Veterans Park East Lobe Expansion - Technical Specifications Summary

This is a comprehensive technical specification document issued by Okaloosa County Board of County Commissioners, Florida, for the Veterans Park East Lobe Expansion project (ITB PW 41-26). The project encompasses construction of a concrete walking path, boardwalk, statue pedestals, irrigation well, and landscaping improvements. The specifications cover all division work including civil, concrete, structural steel, miscellaneous metals, timber piles, rough carpentry, HDPE deck boards, and complete electrical systems. Key components include site preparation with erosion control, clearing and grubbing, earthwork and stabilized subgrade work, concrete sidewalks and curbs with integrally colored finishes, structural steel and miscellaneous metal fabrication, planting and irrigation systems with controllers and sprinklers, and comprehensive electrical distribution including panelboards, lighting poles, conduit raceways, grounding systems, and underground duct banks. The bid submission deadline is 3:00 PM CST on April 23, 2026, with the work defined by detailed plans and contract documents prepared by Mott MacDonald for the project number 502101659-011.

The specifications establish detailed performance requirements, material standards, and execution procedures in compliance with applicable codes including NFPA 70, ASTM standards, AASHTO guidelines, and Florida Department of Transportation standards. All electrical components must be listed and labeled by qualified testing agencies, with emphasis on grounding and bonding systems for both power and signal circuits. Material sourcing emphasizes single-source procurement where possible to ensure consistency, with specific manufacturer approvals required for critical items such as structural steel, electrical equipment, lighting poles, and treatment-preserving systems. The contractor bears responsibility for site safety, quality control testing, field inspections, load calculations, and compliance with all applicable federal, state, and local regulations. Special attention is directed to environmental protection measures including erosion control, stormwater management, and hazardous materials handling, with the contractor required to maintain protection of the site throughout the construction period and perform final cleanup and restoration of disturbed areas.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Veterans Park East Lobe Expansion

February 2026

POW107718

Text Box

Page iii of iv

Mott MacDonald 220 West Garden Street Suite 700 Pensacola

FL 32502

United States of America

T +1 (850) 484 6011 mottmac.com

Okaloosa County Board of County Commissioners Public Works Department 1759 S. Ferdon Boulevard Crestview, FL 32536

Veterans Park East Lobe Expansion

December 2024

POW107718

Text Box

Mott MacDonald | Veterans Park East Lobe Expansion

Page iv of iv

Issue and revision record

Revision Date Originator Checker Approver Description

Document reference: 502101659-011 |

This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.

Mott MacDonald Restricted

INDEX

Name of Project: Veterans Park – East Lobe Expansion

I. Technical Specifications:

Division 1 – Civil 01019 Mobilization and Demobilization 01050 Erosion Control 01110 Clearing and Grubbing 01240 Stabilized Subgrade 01300 Earthwork 01400 Traffic Signs 01500 Concrete Sidewalks, Curb, and Gutter 01540 Plants 01550 Planting Irrigation 01560 Integrally Colored Concrete 01660 Maintenance of Traffic

Division 3 – Concrete 03300 Cast-In-Place Concrete

Division 5 – Metals 05120 Structural Steel 05500 Miscellaneous Metals

Division 6 – Wood, Plastics, & Composites 02459 Timber Piles 06100 – Rough Carpentry 06531 – HDPE Deck Boards

Division 26 – Electrical 260500 Basic Electrical Requirements 260519 Low Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding 260529 Hangers and Supports for Electrical Systems 260533 Raceways and Boxes 260543 Underground Ducts and Raceways for Electrical Systems 260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 260553 Identification for Electrical Systems 262416 Panelboards 265613 Lighting Poles and Standards 265619 LED Exterior Lighting

Veteran’s Park- East Lobe Expansion MM Project No. 502101659-011

MOBILIZATION AND DEMOBILIZATION 01019 - 1

SECTION 01019

MOBILIZATION AND DEMOBILIZATION

PART 1 GENERAL

1.1 DESCRIPTION

A. Mobilization consists of preparatory Work and operations, including those necessary for movement of personnel, equipment, supplies and incidentals to and within the Work Area; the cost of bonds and any required insurance; and other pre-construction expenses necessary for start of the Work. All equipment transported to the Site by barge must be floating at all times during the transit to and from the Site of Work, i.e., no grounding of equipment will be permitted during transit.

1.2 ARBITRARY MOBILIZATION BY CONTRACTOR

A. The Owner will pay for the Schedule of Values Bid Item No. 1 “Mobilization and Demobilization” only once. Should the Contractor demobilize prior to completing the project, such demobilization and subsequent remobilization shall be at no additional cost to the Owner.

1.3 RATIO OF MOBILIZATION AND DEMOBILIZATION

A. Mobilization and Demobilization is a lump sum price, but will be paid to the Contractor on a percentage basis upon completion of mobilization to the Work Area for that particular pay period.

1.4 JUSTIFICATION OF MOBILIZATION COSTS

A. In the event that the Owner considers the amount of this item does not bear a reasonable relation to the cost of the Work in this Contract, the Owner may require the Contractor to produce cost data to justify this portion of the Bid. Failure to justify such price to the satisfaction of the Owner will result in payment of actual mobilization costs, as determined by the Owner at the completion of mobilization, and actual demobilization costs at the completion of demobilization, and payment of the remainder of this item in the final payment under this Contract. The determination of the Owner is not subject to appeal.

