Vendor Questions and Agency Responses B-52317.docx
DOCX document 20 KB Posted
- Attached to
- ReBid Scrap Metal and Material Removal
- Solicitation number
- 26-426DOC-CENTO-B-52317
- Issued by
- Lee County, Illinois
About this file
This document contains vendor questions and agency responses for the Illinois Department of Corrections' rebid for scrap metal and material removal services at Dixon Correctional Center in Dixon, Illinois. The project involves the removal of scrap metal and materials from the correctional facility, with an estimated total weight of 77 tons. Per RFQ Section 1.2.2, the awarded vendor will have a maximum of 14 calendar days for discussion and planning, followed by 14 calendar days to complete the required removal services. No site visit is permitted prior to contract award; however, vendors may request additional project photographs for estimation purposes, which the agency has provided in PDF format to supplement the original portfolio documentation.
The agency's responses address key vendor concerns regarding project scope and execution logistics. Vendors are responsible for bringing their own equipment to the site and must be prepared to begin work immediately upon award if they do not require the full 14-day planning period. The document does not address pricing terms, set-asides, funding sources, or other financial considerations, as it serves solely to clarify scope and procedural requirements for prospective bidders.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Portfolio1.pdf | ||
| Pictures.pdf | ||
| Dixon Scrap Metal B-52317 RFQ~1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ILLINIOS DEPARTMENT OF CORRECTIONS
Vendor Questions and Agency Responses
26-426DOC-CENTO-B-52317
ReBid Scrap Metal and Material Removal
Vendor Question: The document "Portfolio 1.pdf" on this bid attachment is not opening so it would be nice if you can add photos of scrap materials that need to be removed.
Agency Answer: Attached another PDF of the pictures.
Vendor Question: Please let us know the total weight for all scrap metal and material for proper estimate.
Agency Answer: On the line item we have estimated 77 Tons.
Vendor Question: Please let us know if we can visit the area for a better estimate and equipment we have to bring on the site.
Agency Answer: There will be no site visit prior to award. Per the RFQ Section 1.2.2. 1.2.2. “Awarded Vendor shall have at most 14 calendar days to discuss and plan and another 14 calendar days to complete the required services per this Contract. Note, if Vendor doesn’t need the full 14 days to discuss and plan, starting early is permitted.”
File details come from the government source that posted it. Updated .