 101, Life Safety Code.

e. Unified Facilities Code (UFC)

(1) UFC 1-200-01, DoD Building Code.

(2) UFC 3-101-01, Architecture.

(3) UFC 3-301-01, Structural Engineering.

(4) UFC 3-310-04, Seismic Design for Buildings.

(5) UFC 3-401-01, Mechanical Engineering.

(6) UFC 3-490-06, Elevators.

(7) UFC 3-501-01, Electrical Engineering.

(8) UFC 3-600-01, Fire Protection Engineering for Facilities.

(9) UFC 4-010-06, Cybersecurity of Facility-Related Control Systems.

f. United States Department of Defense (DoD).

(1) ADA Accessibility Standard for Department of Defense Facilities.

(2) DEPSECDEF Memorandum, Subject: Access for People with Disabilities, 31 Oct 08.

g. Elevator Industry Field Employees’ Safety Handbook.