PART 2 PRODUCTS

2.1 NOT USED

PART 3 EXECUTION

3.1 NOT USED

MOBILIZATION AND DEMOBILIZATION 01019 - 2

3.2 Seeding: Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.

PART 4 MEASUREMENT AND PAYMENT

4.1 MEASUREMENT

A. No specific unit of measurement will apply to the lump sum Schedule of Values Bid Item No. 1 “Mobilization and Demobilization”.

4.2 PAYMENT

A. All costs associated with mobilization and demobilization of the entire Contractor's plant, equipment, personnel, and those of his/her Subcontractors and such others costs as may be denoted in the Contract Documents shall be paid for at the Contract lump sum price for Schedule of Values Bid Item No. 1 “Mobilization and Demobilization”.

END OF SECTION 01019

EROSION-POLLUTION CONTROL 01050 - 1

SECTION 01050

EROSION-POLLUTION CONTROL

PART 1 GENERAL

1.1 SCOPE

A. The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.

1.2 MATERIAL

A. All material furnished shall meet the requirements of the Erosion Control Plan in the Construction Documents.

1.3 EROSION AND SEDIMENT CONTROL MEASURES AND WORKS

A. The measures and works shall include, but are not limited to, the following:

• Staging of earthwork activities: The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.

• Seeding: Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.

• Mulching: Mulching to provide temporary protection of the soil surface from erosion.

• Diversions: Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.

• Stream crossings: Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.

• Sediment basins: Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s).

These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

EROSION-POLLUTION CONTROL 01050 - 2

• Sediment filters: Straw bale filters or geotextile sediment fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

• Waterways: Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

• Other: Additional protection measures as required by Federal, State, or local government.

1.4 CHEMICAL POLLUTION

A. The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to dispose of chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction activities. At the completion of the construction work, sumps shall be removed and the area restored to its original condition. Sump removal shall be conducted without causing pollution.

B. Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution.

1.5 AIR POLLUTION

A. The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.

B. Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.

C. All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.

EROSION-POLLUTION CONTROL 01050 - 3

1.6 MAINTENANCE, REMOVAL, AND RESTORATION

A. All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.

END OF SECTION 01050

CLEARING AND GRUBBING 01110 - 1

SECTION 01110

CLEARING AND GRUBBING

PART 1 GENERAL

1.1 DESCRIPTION

A. Clear and grub within the areas shown in the Plans. Remove and dispose of all trees, stumps, roots and other such protruding objects, buildings, structures, appurtenances, existing flexible asphalt pavement, concrete, and other facilities necessary to prepare the area for the proposed construction. Remove and dispose of all product and debris not required to be salvaged or not required to complete the construction. Perform miscellaneous work necessary for the complete preparation of the overall project site as specified in 110-10.

PART 2 STANDARD CLEARING AND GRUBBING

A. Work Included: Completely remove and dispose of all buildings, timber, brush, trees, stumps, roots, rubbish, debris, tree trimming, sawcutting, existing flexible pavement and base, drainage structures, culverts, and pipes. Remove all other obstructions resting on or protruding through the surface of the existing ground and the surface of excavated areas.

B. Perform standard clearing and grubbing within the following areas:

• All areas where excavation is to be done, including borrow pits, lateral ditches, right-of-way ditches, etc.

• All areas where roadway embankments will be constructed.

• All areas where structures will be constructed, including pipe culverts

2.1 DEPTHS OF REMOVAL OF ROOTS, STUMPS, AND OTHER DEBRIS

A. In all areas where excavation is to be performed, or roadway embankments are to be constructed, remove roots and other debris to a depth of 12 inches below the ground surface. Remove roots and other debris from all excavated material to be used in the construction of roadway embankment or roadway base. Plow the surface to a depth of at least 6 inches, and remove all roots thereby exposed to a depth of at least 12 inches.

Completely remove and dispose of all stumps within the roadway right-of-way.

• Remove all roots, etc., protruding through or appearing on the surface of the completed excavation within the roadway area and for structures, to a depth of at least 12 inches below the finished excavation surface.

CLEARING AND GRUBBING 01110 - 2

• Remove or cut off all stumps, roots, etc., below the surface of the completed excavation in borrow pits, material pits, and lateral ditches.

• In borrow and material pits, do not perform any clearing or grubbing within 3 feet inside the right-of-way line.

• Within all other areas where standard clearing and grubbing is to be performed, remove roots and other debris projecting through or appearing on the surface of the original ground to a depth of 12 inches below the surface, but do not plow or harrow these areas.

2.2 BOULDERS

A. Remove any boulders encountered in the roadway excavation (other than as permitted under the provisions of 120-7.2) or found on the surface of the ground. When approved by the Engineer place boulders in neat piles inside the right of way. The Contractor may stockpile boulders encountered in Department-furnished borrow areas, which are not suitable for use in the embankment construction, within the borrow area.

2.3 ASBESTOS CONTAINING MATERIALS (ACM) NOT IDENTIFED PRIOR TO WORK

A. When encountering or exposing any condition indicating the presence of asbestos, cease operations immediately in the vicinity and notify the Engineer, in accordance with 110- 6.5.

