VOY – Falkner Park Restroom Building Project Specifications.pdf
PDF 760 KB Posted
- Attached to
- FALKNER PARK RESTROOM BUILDING
- Solicitation number
- 2140442
- Issued by
- Niagara County, New York
About this file
This is a Project Specifications and Bid Document for the Village of Youngstown, New York, for construction of a new single-story, wood-framed public restroom building at Falkner Park (File No. 25-086-C). The project scope includes complete site clearing and demolition, earthwork, cast-in-place concrete footings and slab-on-grade, full wood-frame construction with vinyl siding exterior, TPO membrane roofing, all interior finishes including fiber-reinforced polymer (FRP) wall panels in wet areas, complete plumbing with domestic water supply and sanitary waste systems, mechanical systems with electric wall heaters, complete electrical service and lighting, a remote access electronic door lock system with cellular connectivity, and fire detection and alarm systems. The building also includes ADA-accessible concrete walks and site restoration. Bids must be submitted in sealed opaque envelopes on the Owner-provided Bid Form to the Village Clerk's office by the date and time specified in the Notice to Bidders, with bids remaining irrevocable for sixty (60) calendar days following the bid opening. The project documents incorporate by reference AIA Document A101 (Standard Form of Agreement), AIA Document A201-2017 (General Conditions), and the Supplementary Conditions (Section 00 73 00).
Bidders must comply with New York State Labor Law Article 8 prevailing wage requirements and submit a Non-Collusion Affidavit per General Municipal Law 103-d. The Contractor must procure commercial general liability insurance of $1,000,000 per occurrence/$2,000,000 aggregate with the Village named as additional insured, builder's risk coverage at full replacement value, workers' compensation per NYS law, and automobile liability of $1,000,000 combined single limit. Bid Bonds (Section 00 43 13) and Performance and Payment Bonds (Section 00 61 13) are expressly excluded from this project. A ten percent (10%) retainage applies until fifty percent (50%) completion, then five percent (5%) retainage on remaining balance; final retainage is released upon achievement of Final Completion. The Agreement is structured as a fixed-price (Stipulated Sum) contract. The Village reserves the right to reject any or all bids and is not obligated to award to the lowest responsible bidder. Qualified bidders must demonstrate minimum five (5) years of general contracting experience in New York State, at least three (3) comparable completed wood-frame commercial or institutional building projects, valid NYS contractor's license, an OSHA Experience Modification Rate (EMR) of 1.0 or lower, and demonstrated financial capacity to complete the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VILLAGE OF YOUNGSTOWN
NEW YORK
FALKNER PARK RESTROOM BUILDING
PROJECT SPECIFICATIONS
File No.: 25-086-C
Drawing Date: November 3, 2025
Document Date: November 3, 2025
Owner: Village of Youngstown, New York
Prepared in accordance with architectural drawings File No. 25-086-C, dated 11/03/2025.
This document constitutes the Project Manual for competitive public bidding.
All contractors submitting bids shall read, understand, and comply with all sections herein.
Village of Youngstown reserves the right to reject any or all bids.
TABLE OF CONTENTS
Section Number Section Title Division
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 01 Project Title Page 00
00 01 10 Table of Contents 00
00 21 13 Instructions to Bidders 00
00 52 00 Agreement 00
00 72 00 General Conditions 00
00 73 00 Supplementary Conditions 00
NOTE: Section 00 43 13 (Bid Bond) is NOT included. Section 00 61 13 (Performance Bond and Payment Bond) is NOT included. These sections are expressly excluded from this Project Manual.
DIVISION 01 – GENERAL REQUIREMENTS
01 10 00 Summary of Work 01
01 20 00 Price and Payment Procedures 01
01 30 00 Administrative Requirements 01
01 40 00 Quality Requirements 01
01 50 00 Temporary Facilities and Controls 01
01 60 00 Product Requirements 01
01 70 00 Execution and Closeout Requirements 01
01 78 00 Closeout Submittals 01
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 02
DIVISION 03 – CONCRETE
03 10 00 Concrete Forming and Accessories 03
03 20 00 Concrete Reinforcing 03
03 30 00 Cast-in-Place Concrete 03
DIVISION 05 – METALS
05 50 00 Metal Fabrications 05
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 06
06 16 00 Sheathing 06
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 10 00 Dampproofing and Waterproofing 07
07 20 00 Thermal Protection 07
07 46 23 Vinyl Siding 07
07 50 00 Membrane Roofing 07
07 60 00 Flashing and Sheet Metal 07
07 90 00 Joint Protection 07
07 95 00 Fiber-Reinforced Polymer (FRP) Wall Panels 07
DIVISION 08 – OPENINGS
08 11 00 Metal Doors and Frames 08
08 71 00 Door Hardware 08
08 71 13 Remote Access Door Lock Systems 08
08 80 00 Glazing 08
DIVISION 09 – FINISHES
09 29 00 Gypsum Board 09
09 30 00 Tiling 09
09 90 00 Paints and Coatings 09
DIVISION 10 – SPECIALTIES
10 21 13 Toilet Compartments 10
10 28 00 Toilet, Bath, and Laundry Accessories 10
10 44 00 Fire Protection Specialties 10
DIVISION 22 – PLUMBING
22 00 00 Plumbing, General 22
22 10 00 Plumbing Piping 22
22 40 00 Plumbing Fixtures 22
22 42 00 Frost-Free Hose Bibbs 22
DIVISION 23 – HVAC
23 00 00 Mechanical, General 23
23 82 00 Electric Wall Heaters 23
DIVISION 26 – ELECTRICAL
26 00 00 Electrical, General 26
26 05 00 Common Work Results for Electrical 26
26 20 00 Branch Circuits and Devices 26
26 50 00 Lighting 26
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm 28
DIVISION 31 – EARTHWORK
31 10 00 Site Clearing 31
31 20 00 Earth Moving 31
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 13 00 Concrete Paving 32
32 90 00 Planting 32
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 33
33 30 00 Sanitary Sewerage Utilities 33
33 40 00 Storm Drainage Utilities 33
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 01 – PROJECT TITLE PAGE
PART 1 – GENERAL
1.01 Project Identification
A. Project Name: Falkner Park Restroom Building
B. Owner: Village of Youngstown, New York
C. File No.: 25-086-C
D. Drawing Date: November 3, 2025
E. Document Date: November 3, 2025
F. Building Type: Single-story, wood-framed public restroom building with vinyl siding exterior, located at Falkner Park, Village of Youngstown, New York.
