VA797H-17-R-0032-0007000.docx
DOCX document 30 KB Posted
- Solicitation number
- VA797H17R0032
About this file
VA797H-17-R-0032 0007 VA797H-17-R-0032 0007.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36H79718C0012-000.docx | DOCX document | |
| VA797H-17-R-0032-0010000.docx | DOCX document | |
| VA797H-17-R-0032-0009000.docx | DOCX document | |
| VA797H-17-R-0032-0008000.docx | DOCX document | |
| VA797H-17-R-0032-0006000.docx | DOCX document | |
| VA797H-17-R-0032-0006001.docx | DOCX document | |
| VA797H-17-R-0032-0005000.docx | DOCX document | |
| VA797H-17-R-0032-0004000.docx | DOCX document | |
| VA797H-17-R-0032-0004001.pdf | ||
| VA797H-17-R-0032-0003000.docx | DOCX document | |
| VA797H-17-R-0032-0003001.pdf | ||
| VA797H-17-R-0032-00002000.docx | DOCX document | |
| VA797H-17-R-0032-00001000.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2.
AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF
CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV.
11/2016) is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR
43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS
ENTERED INTO
PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14.
DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME
AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS
OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 07-02-2018 644-B88011 none Department of Veterans Affairs NAC, NCS, HTME Contracts P.O. Box 76, 1st Avenue, One Block North of Cermak Hines IL 60440 Department of Veterans Affairs OPAL/ National Acquisition Center Building 37 1st Avenue, One Block North of Cermak Hines IL 60141 To all Offerors/Bidders
VA797H-17-R-0032
05-16-2018
X X X X The purpose of thsi amendment is to provide the Request for Information (RFI) Clarifications to all offerors.
The response date remains unchanged.
All other terms and conditions remain unchanged.
Donnie Reeves Contracting Officer Continuation
LOUISVILLE, KY REQUEST FOR INFORMATION (RFI) # 4
B.2 SCHEDULE OF SUPPLIES & DELIVERY:
1. Item 1 Trade-In – Soiled Monorail System
Q- There is a (Qty. 1) Transcell recessed-type floor scale with model TL-500E SS indicator panel being utilized to weigh filled sling carts prior to slings being lifted to overhead storage. Is this scale system included in the trade-in?
Answer – Yes. This scale system is included in the trade-in.
If yes, is the successful bidder required to remove the imbedded steel coping frame, floor-mounted indicator stand & under slab conduit and infill the pit/floor to match existing floor slab construction?
Answer – Yes. The contractor is required to remove the imbedded steel coping frame, floor-mounted indicator stand & under slab conduit and infill the pit/floor to match existing floor slab construction.
B.4 STATEMENT OF WORK:
A. Project Special Requirements:
1. Does the reference to “any changes to the building to accommodate installation of new equipment” include that the successful bidder’s equipment layout design shall maintain the posted building evacuation routes for the clean area (i.e. to the garage doors located by the clean monorail hoist where the wash cloth station is located) and for the soil area (i.e. to the exterior door adjacent to garage door by cart washer)?
Answer – Yes. The contractor’s equipment layout design shall maintain the posted building evacuation routes for the clean area (i.e. to the garage doors located by the clean monorail hoist where the wash cloth station is located) and for the soil area (i.e. to the exterior door adjacent to garage door by cart washer).
B. General Installation Requirements:
1. Laundry B7 Natural Gas Supply - Amendment 0002 states the successful bidder is responsible for providing sufficient natural gas to the laundry system [assumes Item 2 & 3 with gas-heated equipment will be awarded to one bidder for sole responsibility]. The existing gas distribution system, in part, currently serves (3) production dryers, (2) non-production dryers, (2) flatwork ironers, (1) garment finisher and (1) hot water heater. All equipment are served with individual regulators with pressure settings accommodating the existing supply pressure/volumes. The existing gas header with regulator serving the (2) non-production tumblers is sized for the two specific machines (same with the existing cold water line with back flow prevention for fire suppression). A new branch line from the existing gas main will be required to supply the (3) new non-production tumblers. There is an active flow meter device marked # BLDG-7-NG-01 with wall-mounted recording indicator installed in the main gas supply downstream of the building regulator.
Q1- As a result of the increased gas volume required by the addition of the new Item 3 drying tumblers and potentially the new Item 2 production dryers, if the new total flow volume required for the connected equipment system exceeds the capacity of this meter, who is responsible for sizing, furnishing, installing and calibrating the new meter system, the VA or the successful bidder?
Answer – It is contractor’s responsibility for any increased gas volume required by the addition of the new Item 3 drying tumblers and potentially the new Item 2 production dryers; if the new total flow volume required for the connected equipment system exceeds the capacity of this meter.
Q2- If installation changes are made to the existing gas distribution system, is the successful bidder also responsible for recalibrating the regulators serving existing equipment affected by the design modification?
Answer – Yes. It is the contractor’s responsibility for recalibrating the regulators serving existing equipment affected by the design modification.
Q3- If multiple awards are made for Item 2 and Item 3, which successful bidder is responsible for the natural gas supply modifications? (Note: both items require installation of new gas-heated dryers that will impact the existing gas distribution system. The existing gas header with regulator serving the (2) non-production tumblers is sized for the two specific machines. A new branch line from the existing main will be required to supply the (3) new non-production dryers.)
Answer – Items 2 and 3 shall be awarded together to ensure there is no misunderstanding as to whom is responsible for new gas connections.
ATTACHMENT – TECHNICAL/PERFORMANCE SPECIFICATIONS:
1. ITEM #2 – CONTINUOUS WASH EXTRACT TUNNEL SYSTEM a. Para. 1A p (p.5) States “connection points for water and compressed air shall be from the main headers in the mechanical room.”
Q- Clarify if the successful bidder for Item 2 is required to:
a. Replace the existing hot & tempered process water header piping, hangers, and bracing with new that extend from the header connection points within the Basement Mechanical Room through the pipe space up to the first floor and connect to the new tunnel washer; and, Answer – Yes. The contractor is required to replace the existing hot & tempered process water header piping, hangers, and bracing with new equipment that extend from the header connection points within the Basement Mechanical Room through the pipe space up to the first floor and connect to the new tunnel washer.
b. That work includes replacing the existing +20 year old hot and tempered water headers and branch piping to the cart washer and five (5) existing non-production washer extractors and installing new ball-type isolation valves and water hammer arrestors at each machine connection?
Answer – Yes. The contractor is required to do all work that includes replacing the existing +20-year-old hot and tempered water headers and branch piping to the cart washer and five (5) existing non-production washer extractors. Also, installing new ball-type isolation valves and water hammer arrestors at each machine connection
b. CWES Interface with Existing Process Water System:
Q – Is the existing 2” temperature blending valve assembly furnished with the Thermal Engineering (TEA) process water system required to be installed in the water inlet connections for the new tunnel washer and the control valves interconnected with the TEA waste water heat recovery system for the purpose of automatically modulating the hot & tempered water flows for the desired tunnel inlet water temperatures?
Answer – Yes. the existing 2” temperature blending valve assembly furnished with the Thermal Engineering (TEA) process water system is required to be installed in the water inlet connections for the new tunnel washer. The control valves interconnected with the TEA waste water heat recovery system for automatically modulating the hot & tempered water flows for the desired tunnel inlet water temperatures.