VICK_322550A_Sched_of_Values_Replace_Cemetery_Shop_Roof.pdf

PDF 107 KB Posted

Attached to
RE-ROOF CEMETERY MAINTENANCE BLDG
Solicitation number
140P5225Q0026
Issued by

About this file

The document is a Schedule of Values (SOV) / Contract Price Schedule for the Cyclic Replacement of Cemetery Shop Roof at Vicksburg National Military Park. The schedule outlines eight contract line items (CLIs) for a roofing project, including mobilization, bonds, project conditions, removal of existing roof material, decking repairs, and installation of new underlayments and asphalt shingles. The document includes two optional line items for replacing asphalt shingle roofs and flashing for Quarters 2 and Quarters 4. Offerors are required to submit pricing for both base line items and option line items, with a warning that failure to do so may render the proposal unacceptable. The pricing structure allows for both lump-sum and unit-priced line items, with specific instructions for handling calculation errors and rounding of totals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM

NUMBER

Contract Line Item (CLI) Title Labor Materials TOTAL PRICE

1 Mobilization

2 Bonds

Project Conditions (safety, temp facilities/control, waste disposal, etc.)

4 Removal of existing roof material

5 Repair decking components

Install new underlayments, asphalt Shingles flashing, etc.

Option 1: Replace Quarters 2 asphalt Shingle roof and flashing

Option 2: Replace Quarters 4 asphalt Shingle roof and flashing

PROJECT TITLE: Cyclic Replacement of Cemetery Shop Roof

Schedule of Values (SOV) / Contract Price Schedule

Contract NUMBER:

PARK - PMIS: Vicksburg National Military Park (VICK) - 322550 DEVELOPED AREAS: Active Maintenance Complex

Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only, for allunit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price or labor/material price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.

TOTAL PROPOSED PRICE

VICK - 322550

CPS - 1

Price Schedule Template

LaborMobilization:
MaterialsMobilization:
TOTAL PRICEMobilization:
LaborBonds:
MaterialsBonds:
TOTAL PRICEBonds:
LaborProject Conditions safety temp facilitiescontrol waste disposal etc:
MaterialsProject Conditions safety temp facilitiescontrol waste disposal etc:
TOTAL PRICEProject Conditions safety temp facilitiescontrol waste disposal etc:
LaborRemoval of existing roof material:
MaterialsRemoval of existing roof material:
TOTAL PRICERemoval of existing roof material:
LaborRepair decking components:
MaterialsRepair decking components:
TOTAL PRICERepair decking components:
LaborInstall new underlayments asphalt Shingles flashing etc:
MaterialsInstall new underlayments asphalt Shingles flashing etc:
TOTAL PRICEInstall new underlayments asphalt Shingles flashing etc:
TOTAL PRICETOTAL PROPOSED PRICE:
TOTAL PRICEOption 1 Replace Quarters 2 asphalt Shingle roof and flashing:
TOTAL PRICEOption 2 Replace Quarters 4 asphalt Shingle roof and flashing:
Option 1 Replace Quarters 2 asphalt Shingle roof and flashing:
Option 2 Replace Quarters 4 asphalt Shingle roof and flashing:
1 Materials Replace Quarters 2 asphalt Shingle roof and flashing:
2 Materials Replace Quarters 4 asphalt Shingle roof and flashing: