VA_WAC Fire Suppression - Bid Set Drawings.pdf
PDF 46 MB Posted
- Attached to
- Y1DA--674A4-20-110 Improve Fire Suppression System - Waco Federal contract opportunity
- Solicitation number
- 36C25722B0008
- Issued by
- Department of Veterans Affairs
About this file
This solicitation is for a construction contract to improve the fire suppression system at the Doris Miller VA Medical Center in Waco, Texas. The Department of Veterans Affairs will award a firm-fixed-price contract with an estimated value between $5-10 million through an invitation for bid process. Contractors will provide all labor, materials and equipment to upgrade the fire suppression system in specified buildings by November 15, 2022 based on provided specifications and drawings. Work includes general construction, fire suppression components, sprinkler heads and associated repair work over a 365-day performance period. This requirement is set aside 100% for Service-Disabled Veteran Owned Small Businesses.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25722B0008 0002.docx | DOCX document | |
| Prebid Sign in Sheet.pdf | ||
| 36C25722B0008 0001.docx | DOCX document | |
| 36C25722B0008_1.docx | DOCX document | |
| VA_WAC Fire Suppression - Bid Set Narrative.pdf | ||
| 674A4-20-110 Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Above finished floor AFF Acoustic ACST Acoustic Panel Ceiling APC Addendum ADD Alternate ALT Aluminum AL Angle L Approximate APPROX Architecture, architectural ARCH Asbestos ASB Asphalt ASPH Assistant ASST Association ASSN Automatic AUTO Average AVG Base plate BP Basement BSMT Beam BM Bearing BRG Bedroom BR Benchmark BM Board BD Boiler BLR Bottom BOT Brick BRK Building line BL Building BLDG Built-up-roof BUR Cabinet CAB Carpet CPT Catalog CAT Ceiling height CH Ceiling CLG Center CTR Centerline CL Ceramic Tile CT Ceramic CER Chalkboard CB Clear CLR Closet CLO Coated CTD Cold rolled CR Column COL Company CO Composition COMP Concrete Masonry Unit CMU Concrete CONC Construction joint CJ Construction CONSTR "Continue, Continuous" CONT Corridor CORR Countersink CSK Cubic CU Curve(d) CRV Dampproofing DP Degree DEG Department(al) DEPT Detail DET Diagonal DIAG Diameter DIA Dimension DIM Dishwasher DW Dispenser DISP Door DR Double DBL Double-hung DH Down DN Downspout DS Drain DR Drawing DWG Each EA East E Electric Water Cooler EWC "Electric, electrical" ELEC Elevation EL Elevator ELEV Engineer ENGR Entrance ENTR Equal EQ Equipment EQUIP Exhaust EXH Existing EXIST Expansion joint EXP JT Exposed EXP Exterior EXT Fabricate FAB Face of Stud F. OF S.