1.02 Project Description
A. The work consists of the complete construction of a new single-story, wood-framed public restroom building at Falkner Park. The building exterior is clad with vinyl siding. Work includes all site, civil, structural, architectural, plumbing, mechanical, and electrical work as shown on drawings File No. 25-
086-C, dated November 3, 2025, and as specified herein.
B. This Project Manual is prepared in accordance with architectural drawings File No. 25-086-C, dated
11/03/2025.
NOTICE TO BIDDERS:
Section 00 43 13 (Bid Bond) is NOT included in this Project Manual and is expressly excluded from this project. Section 00 61 13 (Performance Bond and
Payment Bond) is NOT included and is expressly excluded from this project.
Falkner Park Restroom Building | File No. 25-086-C | Section 00 01 01
END OF SECTION 00 01 01
SECTION 00 01 10 – TABLE OF CONTENTS
1.01 Table of Contents
A. The Table of Contents for this Project Manual is provided in its entirety on the preceding pages of this document. All sections enumerated therein are incorporated herein by reference.
B. Bidders and Contractors shall review the Table of Contents in its entirety to ensure all sections have been received and reviewed before submitting a bid.
C. Any discrepancy between the Table of Contents and the sections actually contained in this Project
Manual shall be immediately reported to the Owner in writing via the RFI process described in Section
01 30 00.
Falkner Park Restroom Building | File No. 25-086-C | Section 00 01 10
END OF SECTION 00 01 10
SECTION 00 21 13 – INSTRUCTIONS TO BIDDERS
1.01 Bid Submission Requirements
A. Bids shall be submitted on the Owner-provided Bid Form only. No substitutions or alternate bid forms will be accepted.
B. Bids shall be submitted in a sealed opaque envelope clearly labeled: "SEALED BID – Falkner Park
Restroom Building – File No. 25-086-C – DO NOT OPEN BEFORE BID OPENING."
C. Bids shall be delivered to the Office of the Village Clerk, Village of Youngstown, New York, at the address designated in the bid advertisement, no later than the date and time specified in the Notice to
Bidders. Late bids will not be accepted and will be returned unopened.
D. The Bid Form shall be fully completed, signed, and dated by an authorized representative of the
Bidder. Erasures and alterations must be initialed by the authorized representative.
E. Each Bidder shall include in the bid all labor, materials, equipment, permits, taxes, insurance, overhead, and profit necessary to complete the Work in accordance with the Contract Documents.
F. Bids shall remain in effect and irrevocable for a period of sixty (60) calendar days following the bid opening date.
1.02 Prevailing Wage Requirements – New York State Labor Law Article 8
A. This is a public works project subject to the requirements of New York State Labor Law Article 8. All workers employed on this project shall be paid not less than the prevailing wages and supplements as determined by the NYS Commissioner of Labor for the locality in which the work is performed.
B. The applicable Prevailing Wage Schedule shall be obtained by the Contractor directly from the NYS
Department of Labor. The Prevailing Wage Rate Schedule is available through the NYS DOL Public Work
Unit.
C. The Contractor and all subcontractors shall file certified payrolls with the Owner as required by NYS
Labor Law §220. Failure to pay prevailing wages is a violation of New York State Law and may result in debarment, civil penalties, and criminal prosecution.
D. The applicable Prevailing Wage Case Number shall be obtained prior to bid submission. Bidders are responsible for incorporating prevailing wage rates into their bid pricing.
1.03 Non-Collusion Affidavit
A. Each Bidder shall execute and submit with the Bid Form a Non-Collusion Affidavit as required by New
York State General Municipal Law §103-d.
B. The affidavit shall certify that the prices in the bid have been arrived at independently, without collusion, consultation, communication, or agreement with any other Bidder or competitor regarding the price submitted.
C. Bids submitted without a signed Non-Collusion Affidavit may be deemed non-responsive and rejected.
1.04 Right to Reject Bids
A. The Village of Youngstown reserves the right, in its sole and absolute discretion, to reject any or all bids, to waive any informality or irregularity in any bid, and to accept the bid that is in the best interest of the Village.
B. The Village is not obligated to award to the lowest responsible bidder if the Village determines, for any reason, that doing so is not in the public interest.
C. The Village reserves the right to reject all bids and re-advertise for bids at any time prior to the award of a contract.
1.05 Bid Opening Procedures
A. Bids will be publicly opened and read aloud at the time, date, and location specified in the Notice to
Bidders. All Bidders and members of the public are welcome to attend.
B. Bid results will be tabulated by the Village Clerk or designated representative and made available to all Bidders within a reasonable time following the bid opening.
C. The apparent low Bidder will be subject to review of qualifications, licensing, insurance, and compliance with all bid requirements prior to award. The Owner reserves the right to request documentation of qualifications from any Bidder.
1.06 Questions and Addenda
A. Questions regarding the Contract Documents shall be submitted in writing to the designated contact as identified in the Notice to Bidders. Verbal inquiries will not receive binding responses.
B. Questions must be submitted no later than seven (7) calendar days prior to the scheduled bid opening to allow adequate time for preparation and issuance of an addendum.
C. Responses to questions of general interest will be issued in the form of written Addenda to all registered plan holders. Addenda will be issued via the same distribution method as the original bid documents.
D. Each Bidder is responsible for ensuring receipt of all Addenda prior to submitting a bid. Bidders shall acknowledge all received Addenda on the Bid Form. Failure to acknowledge all Addenda may result in bid rejection.