PART 3 SELECTIVE CLEARING AND GRUBBING

3.1 GENERAL

A. Remove and dispose of vegetation, obstructions, etc., as shown in the Plans. Provide acceptable fill material, and grade and compact holes or voids created by the removal of the stumps. Perform all selective clearing and grubbing in accordance with ANSI A300.

B. No staging, storing, stockpiling, parking or dumping will be allowed in selective clearing and grubbing areas. Only mechanical equipment related to selective clearing and grubbing activities will be allowed in selective clearing and grubbing areas. Protect trees to remain from trunk, branch and root damage.

3.2 PROTECTION OF PLANT PRESERVATION AREA

A. Areas to remain natural may be designated in the Plans. No clearing and grubbing, staging, storage, stockpiling, parking or dumping is allowed in these areas. Do not bring equipment into these areas.

CLEARING AND GRUBBING 01110 - 3

3.3 TREE PROTECTION BARRIER

A. Construct a tree protection barrier in accordance with FDOT Standard Plans Index 110 100 and the Plans. Maintain barrier for duration of the Contract.

3.4 TREE ROOT AND BRANCH PRUNING

A. When pruning cuts or root pruning to existing trees are shown in the Plans, work is to be supervised on site by an International Society of Arboriculture (ISA) Certified Arborist and performed in accordance with ANSI A300.

3.5 TREE REMOVAL

A. Remove trees as shown in the Plans.

3.6 PROTECTION OF THE PROPERTY REMAIN IN PLACE

A. Protect property to remain in place in accordance with 7-11.

3.7 REMOVAL OF BUILDINGS

A. PARTS TO BE REMOVED

• Completely remove all parts of the buildings, including utilities, plumbing, foundations, floors, basements, steps, connecting concrete sidewalks or other pavement, septic tanks, and any other appurtenances, by any practical manner which is not detrimental to other property and improvements. Remove utilities to the point of connection to the utility authority’s cut-in. After removing the sewer connections to the point of cut-in, construct a concrete plug at the cut-in point, as directed by the Engineer, except where the utility owners may elect to perform their own plugging.

Contact the appropriate utility companies prior to removal of any part of the building to ensure disconnection of services. Submit demolition schedule 15 working days before beginning any demolition or renovation of a building.

B. REMOVAL BY OTHERS

• Where buildings within the area to be cleared and grubbed are so specified to be removed by others, remove and dispose of any foundations, curtain walls, concrete floors, basements or other foundation parts which might be left in place after such removal of buildings by others.

CLEARING AND GRUBBING 01110 - 4

3.8 REMOVAL OF EXISTING BRIDGES

A. The work under this Article includes bridges, as defined below. Remove and dispose of the materials from existing bridges. Remove

• Those bridges and approach slabs, or portions of bridges, shown in the Plans to be removed,

• Those bridges and approach slabs, or portions of bridges, found within the limits of the area to be cleared and grubbed, and directed by the Engineer to be removed,

• Those bridges and approach slabs, or portion of bridges, which are necessary to be removed in order to complete the work, and

• Other appurtenances or obstructions which may be designated in the Contract Documents to be included as an item of payment for the work under this Article.

Submit schedule information and demolition plan for approval 15 working days before beginning any demolition or renovation of any structures.

3.9 METHOD OF REMOVAL

A. GENERAL

• Remove the structures in such a way so as to leave no obstructions to any proposed new bridge or to any waterways. Pull, cut off, or break off pilings to the requirements of the permit or other Contract Documents, or if not specified, not less than 2 feet below the finish ground line. In the event that the Plans indicate channel excavation to be done by others, consider the finish ground line as the limits of such excavation. For materials which are to remain the property of the Department or are to be salvaged for use in temporary bridges, avoid damage to such materials, and entirely remove all bolts, nails, etc. from timbers to be so salvaged. Mark structural steel members for identification as directed.

B. REMOVAL OF STEEL MEMBERS WITH HAZRDOUS COATING

• Submit to the Engineer for approval the “Contractor’s Lead in Construction Compliance Program”, QP2 certification from the Society for Protective Coatings (SSPC) from the firm actually removing and disposing of these steel members before any members are disturbed.

• Vacuum power tool cleans any coated steel member to bare metal as defined by SSPC-SP11 a minimum of 4 inches either side of any area to be heated (e.g. torch cutting, sawing, grinding, etc.) in accordance with 29 CFR 1926.354. Abrasive blasting is prohibited.

CLEARING AND GRUBBING 01110 - 5

3.10 PARTIAL REMOVAL OF BRIGES

A. On concrete bridges to be partially removed and widened, remove concrete by manually or mechanically operated pavement breakers, by concrete saws, by chipping hammers, or by hydro-demolition methods. Do not use explosives. Where concrete is to be removed to neat lines, use concrete saws or hydro-demolition methods capable of providing a reasonably uniform cleavage face. If the equipment used will not provide a uniform cut without surface spalling, first score the outlines of the work with small trenches or grooves. For all demolition methods, submit for review and approval of the Engineer, a demolition plan that describes the method of removal, equipment to be used, types of rebar splices or couplers, and method of straightening or cutting rebar. In addition, for hydro-demolition, describe the method for control of water or slurry runoff and measures for safe containment of concrete fragments that are thrown out by the hydro-demolition machine.