Fan Coil Unit FCU Fiberglass-reinforced plastics FRP Finish FIN Finished Floor FF Fire Extinguisher FE Fire Extinguisher & Cabinet FEC Fire Retardant Treated FRT Fireproof FPRF Fixture FXTR Flange FLG Flashing FL Floor FL Floor drain FD Flooring FLG Fluorescent FLUOR
Footing FTG Foundation FDN Furnish(ed), furniture FURN Furring FURR Gage (gauge) GA Galvanize(d) GALV Galvanized Iron GALVI Glazed Wall Tile GWT Grab Bar GB Grade GR Gravel GVL Gypsum Wallboard GWB Gypsum GYP Handicapped HC Hardware HDW Heating ventilating and HVAC air conditioning Height HGT High Point HPT High Performance HP High Performance Coating HPC Hollow Metal HM Horizontal HORIZ Include(d), inclusive INCL Incorporated INC Information INFO Inside diameter ID Install(ed), installation INSTL Insulation INSUL Interior INT Janitor JAN Joint JT Joist J, JST Junction box JB Knock down KD Laboratory LAB Lavatory LAV Left Hand LH Left L Length LG Level LVL Light LT Machine MACH Maintenance MAINT Manager MGR Manual MNL Manufacturing MFG Markerboard MB Masonry opening MO Masonry MSNRY Master bedroom MBR Material MATL Maximum MAX Mechanical MECH Membrane MEMB Men M Metal MET, MTL Mezzanine MEZZ Minimum MIN Mirror MIR Miscellaneous MISC Mounted MTD Mounting MTG Necessary NEC Noise-reduction coefficient NRC Nominal NOM Non Combustible NC, NONCOM North N Not in Contract NIC Not to scale NTS Not available NA Number NO Office OFF On center OC Opening OPNG Opposite OPP Outside diameter OD Overall OA Overhead OVHD Page P Painted PTD Pair PR Panel PNL Partition PTN Percent PCT Perforate(d) PERF Permanent PERM Perpendicular PERP Piece PC Plastic Laminate PLAM Plastic Laminate PLAS.LAM Plate PL Plumbing PLMB Plywood PLYWD Point PT Polyvinyl chloride PVC Precast PRCST Prefabricated PREFAB Preliminary PRELIM Preparation, prepare PREP Program PRGM Projection Screen PS
Project PROJ Property PROP Public Address PA Quality control QC Quality QUAL Quantity QTY Quarry Tile QT Radius RAD Rain Leader RL Received RCVD Receptacle RCPT Receptionist RECPT Recess(ed) REC Refer, reference REF Refrigerate, refrigerator REFR Reinforce REINF Reinforced concrete RC Remove RMV Repair RPR Required REQD Revise, revision REV Right hand RH Road RD Roof Drain RD Roof RF Roofing RFG Room RM Rubber tile floor RTF Rubber RBR Schedule SCHED Schematic SCHEM Section SECT Service SVCE "Sheet, sheeting" SHT Shower SH Siding SDG Similar SIM Slope SL Sound-transmission class STC South S Speaker SPKR Specification SPEC Sprinkler SPR Square SQ Stainless steel SS Standard STD Standpipe SP Steel STL Storage STOR Structural Glazed Facing Tile SGFT Structural, structure STRUCT Substitute SUBST Surface SURF Suspend(ed) SUSP Switch SW Symmetrical SYM System SYS Tackboard TB Tackstrip TS Telephone TEL Television TV Temporary TEMP Terrazzo TER Thick THK Through THRU Toilet T Tongue and groove T&G Top and bottom T&B Top chord TC Top of Masonry Parapet TMP Top of Bearing TOFB Top of Steel T.O.S.
Topping TOPG Total TOT Transformer XFMR Transom TR Transparent TRANS Tread TRD Threshold THRESH Typical TYP Underground UG Underwriters Laboratories UL Unfinished UNF Unit Ventilator UV Unless Otherwise Noted UON Urinal UR US Gypsum Company USG Vertical VERT Vestibule VEST, V Vinyl Reducing Strip VRS Vinyl Composite Tile VCT Vinyl asbestos tile VAT Wardrobe WARD Water closet WC Waterproof WP Weight WT Welded WLD Welded Wire Mesh WWM With W/ Without W/O Women W Wood WD Wrought Iron WI
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET 4800 MEMORIAL DRIVE
WACO, TX 76711
67A4-20-110
EWMDLO
COVER SHEET
GI001
A
-2
-1
G I0
/0
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADES
Fire Suppression Campus Upgrades
100% BID SET
67A4-20-110
Waco VA Medical Center 4800 Memorial Drive
Waco, TX 76711
219-FX101 BUILDING 219 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
219-FD101 BUILDING 219 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT PLAN X
202-FX101 BUILDING 202 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
202-FD101 BUILDING 202 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