E. No oral interpretations will be made to any Bidder. Only written Addenda signed by the Owner or
Owner's representative shall be binding.
Falkner Park Restroom Building | File No. 25-086-C | Section 00 21 13
END OF SECTION 00 21 13
SECTION 00 52 00 – AGREEMENT
1.01 Standard Form of Agreement
A. The Agreement between the Owner and Contractor shall be AIA Document A101, Standard Form of
Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum, current edition, as modified by the Owner's Supplementary Conditions (Section 00 73 00).
B. The Agreement is incorporated by reference into this Project Manual and shall be executed by the
Village of Youngstown and the successful Bidder upon award of the Contract.
1.02 Contract Sum
A. The Contract Sum shall be as established in the executed Agreement between the Owner and
Contractor, equal to the accepted bid amount including all accepted alternates.
B. The Contract Sum shall constitute full compensation for all labor, materials, equipment, supervision, insurance, bonds (if applicable), permits, taxes, fees, overhead, and profit required to perform and complete the Work.
1.03 Substantial Completion
A. The Date of Substantial Completion shall be established in the Agreement. The Contractor shall achieve Substantial Completion of the entire Work by the date stipulated in the Agreement.
B. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.
C. Liquidated damages may be assessed for failure to achieve Substantial Completion by the required date as stipulated in the Agreement.
1.04 Final Completion
A. Final Completion shall be achieved within thirty (30) calendar days following the date of Substantial
Completion, unless otherwise stipulated in the Agreement.
B. Final Completion requires completion of all punch list items, submission of all Closeout Submittals per
Section 01 78 00, and Architect's issuance of a Final Certificate for Payment.
Falkner Park Restroom Building | File No. 25-086-C | Section 00 52 00
END OF SECTION 00 52 00
SECTION 00 72 00 – GENERAL CONDITIONS
1.01 Reference to AIA A201
A. The General Conditions of the Contract for Construction shall be AIA Document A201-2017, General
Conditions of the Contract for Construction, which is incorporated herein by reference and made a part of the Contract Documents.
B. A copy of AIA A201-2017 shall be obtained by the Contractor from the Owner or the American
Institute of Architects. All provisions of AIA A201-2017 apply to this Contract except as modified by the
Supplementary Conditions (Section 00 73 00).
C. In the event of a conflict between AIA A201-2017 and the Supplementary Conditions (Section 00 73
00), the Supplementary Conditions shall govern.
Falkner Park Restroom Building | File No. 25-086-C | Section 00 72 00
END OF SECTION 00 72 00
SECTION 00 73 00 – SUPPLEMENTARY CONDITIONS
1.01 NYS Prevailing Wage Requirements
A. New York State Prevailing Wage rates are applicable to this project pursuant to NYS Labor Law Article
8. The Contractor shall obtain the current Prevailing Wage Schedule applicable to this project from the
New York State Department of Labor prior to commencement of construction.
B. The Contractor and all subcontractors shall pay all workers employed on this public works project wages and supplements not less than those set forth in the applicable Prevailing Wage Schedule. The
Contractor shall post the Prevailing Wage Schedule at the job site in a prominent location accessible to all workers.
C. Certified payroll records shall be maintained and submitted as required by NYS Labor Law §220(3-a) and upon request by the Owner or the NYS Department of Labor.
1.02 Insurance Requirements
A. The Contractor shall procure and maintain, at its own expense and without additional compensation, the following insurance coverages throughout the duration of the Contract:
1. Commercial General Liability (CGL): Minimum $1,000,000 per occurrence; $2,000,000 aggregate;
Products and Completed Operations coverage included. The Village of Youngstown shall be named as an
Additional Insured on a primary and non-contributory basis.
2. Builder's Risk (Installation Floater): All-risk coverage for the full replacement value of the Work in progress, including materials stored on-site and off-site. The Village of Youngstown shall be a named insured.
3. Workers' Compensation and Employer's Liability: In accordance with the requirements of the New
York State Workers' Compensation Law, including Disability Benefits coverage. Contractor shall provide certificates of compliance (Form C-105.2 or equivalent) prior to commencing work.
4. Automobile Liability: Minimum $1,000,000 combined single limit covering all owned, hired, and non-owned vehicles.
B. All insurance shall be placed with companies licensed to do business in New York State with an A.M.
Best rating of A- VII or better. Certificates of Insurance and Additional Insured endorsements acceptable to the Owner shall be submitted prior to commencement of any Work and shall be maintained continuously throughout the project.
C. The Contractor's insurance shall be primary with respect to the Owner and shall not be reduced or cancelled without thirty (30) days' prior written notice to the Village of Youngstown.
1.03 Indemnification
A. To the fullest extent permitted by law, the Contractor shall indemnify, defend, and hold harmless the
Village of Youngstown, its officers, officials, employees, agents, and volunteers from and against any and all claims, damages, losses, costs, and expenses, including reasonable attorneys' fees, arising out of or resulting from the Contractor's performance of the Work, including any acts or omissions of the
Contractor, its subcontractors, suppliers, employees, or agents, provided that such claim, damage, loss, or expense is attributable to bodily injury, sickness, disease, or death, or injury to or destruction of tangible property.
B. This indemnification obligation shall not be construed to negate, abridge, or otherwise reduce any other right or obligation of indemnity which would otherwise exist as to any party described in this paragraph.
1.04 Governing Law
A. This Contract shall be governed by, interpreted, and enforced in accordance with the laws of the
State of New York, without regard to conflicts of law principles. Any disputes arising hereunder shall be resolved in a court of competent jurisdiction in the State of New York.
Falkner Park Restroom Building | File No. 25-086-C | Section 00 73 00
END OF SECTION 00 73 00
DIVISION 01 – GENERAL REQUIREMENTS
SECTION 01 10 00 – SUMMARY OF WORK
1.01 Project Description
A. The Work consists of the complete construction of a new single-story, wood-framed public restroom building with vinyl siding exterior at Falkner Park, Village of Youngstown, New York. The building superstructure is entirely wood-framed. There is no masonry construction of any kind in this project.
B. Scope of Work includes, but is not limited to:
● Site clearing, demolition of any existing structures, and grading
● Earthwork and excavation for concrete footings and utilities
● Cast-in-place concrete footings and slab-on-grade (no masonry)
● Complete wood-frame construction including exterior walls, interior partitions, and roof framing
● Structural wall and roof sheathing with weather-resistive barrier
● Vinyl siding, vinyl soffit, and vinyl trim accessories at all exterior wall surfaces
● TPO membrane roofing system with full flashing
● Exterior and interior doors, hollow metal frames, and all hardware including remote access lock systems
● All thermal insulation and moisture protection
● FRP wall panels in all interior wet areas
● Floor and wall tile in restroom areas
● Gypsum wallboard and painting
● All restroom accessories and specialties
● Complete domestic water supply, sanitary waste and vent, and all plumbing fixtures
● Frost-free exterior hose bibbs
● Electric wall heaters in all restroom spaces
● Complete electrical service, distribution, branch circuits, devices, and lighting
● Remote access door lock system with cellular connectivity
● Fire detection and alarm system as required by code
● Site work including ADA-accessible concrete walks, connections to utilities, and site restoration
1.02 Contract Documents
A. The Work shall be performed in strict conformance with all applicable drawings, File No. 25-086-C, dated November 3, 2025, and all sections of this Project Manual. The drawings and Project Manual are complementary; what is shown or specified in one is as binding as if shown or specified in both.
B. In the event of a conflict between the drawings and the specifications, the more stringent or more costly requirement shall govern, unless the Architect/Engineer provides written clarification.
1.03 Work by Owner
A. The Owner will coordinate utility shut-off and reconnections at the property line. The Owner will provide keys and access as needed for construction. All other work is the responsibility of the
Contractor.
1.04 Use of Site
A. Falkner Park remains an active public park during construction. The Contractor shall minimize disruption to park operations and shall maintain safe, unobstructed public access to all park areas not within the fenced construction zone at all times.
B. The Contractor shall coordinate with the Village DPW and Parks Department regarding construction hours, access routes, and any temporary closures of adjacent pathways.
Falkner Park Restroom Building | File No. 25-086-C | Section 01 10 00
END OF SECTION 01 10 00
SECTION 01 20 00 – PRICE AND PAYMENT PROCEDURES
1.01 Schedule of Values
A. Within fifteen (15) calendar days of Contract award, and prior to the first Application for Payment, the Contractor shall submit to the Architect a Schedule of Values allocating the entire Contract Sum among the various portions of the Work. The Schedule of Values shall be organized by CSI Division and
Section.
B. The Schedule of Values shall be subject to review and approval by the Architect. Values shall be balanced; front-loading will not be approved.
1.02 Applications for Payment
A. The Contractor shall submit monthly Applications for Payment using AIA Document G702 and G703, or equivalent form acceptable to the Owner. Applications shall be submitted on or before the 25th of each month.
B. Each Application for Payment shall reflect the amount of Work completed through the end of the application period, as measured against the approved Schedule of Values.
C. Applications for Payment shall include all required lien waivers from the Contractor, subcontractors, and suppliers for all prior payments received.
1.03 Retainage
A. Retainage of ten percent (10%) shall be withheld from each progress payment until the Work is fifty percent (50%) complete.
B. Upon achievement of fifty percent (50%) completion, as certified by the Architect, retainage shall be reduced to five percent (5%) of the balance of the Contract Sum for subsequent progress payments.
C. Retainage will be released upon Final Completion and Owner acceptance, including receipt of all
Closeout Submittals per Section 01 78 00, in accordance with the terms of the Agreement and applicable
New York State law.
Falkner Park Restroom Building | File No. 25-086-C | Section 01 20 00
END OF SECTION 01 20 00
SECTION 01 30 00 – ADMINISTRATIVE REQUIREMENTS
1.01 Submittal Procedures
A. The Contractor shall prepare and submit a Submittal Log to the Architect within fifteen (15) days of
Contract award. The Submittal Log shall identify all required submittals by specification section, description, and scheduled submission date.
B. Product Data, Shop Drawings, and Samples shall be submitted sufficiently in advance of need to allow a minimum of fifteen (15) business days for Architect review, plus additional time for resubmittal if required.
C. Each submittal shall bear the Contractor's stamp of approval indicating the Contractor has reviewed and coordinated the submittal with the Contract Documents. Submittals without the Contractor's stamp will be returned without review.
D. Substitution requests shall be submitted in writing with full technical documentation per Section 01
60 00 at least ten (10) business days before the bid opening (for pre-bid substitutions) or within thirty
(30) days of Contract award (for post-award substitutions).
1.02 Request for Information (RFI) Process
A. Requests for Information shall be submitted in writing on a standard RFI form to the Architect. Verbal
RFIs will not be accepted as binding.
B. RFIs shall be numbered sequentially. Each RFI shall clearly describe the information requested, reference the applicable drawing or specification section, and indicate the date response is needed.
C. The Architect will respond to RFIs within ten (10) business days, unless the RFI requires additional information from the Contractor or is unduly complex.
D. RFI responses shall not be used as a basis for extra compensation unless the response reflects a genuine change in the Work, in which case a Change Order shall be processed per AIA A201.
1.03 Project Meetings
A. A pre-construction meeting shall be held prior to commencement of any Work. Attendees shall include the Owner's representative, Architect, Contractor's superintendent, and major subcontractor representatives.
B. Regular progress meetings shall be held not less than bi-weekly, or as determined at the pre-construction meeting. The Contractor shall prepare and distribute meeting minutes within three (3) business days of each meeting.
1.04 Project Schedule
A. The Contractor shall submit a preliminary project schedule in bar chart (Gantt) format within ten (10) calendar days of Contract award. The schedule shall show all major activities, milestones, and critical path items.
B. An updated schedule shall be submitted with each monthly Application for Payment. The Contractor shall promptly notify the Owner and Architect of any circumstances that may delay Substantial
Completion.
