Vendor Questions B-47557.pdf
PDF 134 KB Posted
- Attached to
- Lake Michigan Boat and Trailer Des Plaines
- Solicitation number
- 25-532EPA-WATER-B-47557
- Issued by
- Cook County, Illinois
About this file
This document is a Questions and Answers (Q&A) file from the Illinois Environmental Protection Agency (Illinois EPA) for the Lake Michigan Boat and Trailer Des Plaines procurement, identified by solicitation number 25-532EPA-WATER-B-47557. The document addresses two key vendor inquiries: first, confirming that the delivery date of September 30, 2025, is firm, and second, clarifying the payment terms, which specify that payment will be made only after complete delivery and successful water testing, with no options for milestone payments as outlined in section 2.3 of the Transportation and Delivery terms.
The Q&A document provides critical clarification for potential bidders about the contract's timeline and payment structure, ensuring vendors understand the strict delivery expectations and payment conditions. While the document itself is brief, it complements the broader procurement details for a specialized marine vessel intended for water quality monitoring activities on Lake Michigan, reinforcing the Illinois EPA's precise requirements for vendors participating in this procurement opportunity.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Blank vendor-disclosure~1.docx | DOCX document | |
| Blank ipg-active-registered-vendor-disclosure~1.docx | DOCX document | |
| B-47557 Invitation for Bid Vendor Instructions and Requirements.docx | DOCX document | |
| Lake Michigan Monitoring Vessel 2025 - Contract.docx | DOCX document | |
| B-47557 invitation-for-bid-offer-to-the-state-of-illinois.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lake Michigan Boat and Trailer Des Plaines
25-532EPA-WATER-B-47557
Questions and Answers
1. Q: Is the September 25, 2025, delivery date firm?
A: The September 30, 2025, delivery date is firm.
2. Q: Will milestone payments be made?
A: Payment will be made after completion of delivery and successful water test. Per section 2.3 under Transportation and Delivery. There are no options for milestone payments.