189-FX101 BUILDING 189 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
189-FD101 BUILDING 189 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X
99-FX101 BUILDING 99 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL AND LEVEL 1 X X
99-FD101 BUILDING 99 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL AND LEVEL 1 X
94-FX103 BUILDING 94 - FIRE SUPPRESSION PLAN - ATTIC X X
94-FX102 BUILDING 94 - FIRE SUPPRESSION PLAN - LEVEL 1 X X
94-FX101 BUILDING 94 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
94-FD103 BUILDING 94 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC X X
94-FD102 BUILDING 94 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 X X
94-FD101 BUILDING 94 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
93-FX104 BUILDING 93 - FIRE SUPPRESSION PLAN - ATTIC X X
93-FX103 BUILDING 93 - FIRE SUPPRESSION PLAN - LEVEL 2 X X
93-FX102 BUILDING 93 - FIRE SUPPRESSION PLAN - LEVEL 1 X X
93-FX101 BUILDING 93 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
93-FD104 BUILDING 93 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC X X
93-FD103 BUILDING 93 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 X X
93-FD102 BUILDING 93 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 X X
93-FD101 BUILDING 93 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
92-FX104 BUILDING 92 - FIRE SUPPRESSION PLAN - ATTIC X X
92-FX103 BUILDING 92 - FIRE SUPPRESSION PLAN - LEVEL 2 X X
92-FX102 BUILDING 92 - FIRE SUPPRESSION PLAN - LEVEL 1 X X
92-FX101 BUILDING 92 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
92-FX100 BUILDING 92 - FIRE SUPPRESSION PLAN - SUB-BASEMENT LEVEL X X
92-FD104 BUILDING 92 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC X X
92-FD103 BUILDING 92 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 X X
92-FD102 BUILDING 92 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 X X
92-FD101 BUILDING 92 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
92-FD100 BUILDING 92 - FIRE SUPPRESSION DEMOLITION PLAN - SUB-BASEMENT LEVEL X X
91-FX104 BUILDING 91 - FIRE SUPPRESSION PLAN - ATTIC X X
91-FX103 BUILDING 91 - FIRE SUPPRESSION PLAN - LEVEL X X
91-FX102 BUILDING 91 - FIRE SUPPRESSION PLAN - LEVEL X X
91-FX101 BUILDING 91 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
91-FX100 BUILDING 91 - FIRE SUPPRESSION PLAN - SUB-BASEMENT LEVEL X
91-FD104 BUILDING 91 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC X X
91-FD103 BUILDING 91 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 X X
91-FD102 BUILDING 91 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 X X
91-FD101 BUILDING 91 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
91-FD100 BUILDING 91 - FIRE SUPPRESSION DEMOLITION PLAN - SUB-BASEMENT LEVEL X
90-FX104 BUILDING 90 - FIRE SUPPRESSION PLAN - ATTIC X X
90-FX103 BUILDING 90 - FIRE SUPPRESSION PLAN - LEVEL 1 X X
90-FX102 BUILDING 90 - FIRE SUPPRESSION PLAN - LEVEL 1 X X
90-FX101 BUILDING 90 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
90-FX100 BUILDING 90 - FIRE SUPPRESSION PLAN - SUB-BASEMENT LEVEL X X
90-FD104 BUILDING 90 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC X X
90-FD103 BUILDING 90 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 X X
90-FD102 BUILDING 90 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 X X
90-FD101 BUILDING 90 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
90-FD100 BUILDING 90 - FIRE SUPPRESSION DEMOLITION PLAN - SUB-BASEMENT LEVEL X X
24-FX101 BUILDING 24 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
18-FX100 BUILDING 18 - FIRE SUPPRESSION PLANS X X
18-FD100 BUILDING 18 - FIRE SUPPRESSION DEMOLITION PLANS X X
16-FX101 BUILDING 16 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
16-FD101 BUILDING 16 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
98-FX101 BUILDING 98 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
98-FD101 BUILDING 98 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X
15-FX101 BUILDING 15 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X
15-FD101 BUILDING 15 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