Falkner Park Restroom Building | File No. 25-086-C | Section 01 30 00
END OF SECTION 01 30 00
SECTION 01 40 00 – QUALITY REQUIREMENTS
1.01 Testing and Inspection
A. The Owner shall retain an independent testing and inspection agency to perform special inspections and testing as required by IBC Chapter 17 and the Contract Documents. The cost of Owner-directed testing and inspection shall be borne by the Owner, except that re-testing or re-inspection required due to Contractor's failure shall be at the Contractor's expense.
B. The Contractor shall cooperate fully with the testing and inspection agency, provide access to all
Work areas, and provide advance notice of operations requiring inspection as specified herein.
C. Work concealed before required inspections and approvals have been obtained shall be uncovered at the Contractor's sole expense and re-inspected.
1.02 Special Inspections – IBC Chapter 17
A. Special inspections shall be performed for the following operations in accordance with IBC Chapter 17 and the Statement of Special Inspections prepared by the Structural Engineer of Record:
● Concrete: Inspection of formwork, reinforcing placement, and concrete placement; verification of mix design; testing per Section 03 30 00
● Soil: Compaction testing and proof-roll observation per Section 31 20 00
● Wood Framing: Inspection of shear wall nailing patterns per shear wall schedule on structural drawings; inspection of holdown anchor installation; inspection of header sizes, bearing, and connection hardware at all openings per structural drawings
● Structural connectors: Inspection of hurricane tie installation at every rafter-to-plate bearing point
1.03 Concrete Testing
A. Concrete testing shall be performed per Section 03 30 00. One set of four (4) test cylinders shall be taken for each 50 cubic yards of concrete placed or each day's placement, whichever results in more frequent testing.
B. Slump, air content, temperature, and unit weight tests shall be performed at the time of sampling for each set of cylinders. Test results shall be submitted to the Architect and Owner's representative within three (3) business days of testing.
1.04 Soil Compaction Testing
A. Compaction of all backfill shall be tested by the Owner's testing agency. A minimum of one (1) density test per 1,000 square feet of compacted area per lift, or at the frequency directed by the Owner's testing agency, shall be required. All testing shall confirm minimum 95% of Standard Proctor density per
ASTM D698.
1.05 Wood Framing Special Inspection
A. Shear wall nailing shall be inspected prior to installation of any sheathing or cladding. All shear wall nailing patterns shall conform to the Shear Wall Schedule shown on the structural drawings.
B. Holdown anchor installation, including bolt embedment, washer and nut engagement, and strap nailing, shall be inspected and documented prior to framing concealment.
C. Header sizes, bearing length, and connector hardware at all wall openings shall be verified by the special inspector against structural drawings prior to installation of sheathing.
Falkner Park Restroom Building | File No. 25-086-C | Section 01 40 00
END OF SECTION 01 40 00
SECTION 01 50 00 – TEMPORARY FACILITIES AND CONTROLS
1.01 Temporary Fencing and Site Security
A. The Contractor shall erect and maintain a minimum six-foot (6') chain-link construction fence around the entire construction zone prior to any demolition or earthwork activities. Fence shall be maintained in good condition throughout construction.
B. Fence gates shall be kept locked outside of active working hours. No public access to the construction zone shall be permitted at any time.
C. The Contractor is responsible for security of the site and all materials, tools, and equipment stored thereon.
1.02 Sanitary Facilities
A. The Contractor shall provide and maintain adequate sanitary facilities (portable toilets) for construction workers throughout the construction period. Facilities shall be emptied and serviced at least weekly. Facilities shall not be placed in areas accessible to the public.
1.03 Construction Signage
A. The Contractor shall install project identification signage per the Owner's requirements, including the project name, File No. 25-086-C, Owner name (Village of Youngstown), and Contractor name and emergency contact number.
B. Signage shall be posted at all public-facing fence perimeters warning of the active construction zone.
Pedestrian detour signage shall be posted as needed to direct park visitors safely around the construction area.
1.04 Site Access
A. Construction vehicle access routes shall be coordinated with the Village DPW prior to commencement of construction. Damage to existing park paving, turf, landscaping, or infrastructure caused by construction operations shall be repaired by the Contractor at no additional cost to the Owner.
B. Construction deliveries shall be scheduled to minimize interference with park visitors and adjacent neighborhoods.
1.05 Dust and Noise Control
A. The Contractor shall implement dust control measures including watering of disturbed earth surfaces during dry conditions, wheel washing at site exits, and covering of material stockpiles.
B. Noise-generating construction activities shall be limited to the hours permitted by the Village of
Youngstown noise ordinance and shall not impair the enjoyment of Falkner Park by the public during park operating hours. Coordinate construction schedule with the Village DPW to maintain park operational hours throughout construction.
C. Burning of materials on-site is prohibited.
Falkner Park Restroom Building | File No. 25-086-C | Section 01 50 00
END OF SECTION 01 50 00
SECTION 01 60 00 – PRODUCT REQUIREMENTS
1.01 Substitution Requests
A. Where specific products or manufacturers are specified as "or approved equal," the Contractor may submit a substitution request for consideration. The burden of proof of equality rests with the
Contractor.
B. Substitution requests shall include: a written description of the proposed substitution, full technical specifications and data sheets, a comparison of the proposed product against the specified product for all applicable performance criteria, identification of any deviations from the Contract Documents, and any cost or schedule impacts.
C. Approval or rejection of substitution requests is at the sole discretion of the Architect, with concurrence of the Owner. Approved substitutions shall be documented by written addendum (pre-bid) or Architect's Supplemental Instructions or Change Order (post-award).
D. Substitutions shall not be implemented prior to written approval. The Contractor assumes all risks associated with unapproved substitutions, including cost of removal and replacement with specified products.
1.02 Approved Manufacturers
A. Where named manufacturers are listed in specifications, these represent the standard of quality required. Other manufacturers may be submitted for approval per paragraph 1.01 above. Products shall be current-production models with available local technical support.
1.03 Delivery, Storage, and Handling
A. Deliver materials in manufacturer's original, sealed, labeled containers. Inspect deliveries upon receipt; reject and return damaged or non-conforming materials promptly.
B. Store materials in accordance with manufacturer's written recommendations. Protect from weather, moisture, damage, and theft. Do not store materials directly on the ground without protection.
C. Pressure-treated lumber, gypsum board, cement board, vinyl siding, and other moisture-sensitive materials shall be stored off the ground, covered, and ventilated. Wet or damaged materials shall be removed from the site and replaced.
Falkner Park Restroom Building | File No. 25-086-C | Section 01 60 00
END OF SECTION 01 60 00
SECTION 01 70 00 – EXECUTION AND CLOSEOUT REQUIREMENTS
1.01 Cleaning
A. The Contractor shall maintain the construction site in a neat, orderly, and clean condition throughout the construction period. Waste materials, debris, and rubbish shall be removed from the site on a daily basis or as necessary to maintain cleanliness.
B. Upon completion of the Work and prior to Substantial Completion, the Contractor shall thoroughly clean all interior and exterior spaces, removing all construction debris, dust, paint overspray, labels, temporary markings, and protective coverings. All glazing shall be clean and free of smears, spots, and scratches.
C. Final cleaning shall produce a facility in move-in-ready condition, as if newly constructed and professionally cleaned.
1.02 Final Inspection
A. When the Contractor considers the Work substantially complete, the Contractor shall notify the
Architect in writing and request a Substantial Completion inspection. The Architect and Owner's representative shall conduct the inspection within ten (10) business days of receipt of the Contractor's notice.
B. The Architect will issue a Certificate of Substantial Completion (AIA G704 or equivalent) upon determining that the Work is substantially complete. The Certificate shall list all items requiring completion or correction (punch list).
1.03 Punch List
A. The Architect will issue the Punch List to the Contractor concurrent with or following the Substantial
Completion inspection.
B. The Contractor shall complete all Punch List items within thirty (30) calendar days of the date of
Substantial Completion. Failure to complete Punch List items within this period may result in the Owner completing the work by separate contract and deducting the cost from amounts due the Contractor.
1.04 Record Drawings
A. Throughout construction, the Contractor shall maintain a set of Contract Drawings on-site with all changes, deviations, and as-built conditions clearly and accurately marked in red ink.
B. As-built record drawings shall be submitted to the Architect within thirty (30) calendar days of
Substantial Completion. Record drawings shall be provided as full-size prints with handwritten as-built notations, plus a PDF copy on electronic media.
1.05 O&M Manuals
A. Three (3) complete bound hard-copy sets plus one (1) complete electronic PDF copy (on USB drive) of
Operation and Maintenance (O&M) Manuals shall be submitted for all installed equipment, systems, and building components requiring maintenance, operation, or service.
B. O&M Manuals shall include: manufacturer's installation instructions, operation and maintenance procedures, parts lists, warranty documents, contact information for manufacturers and service providers, and all other information specified in individual sections.
Falkner Park Restroom Building | File No. 25-086-C | Section 01 70 00
END OF SECTION 01 70 00
SECTION 01 78 00 – CLOSEOUT SUBMITTALS
1.01 Punch List Procedures
A. The Architect will issue the Punch List to the Contractor upon or following the Substantial Completion inspection. The Contractor shall complete all items on the Punch List within thirty (30) calendar days of the date of Substantial Completion, unless a specific item requires materials or equipment with a longer lead time, in which case the Contractor shall provide a written schedule for completion acceptable to the Architect.
1.02 As-Built Record Drawings
A. As-built record drawings shall be submitted to the Architect within thirty (30) calendar days of
Substantial Completion in both marked-up print format and PDF electronic format.
1.03 O&M Manuals
A. Three (3) bound hard-copy sets plus one (1) electronic PDF copy on USB drive shall be submitted for all equipment and systems, including but not limited to: electric wall heaters, electric water heater, exhaust fans, remote access door lock system, plumbing fixtures and valves, frost-free hose bibbs, fire detection and alarm system, and electrical panel and breakers.
B. Each manual shall be organized by specification section, three-hole punched, and contained in a durable three-ring binder with a labeled spine. Table of Contents shall be included.
1.04 Warranties
A. Contractor's General Warranty: The Contractor warrants all Work against defects in materials and workmanship for a period of one (1) year from the date of Substantial Completion.
B. Roofing Manufacturer's Warranty: 20-year manufacturer's warranty on the TPO membrane roofing system, as specified in Section 07 50 00. The Contractor shall obtain and deliver the executed warranty to the Owner at or before Final Completion.
C. Vinyl Siding Manufacturer's Warranty: Manufacturer's limited lifetime warranty against defects, cracking, peeling, and color fade, as specified in Section 07 46 23.
D. All manufacturer warranties shall be compiled in the O&M Manuals. A Warranty Summary Sheet shall be prepared by the Contractor listing each warranty, the warranted product/system, the warranty term, and the warranty contact information.
1.05 Training
A. The Contractor shall conduct a minimum of two (2) hours of on-site training for Village of Youngstown
Department of Public Works and Parks Department staff. Training shall cover the operation, maintenance, and troubleshooting of all mechanical, plumbing, and electrical systems, including: electric wall heaters; electric water heater; exhaust fans; plumbing fixtures, shut-off valves, and frost-free hose bibbs (including winterization procedure); remote access door lock system (platform administration, scheduling, audit log, emergency procedures); and the fire detection and alarm system.
B. Training shall be scheduled with the Owner at a mutually convenient time prior to Final Completion. A written training outline shall be submitted to the Architect at least five (5) business days prior to training.
1.06 Attic Stock
A. The Contractor shall deliver to the Owner at Substantial Completion the following attic stock, properly labeled and stored in the facility:
● Floor and wall tile: Two percent (2%) of each tile type and size used, in original unopened boxes
● Caulk and sealant: One (1) full tube of each caulk/sealant color and type used
● Paint: One (1) full gallon of each paint color and sheen used on interior and exterior surfaces
B. Attic stock shall be labeled with the product name, color name/number, and application location, and delivered in original manufacturer's containers where possible.