3.11 AUTHORITY OF U.S. COAST GUARD

A. For bridges in navigable waters, when constructing the project under authority of a U.S.

Coast Guard permit, the U.S. Coast Guard may inspect and approve the work to remove any existing bridges involved therein, prior to acceptance by the Department.

3.12 ASBESTOS CONTAINING MATERIALS (ACM) NOT IDENTIFIED PRIOR TO THE

WORK

A. When encountering or exposing any condition indicating the presence of asbestos, cease operations immediately in the vicinity and notify the Engineer. Make every effort to minimize the disturbance of the ACM. Immediately provide provisions for the health and safety of all jobsite personnel and the public that may be exposed to any ACM.

Provisions shall meet all applicable Federal, State, and Local Rules and Regulations regarding potentially hazardous conditions due to ACM.

B. The Engineer will notify the District Contamination Impact Coordinator (DCIC) who will engage the services of the Department’s Contamination Assessment/Remediation Contractor (CAR). Provide access to the potential contamination area. Preliminary investigation by the CAR Contractor will determine the course of action necessary for site security and the steps necessary to resolve the contamination issue.

C. The CAR Contractor will perform an asbestos survey to delineate the asbestos areas and identify any staging or holding areas that will be needed for assessment or abatement of the asbestos material.

D. The CAR Contractor will maintain jurisdiction over activities within areas contaminated with ACM including staging and holding areas. The CAR Contractor will be responsible for the health and safety of workers within these delineated areas. Provide continuous access to these areas for the CAR Contractor and representatives of regulatory or enforcement agencies having jurisdiction.

CLEARING AND GRUBBING 01110 - 6

E. Coordinate with the CAR Contractor and Engineer to develop a work plan with projected completion dates for the final resolution of the contamination, in coordination with any regulatory agencies as appropriate. Use the work plan and schedule as a basis for planning the completion of all work efforts. The Engineer may grant Contract Time extensions according to the provisions of 8-7.3.2.

F. Cooperate with the CAR Contractor to expedite integration of the CAR Contractor’s operations into the construction project. Adjustments to quantities or to Contract unit prices will be made according to work additions or reductions on the part of the Prime Contractor in accordance with 4-3.

G. The Engineer will inform the Prime Contractor when operations may resume in the affected area.

3.13 REMOVAL OF EXISTING CONCRETE

A. Remove and dispose of existing rigid Portland cement concrete pavement, sidewalk, slope pavement, driveways, ditch pavement, curb, and curb and gutter, etc., B. Remove all gravity walls, noise/sound walls, retaining walls, MSE walls, perimeter walls, and roadway concrete barriers, where shown in the Plans. All ancillary elements of these concrete features being removed including, but not limited to, leveling pads, copings, reinforcing steel or straps, footings, etc, are incidental and included in the cost of the removal.

3.14 OWNERSHIP OF MATERIALS

A. Except as may be otherwise specified in the Contract Documents, take ownership of all buildings, structures, appurtenances, and other materials removed and dispose of them in accordance with 02110-9.

3.15 DISPOSAL OF MATERIALS

A. GENERAL

• Either stack materials designated to remain the property of the Department in neat piles within the right-of-way, load onto the Department’s vehicles, or deliver to location designated in the Plans. Dispose of timber, stumps, brush, roots, rubbish, and other material resulting from clearing and grubbing in areas and by methods meeting the applicable requirements of all Federal, State and Local Rules and Regulations. Do not block waterways by the disposal of debris. With the approval of the Engineer, wood chips may be evenly distributed to a depth of no more than one inch in designated areas in the Department’s right-of-way.

CLEARING AND GRUBBING 01110 - 7

B. BURNING DEBRIS

• Contractor shall submit a request in writing for any burning debris. County to approval burning prior to the Contractor starting any burning.

C. TIMBER AND CORPS

• The Contractor may sell any merchantable timber, fruit trees, and crops that are cleared under the operations of clearing and grubbing for his own benefit, subject to the provisions of 7-1.2, which may require that the timber, fruit trees, or crops be burned at or near the site of their removal, as directed by the Engineer. The Contractor is liable for any claims which may arise pursuant to the provisions of this Subarticle.

D. DISPOSAL OF TREATED WOOD

• Treated wood must be handled and disposed of properly during removal. Treated wood should not be cut or otherwise mechanically altered in a manner that would generate dust or particles without proper respiratory and dermal protection. The treated wood must be disposed of in at least a lined solid waste facility or through recycling/reuse. Treated wood shall not be disposed by burning or placement in a construction and demolition (C&D) debris landfill.

E. HAZARDOUS MATERIALS/WASTE

• Handle, transport, and dispose of hazardous materials/waste in accordance with all Federal, State, and Local Rules and Regulations including, but not limited to, the following:

• SSPC Guide 7

• Federal Water Pollution Control Act, and

• Resource Conservation and Recover Act (RCRA).

• Accept responsibility for the collection, sampling, classification, packaging, labeling, accumulation time, storage, manifesting, transportation, treatment, and disposal of hazardous materials/waste, both solid and liquid. Separate all solid and liquid waste and collect all liquids used at hygiene stations and handle as hazardous materials/waste. Obtain written approval from the Engineer for all hazardous materials/waste stabilization methods before implementation.