12-FX101 BUILDING 12 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
11-FX104 BUILDING 11 - FIRE SUPPRESSION PLAN - ATTIC X X
11-FX103 BUILDING 11 - FIRE SUPPRESSION PLAN - LEVEL 2 X X
11-FX102 BUILDING 11 - FIRE SUPPRESSION PLAN - LEVEL 1 X X
11-FX101 BUILDING 11 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
11-FD104 BUILDING 11 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC X X
11-FD103 BUILDING 11 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 X X
11-FD102 BUILDING 11 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 X X
11-FD101 BUILDING 11 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
8-FX104 BUILDING 8 - FIRE SUPPRESSION PLAN - ATTIC X X
7-FX104-C BUILDING 7 - FIRE SUPPRESSION PLAN - ATTIC AREA C X X
7-FX104-A&B BUILDING 7 - FIRE SUPPRESSION PLAN - ATTIC AREAS A&B X X
7-FX103-C BUILDING 7 - FIRE SUPPRESSION PLAN - LEVEL AREA C X X
7-FX103-A&B BUILDING 7 - FIRE SUPPRESSION PLAN - LEVEL AREAS A&B X X
7-FX102-C BUILDING 7 - FIRE SUPPRESSION PLAN - LEVEL AREA C X X
7-FX102-A&B BUILDING 7 - FIRE SUPPRESSION PLAN - LEVEL AREAS A&B X X
7-FX101-C BUILDING 7 - FIRE SUPPRESSION PLAN - BASEMENT AREA C X X
7-FX101-A&B BUILDING 7 - FIRE SUPPRESSION PLAN - BASEMENT AREAS A&B X X
7-FD104-C BUILDING 7 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC AREA C X X
7-FD104-A&B BUILDING 7 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC AREAS A&B X X
7-FD103-C BUILDING 7 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 AREA C X X
7-FD103-A&B BUILDING 7 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 AREAS A&B X X
7-FD102-C BUILDING 7 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 AREA C X X
7-FD102-A&B BUILDING 7 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 AREAS A&B X X
7-FD101-C BUILDING 7 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT AREA C X X
7-FD101-A&B BUILDING 7 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT AREA A&B X X
6-FX101 BUILDING 6 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
6-FX100 BUILDING 6 - FIRE SUPPRESSION PLAN - SUB-BASEMENT LEVEL X X
6-FD101 BUILDING 6 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
6-FD100 BUILDING 6 - FIRE SUPPRESSION DEMOLITION PLAN - SUB-BASEMENT LEVEL X X
5-FX104 BUILDING 5 - FIRE SUPPRESSION PLAN - ATTIC X X
5-FX103 BUILDING 5 - FIRE SUPPRESSION PLAN - LEVEL 2 X X
5-FX102 BUILDING 5 - FIRE SUPPRESSION PLAN - LEVEL 1 X X
5-FX101 BUILDING 5 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
5-FD104 BUILDING 5 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC X X
5-FD103 BUILDING 5 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 X X
5-FD102 BUILDING 5 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 X X
5-FD101 BUILDING 5 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
4-FX103 BUILDING 4 - FIRE SUPPRESSION PLAN - ATTIC X X
4-FX102 BUILDING 4 - FIRE SUPPRESSION PLAN - LEVEL 1 X X
4-FX101 BUILDING 4 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL X X
4-FD103 BUILDING 4 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC X X
4-FD102 BUILDING 4 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1 X X
4-FD101 BUILDING 4 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL X X
2-FX102 BUILDING 2 - FIRE SUPPRESSION PLAN - LEVEL 2 & ATTIC X X X
2-FX101 BUILDING 2 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL & LEVEL 1 X X X
2-FD102 BUILDING 2 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2 & ATTIC X X X
2-FD101 BUILDING 2 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL & LEVEL 1 X X X
FX101 HYDRANT FLOW TEST SITE PLAN X
FIRE PROTECTION:
GI003 PENETRATION DETAILS X
GI002 VA WACO SITE ORIENTATION PLAN X
GI001 COVER SHEET X X X
GENERAL:
SHEET NUMBER SHEET NAME 35% 65% 100% 100% FINAL
Russell Snapshot
G A T E
G A T E
G A T E
M A
IN
G A T E
G A T E
OLD FARM ROAD
OLD FARM ROAD
DORIS MILLER CIRCLE
DORIS MILLER CIRCLE
D
OR
IS
M
IL
LE
R
CI
RC
LE
DOR
IS M
ILLE
R C
IRCL
E
O U T E R
L O O P
R O A D
O U T E R
L O O P
R O A D
O U T E R
L O O P
R O A D
O U T E R
LO
O P
R O
AD
OUTER LOOP ROAD OUTER LOOP ROAD
OU
TE
R
LO
OP
C
IR
CL
E
MEMORIAL BLVD.