1.07 Substantial Completion Certificate
A. Substantial Completion shall be documented using AIA Document G704, Certificate of Substantial
Completion, or equivalent form acceptable to the Owner. The G704 shall be executed by the Architect, Owner, and Contractor upon agreement that Substantial Completion has been achieved.
Falkner Park Restroom Building | File No. 25-086-C | Section 01 78 00
END OF SECTION 01 78 00
DIVISION 02 – EXISTING CONDITIONS
SECTION 02 41 00 – DEMOLITION
1.01 Summary
A. Work of this section includes selective demolition and removal of existing above-grade structures, site clearing, and protection of existing features to remain.
1.02 Regulatory Requirements
A. All demolition work shall comply with OSHA 29 CFR 1926, Subpart T – Demolition, NYS Building Code, and applicable local regulations. All permits required for demolition shall be obtained by the Contractor prior to commencement of demolition.
PART 2 – PRODUCTS
2.01 Materials
A. No specific products are required for demolition. Contractor shall furnish all tools, equipment, and materials required for safe and complete demolition operations.
PART 3 – EXECUTION
3.01 Removal of Existing Structures
A. Remove all existing structures, foundations, slabs, paving, and site improvements within the construction zone as indicated on the drawings. Coordinate with the Owner and Architect to identify items designated for salvage or Owner retention prior to demolition.
B. All salvageable items identified by the Owner shall be carefully removed, cleaned, and stored on-site at a location designated by the Owner, or delivered to a location designated by the Village of
Youngstown, at no additional cost to the Owner.
3.02 Disposal
A. All demolished materials not designated for salvage shall be legally disposed of off-site at a licensed disposal facility. No burning or burying of demolition debris on-site is permitted.
B. Hazardous materials, if encountered, shall be addressed per a separate Hazardous Materials
Abatement Plan and applicable NYS DEC and OSHA regulations. The Contractor shall notify the Owner and Architect immediately upon discovery of any suspected hazardous materials.
3.03 Protection of Existing Features
A. Existing trees designated to remain shall be protected by orange construction fencing installed at the drip line of each tree prior to any demolition or grading operations. No materials shall be stored, no vehicles operated, and no grading performed within the drip line area of any tree designated to remain.
B. Existing park infrastructure (pathways, lighting, utilities, irrigation, landscaping, playground equipment, and park amenities) outside the construction zone shall be protected from damage throughout construction. Any damage to existing park features shall be repaired by the Contractor to equal or better condition at no additional cost to the Owner.
Falkner Park Restroom Building | File No. 25-086-C | Section 02 41 00
END OF SECTION 02 41 00
DIVISION 03 – CONCRETE
IMPORTANT – SCOPE LIMITATION:
This project is a single-story wood-framed building with vinyl siding. Concrete work is limited to footings and slab-on-grade ONLY. There are NO concrete masonry unit (CMU) walls, NO masonry foundation walls, and NO masonry construction of any kind on this project. Division 04 (Masonry) is entirely omitted from this Project
Manual. The building superstructure is entirely wood-framed.
SECTION 03 10 00 – CONCRETE FORMING AND ACCESSORIES
A. Formwork for cast-in-place concrete footings and slab-on-grade, including form design, erection, accessories, and stripping.
1.02 References
A. ACI 347 – Guide to Formwork for Concrete. ACI 301 – Specifications for Structural Concrete. ACI 318 –
Building Code Requirements for Structural Concrete.
2.01 Form Materials
A. Form materials shall be of adequate strength and quality to resist the pressure of freshly placed concrete without deflection, bulging, or leakage. Lumber, plywood, or engineered form panels are acceptable.
B. Form release agent: Non-staining, non-reactive chemical release agent compatible with the concrete surface and any subsequent coatings or treatments.
C. Form ties: Metal snap ties or she-bolt type; designed and loaded per ACI 347.
3.01 Formwork Construction
A. Design, erect, shore, brace, and maintain formwork to safely support vertical and lateral loads until such loads can be supported by the concrete. All formwork shall be designed by or under the supervision of a competent formwork designer.
B. Apply form release agent to all form surfaces that will contact concrete before placing concrete.
C. Coordinate anchor bolt and holdown anchor templates with Section 05 50 00 and 06 10 00 before concrete placement.
3.02 Form Removal
A. Do not remove forms until the concrete has attained sufficient strength to support its own weight and imposed loads, as confirmed by test cylinder results or by the Structural Engineer of Record.
B. Footing forms: Remove minimum 24 hours after placement, weather permitting, provided concrete temperature has remained above 50°F.
Falkner Park Restroom Building | File No. 25-086-C | Section 03 10 00
END OF SECTION 03 10 00
SECTION 03 20 00 – CONCRETE REINFORCING
A. Deformed reinforcing bars, welded wire fabric (WWF), supports, and accessories for cast-in-place concrete footings and slab-on-grade.
1.02 References
A. ASTM A615 – Deformed and Plain Steel Bars for Concrete Reinforcement. ASTM A185 – Steel Welded
Wire Reinforcement, Plain. ACI 318 – Building Code Requirements for Structural Concrete. CRSI –
Manual of Standard Practice.
2.01 Reinforcing Bars
A. Deformed steel reinforcing bars: ASTM A615, Grade 60, with mill certification. Bar sizes and placement as shown on structural drawings.
2.02 Welded Wire Fabric
A. Welded wire fabric (WWF): ASTM A185, plain wire; size as shown on structural drawings or 6x6-
W1.4xW1.4 minimum for slab-on-grade.
2.03 Concrete Cover and Supports
A. Maintain concrete cover to reinforcing bars per ACI 318 Section 26.6: minimum 3 inches for bars in concrete cast against earth (footings); minimum 1.5 inches for bars in slabs not exposed to weather.