• Obtain an EPA/FDEP Hazardous Waste Identification Number (EPA/FDEP ID Number) before transporting and/or disposal of any hazardous materials/waste.

• List the Department as the generator for hazardous materials/waste resulting from removal or demolition of Department materials.

CLEARING AND GRUBBING 01110 - 8

• Submit the following for the Engineers’ approval before transporting, treatment or disposal of any hazardous materials/waste:

• Name, address and qualifications of the transporter,

• Name, address and qualifications of the treatment facility,

• Proposed treatment and/or disposal of all Hazardous Materials/Waste.

• EPA/FDEP Hazardous Waste Identification Number Application Form.

• Manifest forms.

• Transport all hazardous materials/waste in accordance with applicable Federal, State, and Local Rules and Regulations including, but not limited to, the 40 CFR 263 Standards. Submit all final Hazardous Materials/Waste manifest/bills of lading and certificates of disposal to the Engineer within 21 days of each shipment.

F. STEEL MEMBERS WITH HAZARDOUS COATING

• Dispose of steel members with hazardous coating in one of the following manners:

• Deliver the steel members and other hazardous waste to a licensed recycling or treatment facility capable of processing steel members with hazardous coating.

• Deliver the steel members with hazardous coating to a site designated by the Engineer for use as an offshore artificial reef. Deliver any other hazardous materials/waste to a licensed hazardous materials/waste recycling treatment facility.

• Dismantle and/or cut steel members to meet the required dimensions of the recycling facility, treatment facility or offshore artificial reef agency.

• All compensation for the cost of removal and disposal of hazardous materials/waste will be included in the Cost of Removal of Existing Structures.

G. CERTIFICATION OF COMPLIANCE

• Submit certification of Compliance from the firm actually removing and disposing of the hazardous materials/waste stipulating, the hazardous materials/waste has been handled, transported and disposed of in accordance with this Specification. The Certification of Compliance shall be attested to by a person having legal authority to bind the company.

CLEARING AND GRUBBING 01110 - 9

• Maintain all records required by this Specification and ensure these records are available to the Department upon request.

PART 4 MISCELLANEOUS OPERATIONS

4.1 WATER WELLS REQUIRED TO BE PLUGGED

A. Fill or plug all water wells within the right-of-way, including areas of borrow pits and lateral ditches, that are not to remain in service, in accordance with applicable Federal, State, and Local Rules and Regulations.

B. Cut off the casing of cased wells at least 12 inches below the ground line or 12 inches below the elevation of the finished excavation surface, whichever is lower. Water wells, as referred to herein, are defined either as artesian or non-artesian, as follows:

• An artesian well is an artificial hole in the ground from which water supplies may be obtained and which penetrates any water-bearing rock, the water in which is raised to the surface by natural flow or which rises to an elevation above the top of the water-bearing bed. Artesian wells are further defined to include all holes drilled as a source of water that penetrate any water-bearing beds that are a part of the artesian water system of Florida, as determined by representatives of the applicable Water Management District.

• A non-artesian (water-table) well is a well in which the source of water is an unconfined aquifer. The water in a non-artesian well does not rise above the source bed.

4.2 LEVELING TERRAIN

A. Within the areas between the limits of construction and the outer limits of clearing and grubbing, fill all holes and other depressions, and cut down all mounds and ridges.

Make the area of a sufficient uniform contour so that the Department’s subsequent mowing and cutting operations are not hindered by irregularity of terrain. Perform this work regardless of whether the irregularities were the result of construction operations or existed originally.

4.3 MAILBOXES

A. When the Contract Documents require furnishing and installing mailboxes, permit each owner to remove the existing mailbox. Work with the Local Postmaster to develop a method of temporary mail service for the period between removal and installation of the new mailboxes. Install the mailboxes in accordance with the FDOT Standard Plans.

CLEARING AND GRUBBING 01110 - 10

PART 5 METHOD OF MEASUREMENT

5.1 CLEARING AND GRUBBING

A. LUMP SUM PAYMENT

• Price and payment will be full compensation for all clearing and grubbing required for the construction of the drainage and roadway items and ditches, channel changes, or other outfall areas, and any other clearing and grubbing indicated, or required for the construction of the entire project, including all necessary hauling, furnishing equipment, equipment operation, furnishing any areas required for disposal of debris, leveling of terrain, tree removal, and the landscaping work of trimming, etc.

B. PAYMENT ITEMS

• Payment may include but not limited to these items below be made under:

• Clearing and Grubbing

• Removal of Existing Bridges

• Removal of Existing Concrete

• Plugging Water Wells

• Plugging Water Wells

• Mailboxes

• Tree Protection Barrier

• Tree Root and Tree trimming

• Tree Removal

• Saw cutting

• Disposal and Disposal Fees

• Selective clearing around statues

END OF SECTION 01110

STABILIZED SUBGRADE 01240 - 1

SECTION 01240

STABILIZED SUBGRADE

PART 1 GENERAL

1.1 SCOPE

A. Where it fails to meet the specified Limerock Bearing Ratio (LBR) 40, stabilize the subgrade to the uniformity, density and bearing ratio specified hereinafter. Stabilize parking areas to a minimum depth of 12 inches below the bottom grade of the base material and to a width 6 inches outside each pavement or concrete curb edge. Stabilize roadways and streets to 12 inches unless otherwise indicated on the Drawings.