MEMORIAL BLVD.
QUARTERS DRIVE
C
IR
C
LE
D
RI
VE
BEVERLY DRIVE
BEVERLY DRIVE
BEVERLY DRIVE
N E W
R O A D
N E W
R O A D
H C
V A
N H
C
COURT
COURT
C O
U R
T
V A
N
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET 4800 MEMORIAL DRIVE
WACO, TX 76711
67A4-20-110
EWMDLO
SITE ORIENTATION PLAN
GI002
A
-2
-1
G I0
/0
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADES
N TRUE
NORTH
SCALE: NTS
A12
VA WACO SITE ORIENTATION PLAN
219 PHYSICAL THERAPY
202 DIETETICS
189 TRANSPORTATION
99 FMS SHOPS
98 VBA
94 INPATIENT PSYCH
93 FUTURE CENTER OF EXCELLENCE
92 VA FINANCE CENTER
91 SPECIALTY CLINICS
90 PHARMACY CALL CENTER
24 F.M.S./SHOPS
18 POLICE
16 GARAGE MISC.
15 VBA
12 REG'L COUNCIL/PROSTHETICS/EMS/VACANT
11 NURSING HOME (GP)
8 FUTURE ACUTE MENTAL HEALTH/PARTIAL OCCUPANCY
7 BLIND REHAB UNIT/VACANT
6 AUDITORIUM
5 PHARMACY/EDUCATION
4 OUTPATIENT CLINIC/LAB CLINIC
2 ADMINISTRATIVE
BUILDING # BUILDING NAME
Russell Snapshot
G
T E
G A T E
G A T E
M A
IN
G A T E
G A T E
OLD FARM ROAD
OLD FARM ROAD
DORIS MILLER CIRCLE
DORIS MILLER CIRCLE
D
OR
IS
M
IL
LE
R
CI
RC
LE
DOR
IS M
ILLE
R C
IRCL
E
O U T E R
L O O P
R O A D
O U T E R
L O O P
R O A D
O U T E R
L O O P
R O A D
O U T E R
LO
O P
R O
AD
OUTER LOOP ROAD OUTER LOOP ROAD
OU
TE
R
LO
OP
C
IR
CL
E
MEMORIAL BLVD.
MEMORIAL BLVD.