B. Provide bar chairs, slab bolsters, and other approved supports of adequate size to maintain required cover. Wire tie or plastic-tipped supports in contact with formed surfaces. Do not use brick, stone, or wood for supporting reinforcing.
3.01 Placement
A. Place reinforcing bars at locations and spacings shown on structural drawings. Secure in position prior to concrete placement using tie wire. Bars shall not be displaced during concrete placing operations.
B. Lap splice lengths: Per ACI 318 Table 25.5.2 for deformed bars in tension. Lap splices for Grade 60 deformed bars shall be Class B unless otherwise noted on structural drawings.
C. Do not weld reinforcing bars unless specifically approved in writing by the Structural Engineer.
Falkner Park Restroom Building | File No. 25-086-C | Section 03 20 00
END OF SECTION 03 20 00
SECTION 03 30 00 – CAST-IN-PLACE CONCRETE
A. Cast-in-place concrete for footings and slab-on-grade only. No concrete masonry units (CMU), no masonry foundation walls. All superstructure framing is wood.
1.02 References
A. ACI 301 – Specifications for Structural Concrete. ACI 318 – Building Code Requirements for Structural
Concrete. ACI 305 – Guide to Hot Weather Concreting. ACI 306 – Guide to Cold Weather Concreting.
ASTM C94 – Ready-Mixed Concrete.
1.03 Submittals
A. Concrete mix design(s) certified by a licensed laboratory, at least 14 days prior to first placement. Test results for all concrete placements.
2.01 Concrete Mix Requirements
Application Min. f'c (28-day) Max.
W/C Ratio
Air Entrainment Special Requirements
Footings 4,000 psi 0.45 Yes, per ACI 318 Min. 48" below grade (frost protection)
Slab-on-Grade 4,000 psi 0.45 Per design 4" min. thickness; see 2.02
2.02 Slab-on-Grade Requirements
A. Thickness: Minimum 4 inches throughout.
B. Vapor barrier: 6-mil polyethylene vapor retarder, fully lapped minimum 12 inches at joints and taped, installed directly below slab with no voids or tears.
C. Reinforcing: Welded wire fabric (WWF) per Section 03 20 00, placed at mid-depth of slab.
D. Control joints: Saw-cut or formed control joints at maximum 10-foot spacing in each direction, within
24 hours of placement.
E. Finish: Broom finish at all exterior concrete areas (including accessible walks); steel trowel finish at all interior slab areas.
2.03 Mix Design
A. Concrete mix design per ACI 301. Water-cement ratio shall not exceed 0.45 maximum for all concrete.
Slump: 3 to 5 inches unless otherwise approved. Air entrainment: 5.5% to 7.5% for footings exposed to freeze-thaw cycling. Use Type I/II Portland cement unless otherwise directed.
3.01 Placement
A. Do not place concrete when ambient temperature is below 40°F or forecast to fall below 40°F within
24 hours of placement, unless cold-weather concreting measures per ACI 306 are implemented and approved by the Owner.
B. Do not place concrete when ambient temperature exceeds 90°F unless hot-weather concreting measures per ACI 305 are implemented.
C. Deposit concrete as close to final position as practicable. Do not use vibrators to move concrete horizontally in forms. Consolidate with internal vibrators; avoid over-vibration.
D. Footing concrete shall be placed continuously without interruption. Coordinate anchor bolt and holdown anchor template installation immediately following footing placement and before concrete sets.
3.02 Curing
A. Cure all concrete for a minimum of seven (7) days using wet burlap, curing compound, or curing blankets. Protect concrete from freezing during curing period. Coordinate with cold-weather protection requirements.
3.03 Testing
A. One (1) set of four (4) standard cylinders shall be cast for each 50 cubic yards of concrete placed, or for each day's placement, whichever requires more frequent sampling. Cylinders shall be tested: two (2) at 7 days, two (2) at 28 days.
B. Slump, air content, concrete temperature, and unit weight shall be measured and recorded for each set of cylinders at the time of sampling.
C. Test results failing to meet specified strength requirements shall be reported to the Architect and
Structural Engineer within 24 hours. The Structural Engineer shall determine whether the concrete is acceptable or shall be removed and replaced.
Falkner Park Restroom Building | File No. 25-086-C | Section 03 30 00
END OF SECTION 03 30 00
DIVISION 05 – METALS
NOTE:
Division 04 – Masonry is entirely omitted from this Project Manual. There is no masonry of any kind in this project. The document proceeds directly from Division
03 to Division 05.
SECTION 05 50 00 – METAL FABRICATIONS
A. Miscellaneous metal fabrications required for the wood-framed restroom building, including anchor hardware, bearing plates, structural connectors, stainless steel accessories, and all miscellaneous steel as required by the structural and architectural drawings.
1.02 Submittals
A. Shop drawings showing fabrication details, dimensions, materials, and finishes for all custom fabrications. Product data for standard manufactured items (anchor bolts, hangers, plates). Mill certifications for structural steel.
2.01 Anchor Bolts and Holdown Hardware
A. Sill plate anchor bolts: 1/2-inch diameter, ASTM F1554 Grade 36, hot-dipped galvanized (HDG).
Embed minimum 7 inches into concrete. Space at maximum 6-inch on center; locate within 12 inches of each sill plate end. Provide standard plate washer and heavy hex nut.
B. Holdown anchors: As specified on structural drawings; Simpson Strong-Tie or equivalent; HDG or stainless steel. Install per manufacturer's written instructions and structural drawings. Holdown bolt embedment and nut engagement shall be inspected by the Special Inspector per Section 01 40 00.
2.02 Bearing Plates
A. Steel bearing plates at all post and column bearing locations on concrete: ASTM A36 steel; HDG finish;
sized per structural drawings. Set level in full mortar bed or shim to level; secure with anchor bolts or threaded rod as shown.
2.03 Structural Lintels and Headers
A. Structural steel lintels, if required at any exterior openings, shall be ASTM A36, sized per structural drawings, with…
This is the start of the file's text. The full file is on GovTribe.