B. Definitions: Use FDOT Type B stabilization as described hereinafter to obtain the required bearing ratio by the addition and mixing in of suitable stabilizing material.

PART 2 MATERIAL

2.1 GENERAL

A. Use either Commercial Materials or Local Materials as defined hereunder, at the Contractor's option.

B. Commercial Materials: Limerock, limerock overburden or crushed shell meeting the following requirements:

• At least 97 percent by weight of the total material passing a 1 inch screen and at least 50 percent by weight of the total material retained on the No. 4 sieve.

• Not more than 7.5 percent by weight of the total material passing the No. 200 sieve as determined by washing the material over the sieve

• In the event that the shell meets the above requirements without crushing, crushing will not be required. The use of steamed shell will not be permitted.

C. STABILIZATION

• Determine bearing value by the Limerock Bearing Ratio (LBR) Method.

• After grading operations are substantially complete, determine the quantity (if any) of selected stabilizing material to be added for compliance with the bearing value requirements.

• Ensure that the finished subgrade meets the bearing value requirements, regardless of the quantity of stabilizing materials necessary to be added.

STABILIZED SUBGRADE 01240 - 2

PART 3 EXECUTION

3.1 PREPARATION

A. GENERAL

• Prior to the beginning of stabilizing operations, complete the subgrade to the lines, grades and cross section shown in the plans.

• Stabilize the subgrade in one course, unless the equipment and methods being used do not provide the required uniformity, particle size limitation, compaction and other desired results, in which case, perform the processing in more than one course as approved by the Engineer.

3.2 APPLICATION

A. Stabilizing Material: Spread the stabilizing material uniformly over the area to be stabilized by means of mechanical material spreaders, except that where use of such equipment is not practicable other means of spreading may be used, but only upon written approval of the Engineer.

B. Mixing: By means of rotary tillers, or other equipment meeting the approval of the Engineer, thoroughly mix the subgrade throughout the entire depth and width of the area to be stabilized.

C. Maximum Particle Size Of Mixed Materials: At the completion of mixing, check that all particles of material within the limits of the area to be stabilized pass a 3 ½-inch ring.

Remove from the stabilized area any particles not meeting this requirement or break them down so as to meet this requirement.

D. Compaction: After the mixing operations have been completed and requirements for bearing value, uniformity and particle size have been satisfied, compact the stabilized area to a density of not less than 98% of maximum density as determined by AASHTO T 180. Compact the materials at a moisture content permitting the specified compaction. If the moisture content of the material is improper for attaining the specified density, either add water or allow drying until the proper moisture content for the specified compaction is reached.

E. Finish Grading: Grade and shape the completed stabilized subgrade to conform with the finished lines, grades and cross-section indicated in the Drawings.

F. Quality Assurance:

• After the stabilizing and compacting operations have been completed, check that the subgrade is firm and substantially unyielding, to the extent that it will support construction equipment and will have the bearing value required.

STABILIZED SUBGRADE 01240 - 3

• Remove and replace with suitable material all soft and yielding material, and any other portions of the sub-grade which will not compact readily, and bring the whole subgrade to line and grade, with proper allowance for subsequent compaction.

G. Maintenance Of Completed Subgrade: Upon completion, maintain the subgrade free from ruts, depressions and any damage resulting from the hauling or handling of materials, equipment, tools, etc. Maintain the required density until the subsequent base or pavement is in place. Make any repairs, replacement, etc., of curb and gutter, sidewalk, etc., which might become necessary in order to recompact the subgrade in the event of underwash or other damage. Construct and maintain ditches and drains as necessary to protect the completed subgrade from damage by storm water.

3.3 FIELD QUALITY CONTROL

A. Bearing Value Requirements:

• General: Obtain bearing value samples and provide test results to the Engineer at completion of satisfactory mixing of the stabilized area. For any area where the bearing value obtained is deficient from the value indicated in the Drawings, in excess of the tolerances established herein, spread and mix in additional stabilizing material as specified above for the full width of the roadway being stabilized and longitudinally for a distance of 50 feet beyond the limits of the area in which the bearing value is deficient. Pay for all retesting required until subgrade meets the specified requirements.

• Tolerances In Bearing Value Requirements: A undertolerance of 5.0 from the specified bearing value of LBR 40 will be allowed as based on tests performed on samples obtained after mixing operations have been completed.

END OF SECTION 01240

EARTHWORK 01300-1

SECTION 01300

EARTHWORK

PART 1 GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.

B. Florida Department of Transportation, Standard Specifications for Road and Bridge Construction (FDOT Specs), Section 120, latest edition. Work shall comply with requirements of FDOT Specs as modified herein.

C. General Exceptions: Any reference to FDOT Standard Specifications for Road and Bridge Construction (latest edition) Division I General Requirements & Covenants shall be excluded and not applicable to any specification referred herein, or otherwise listed in this document.

1.2 SUMMARY

A. This Section includes preparing and grading sub-grades for pavements and curbs.

B. The following Sections contain requirements that relate to this Section.

• Section 110 "Clearing & Grubbing" for clearing, grubbing, and tree protection.

1.3 DEFINITIONS

A. EXCAVATION

• The removal of material encountered to sub-grade elevations and the reuse or disposal of materials removed.

B. SUB-GRADE

• The uppermost surface of an excavation or the top surface of a fill or backfill immediately below sub-base, base, drainage fill, or topsoil materials.

C. BORROW

• Soil material obtained off-site when sufficient approved soil material is not available from excavations.

EARTHWORK 01300-2

D. SUBBASE COURSE

• The layer placed between the subgrade and base course in a paving system or the layer placed between the subgrade and surface of a pavement or sidewalk or the existing layer beneath this base.

E. BASE COURSE

• The layer placed between the subbase and surface pavement in a paving system.

F. UNAUTHORIZED EXCAVATION

• Removing materials beyond indicated subgrade elevations or dimensions without direction by the Engineer. Unauthorized excavation, as well as remedial work directed by the Engineer, shall be at the Contractor's expense.

G. STRUCTURES

• Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below ground surface.

H. UTILITIES

• On-site above ground utilities, overhead utilities and underground utilities including: pipes, conduits, ducts, and cables, as well as related appurtenances and underground services within building lines.

I. UNSUITABLE MATERIAL

• Any material such as muck, wood, rock, organic peat, garbage, very fine soil particles unsuitable for compaction, and any other material that is considered unsuitable by the County or its representative shall be considered unsuitable.

J. TOPSOIL

• Topsoil is defined as friable clay loam surface soil found normally to a depth of at least 4 inches. Satisfactory topsoil is reasonably free of subsoil, clay lumps, stones, and other objects over 2 inches in diameter, and without weeds, roots, and other objectionable material.

1.4 SUBMITTALS

A. GENERAL

EARTHWORK 01300-3

• Submit the following in accordance with Section 1300, "Submittals and the General Conditions.”

B. PRODUCT DATA AND SAMPLES OF THE FOLLOWING

• 1-lb representative samples of each proposed fill and backfill soil material from borrow sources as selected by the Engineer.

• 12-by-12-inch sample of filter fabric.

C. Test Reports: In addition to test reports required under field quality control, submit the following original copy directly to the Engineer from the testing services, with a copy to the Contractor:

• Laboratory analysis of each soil material proposed for fill and backfill from borrow sources.

• One optimum moisture-maximum density curve for each soil material.

• Report of actual unconfined compressive strength and/or results of bearing tests of each stratum tested.

1.5 QUALITY ASSURANCE

A. CODES AND STANDARDS

• Perform earthwork complying with all requirements of authorities having jurisdiction. All material and construction methods shall be in accordance with the Standard Specifications for Road and Bridge Construction, State of Florida, Department of Transportation, latest edition.

B. TESTING AND INSPECTIONS SERVICE

• During earthwork operations employ, at the Contractor's expense, a qualified independent geotechnical engineering testing agency, under the direction of a Professional Engineer, licensed in the State of Florida to classify, perform soil tests, and provide inspection services for quality control. All proposed borrow soils will require the testing agency to verify that soils comply with specified requirements and to perform required field and laboratory testing. Contractor shall replace materials removed for testing purposes. Should any work or materials fail to meet the requirements set forth in the plans and specifications, contractor shall pay for re-testing of same.

EARTHWORK 01300-4

C. TESTING LABORATORY QUALIFICATIONS

• To qualify for acceptance, the geotechnical testing laboratory must demonstrate to the Engineer’s satisfaction, based on evaluation of laboratory-submitted criteria, that it has the experience and capability to conduct required field and laboratory geotechnical testing without delaying the progress of the work.

1.6 PROJECT CONDITIONS

A. SITE INFORMATION

• Data in the subsurface investigation report was used for the basis of the design and are available to the contractor for information only. Conditions are not intended as representations or warranties of accuracy or continuity between soil borings. The Engineer/ Owner will not be responsible for interpretations or conclusions drawn from this data by the contractor.

B. EXISTING UTILITIES

• Contractor is responsible for contacting all utility companies to obtain locations of all existing utilities or obstructions that he may encounter during construction. After location of utilities by the appropriate utility company, it is the Contractor's liability to protect all such utility lines, including service lines and appurtenances, and to replace at his own expense any that may be damaged by the Contractor's equipment or forces during construction of the Project.

• Provide a minimum of 48-hours' notice to the Engineer and receive written notice to proceed before interrupting any utility.

• The contractor is responsible for contacting all utility companies to verify locations of all existing utilities, utility-related obstructions, or utility relocations that he may encounter during construction.

• Adequate provision shall be made for the flow of existing sewers, drains, and water courses encountered during construction, and structures which may be disturbed shall be satisfactorily restored by the Contractor.

C. Should uncharted, or incorrectly charted, piping or other utilities be encountered during the course of the work, consult Engineer immediately for directions. Cooperate with owner and utility companies in keeping respective services and facilities in operation.

1.7 SOIL MATERIALS

A. GENERAL

EARTHWORK 01300-5

• Soils used as fill shall be clean sands, similar to existing site soil, with less than 5% passing the number 200 sieve when existing subgrade conditions are considered wet as per the County and/or its representative. Soils as described above with less than 12% passing the number 200 sieve and meeting the requirements of Section 902-6 of the FDOT Specifications may be used when existing subgrade conditions are considered dry as per the County and/or its representative. The sand shall have a maximum dry density of at least 100 pounds per cubic foot, according to the Standard Proctor compaction test, AASHTO T-99, ASTM D698. Provide approved borrow soil materials from off-site when sufficient satisfactory soil materials are not available from excavations. Provide laboratory certification that soils meet requirements of specifications.

B. If the Contractor elects to import any materials other than that excavated on site, then he will do so only with Engineer’s approval and at his own expense, unless separate payment for such items are called for in these specifications.

C. SUB-BASE MATERIAL

• Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand, ASTM D 2940, with at least 95 percent passing a 1- 1/2-inch sieve, and not more than 8 percent passing a No. 200 sieve.

1.8 DEWATERING

A. Prevent surface water and subsurface or ground water from entering excavations, from ponding on prepared subgrades, and from flooding project site and surrounding area.

B. Protect subgrades and foundation soils from softening and damage by rain or water accumulation.

C. The Contractor shall prevent the accumulation of water in excavated areas and shall remove by pumping or other means any water that accumulates in the excavation. The Contractor shall prevent the accumulation of water in both structural and trench excavations and shall remove by well point system or by other means water which accumulates. The Contractor shall provide, install and operate a suitable and satisfactory dewatering system. The contractor shall include the cost of this pumping equipment and work in the unit price bid for the work.

D. Establish and maintain temporary drainage ditches and other diversions outside excavation limits to convey rainwater and water removed from excavations to collection or runoff areas. Do not use trench excavations as temporary drainage ditches.

1.9 EXCAVATION

A. EXPLOSIVES

EARTHWORK 01300-6

• Not permitted.

B. UNCLASSIFIED EXCAVATION

• Excavation is unclassified and includes excavation to required subgrade elevations regardless of the character of materials and obstructions encountered.

C. Strip topsoil to whatever depths encountered in a manner to prevent intermingling with underlying subsoil or other objectionable material. Remove heavy growths of grass from areas before stripping. Where existing trees are indicated to remain, leave existing topsoil in place within drip lines to prevent damage to root systems.

1.10 STABILITY OF EXCAVATION

A. Comply with local codes, ordinances, and requirements of authorities having jurisdiction to maintain stable excavations.

B. All excavation work shall conform to all applicable OSHA Publications, latest editions.

The Contractor's method of providing protective support to prevent cave-ins shall conform to OSHA requirements. Slope excavations, shoring, and trench box usage in the field must be based on tabulated data and designed by the Contractor. The contractor is solely responsible for job site safety.

1.11 EXCAVATION FOR STRUCTURES

A. FOOTINGS AND FOUNDATIONS

• Do not disturb bottom of excavation. Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.

B. PILE FOUNDATIONS

• Stop excavations from 6 inches to 12 inches above bottom of footing before piles are placed. After piles have been driven, remove loose and displaced material.

Excavate to final grade, leaving solid base to receive concrete pile caps.

C. Excavation for Underground Tanks, Basins, and Mechanical or Electrical Appurtenances: Excavate to elevations and dimensions indicated within a tolerance of plus or minus 0.10 foot. Do not disturb bottom of excavations intended for bearing surface.

1.12 EXCAVATION FOR WALKS AND PAVEMENT

EARTHWORK 01300-7

A. Excavate surfaces under walks and pavements to indicated cross sections, elevations, and grades.

1.13 EXCAVATION FOR STORMWATER SYSTEMS

A. Excavate and compact the backfill of trenches to the densities specified for embankment or subgrade, as applicable, and in accordance with the requirements of Section 2600.

1.14 STORAGE OF SOIL MATERIALS

A. Stockpile excavated materials acceptable for backfill and fill soil materials, including acceptable borrow materials. Stockpile soil materials without intermixing. Place, grade and shape stockpiles to drain surface water. Cover to prevent wind-blown dust.

B. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees.

C. Stockpile topsoil and other reusable soils in storage piles in areas indicated or directed.

Construct storage piles to provide free drainage of surface water. Cover storage piles, if required, to prevent erosion.

1.15 BACKFILL

A. Backfill excavations promptly, but not before completing the following:

• Acceptance of construction below finish grade including, where applicable, filter fabric, installation, and gravel bedding.

• Surveying locations of underground utilities for record documents.

• Testing, inspecting, and approval of underground utilities.

• Removal of trash and debris from excavation.

• Removal of temporary shoring, bracing, and sheeting unless specified to remain.

B. No backfill material shall be placed, spread or rolled during unfavorable weather conditions. When the work is interrupted by heavy rain, backfill operations shall not be resumed until the moisture content and density of the fill are as previously specified.

1.16 FILL

A. PREPARATION

EARTHWORK 01300-8

• Remove vegetation, topsoil, debris, wet and unsatisfactory soil materials, obstructions, and deleterious materials from ground surface prior to placing fills.

Plow strip, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing surface. In order to insure proper bond and prevent slipping between the original ground and fill, the surface of the original ground shall be scarified to a depth of at least three inches. Each layer of fill material shall be compacted until the required density is achieved.

B. When sub grade or existing ground surface to receive fill has a density less than that required for fill, break up ground surface to depth required, pulverize, moisture-condition or aerate soil and re-compact to required density.

C. Place fill material in layers to required elevations for each location listed below.

• Under…

This is the start of the file's text. The full file is on GovTribe.