QUARTERS DRIVE
C
IR
C
LE
D
RI
VE
BEVERLY DRIVE
BEVERLY DRIVE
BEVERLY DRIVE
N E W
R O A D
N E W
R O A D
H C
V A
N H
C
COURT
COURT
C O
U R
T
V A
N
FIRE HYDRANT (FH)
WATER VALVE
FH = FIRE HYDRANT
CM = CONTROL MONUMENT
WATER METER
18 20
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET 4800 MEMORIAL DRIVE
WACO, TX 76711
67A4-20-110
EWMDLO
HYDRANT FLOW TEST SITE PLAN
FX001
A
-2
-1
F X
/1
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADES
32 72 65 919 2714
31 73 66 1244 3713
30 At Building 8 68 60 1138 2995
29 At Building 221 70 61 993 2506
28 At Building 226 70 60 1278 3047
27 At Building 219 70 65 1138 3946
26 At Building 99 73 68 1186 4245
25 Parking Lot Between Bldgs 90&91 65 60 1186 3886
24 Parking Lot Between Bldgs 91&92 72 67 1186 4202
23 Parking Lot Between Bldgs 92&93 69 64 1126 3861
22 Parking Lot Between Bldgs 93&94 70 65 1061 3680
21 Inner Loop Behind Bldg 11 65 60 1061 3476
20 Inner Loop Behind Bldg 5 68 60 1061 2793
19 Inner Loop Behind Bldg 9 68 63 1210 4104
18 Inner Loop Behind Bldg 6 67 63 1186 4488
17 At Building 90 69 65 1186 4590
16 At Building 91 68 62 1233 3790
15 At Building 93 70 63 1244 3598
14 At Building 94 70 65 1244 4315
13 At Building 5 69 65 993 3841
12 At Building 202 67 64 1233 5448
11 At Building 1 65 50 1126 3687
10 Front Driveway By Gate Entrance 69 65 1163 4498
9 Front Driveway Between Bldgs... 68 63 1138 3860
8 At Building 18 69 65 1186 4590
7 At Building 21 69 65 1126 4355
6 At Building 11 68 63 1278 4334
5 East Of Building At Gate 2 73 70 1278 6025
4 At Building 4 69 65 1126 4355
3 At Building 12 69 65 1186 4590
2 At Building 15 70 65 1300 4507
1 At Building 14 70 66 993 3442
Hydrant# LOCATION STATIC RESIDUAL FIREFLOW (gpm) FLOW AT 20 psi
SCALE: NTS
A13
HYDRANT FLOW TEST SITE PLAN
N TRUE
NORTH
FIRE RESISTANT RATED WALL CONSTRUCTION
THROUGH PENETRATION FIRESTOPPING SYSTEM
PROVIDE SYSTEM IN ACCORDANCE WITH FIRESTOPPING SCHEDULE
WALL PENETRATION - SEE DRAWINGS
SLAB PENETRATION - SEE DRAWINGS
THROUGH PENETRATION FIRESTOPPING SYSTEM
PROVIDE SYSTEM IN ACCORDANCE WITH
FIRESTOPPING SCHEDULE
FIRE RESISTANCE RATED FLOOR CONSTRUCTION
FLOOR PIPE PENETRATION
UL No: F-L-1020
JOINT SEALANT APPLIED
WITHIN OPENING
METAL PIPE
CONCRETE OVER COMPOSITE
STEEL DECK
MINERAL WOOL INSULATION
JOINT SEALANT
JOINT SEALANT
MINERAL WOOL
INSULATION
METAL PIPE
FLOOR PIPE PENETRATION
UL No: F-L-5014
JOINT SEALANT APPLIED
WITHIN OPENING
METAL PIPE
CONCRETE OVER COMPOSITE
STEEL DECK
MINERAL WOOL INSULATION
JOINT SEALANT
JOINT SEALANT
MINERAL WOOL
INSULATION
GLASS FIBER INSULATION
GLASS FIBER
INSULATION
METAL PIPE
SINGLE CONDUIT/PIPE PENETRATION
UL No: W-L-1063
JOINT SEALANT
PIPE / CONDUIT
JOINT SEALANT
RATED WALL ASSEMBLY - VERIFY
WALL TYPE IN FIELD
48" MAX
V A
R
IE
S
6" M
A X
2" MAX, 1" MIN
1" M
A X
MULTIPLE CONDUIT/PIPE PENETRATIONS
UL No: W-L-1063
MINERAL WOOL INSULATION
WALL TYPE, SEE PLAN
MINERAL WOOD INSULATION
MINERAL WOOL INSULATION
WALL TYPE, SEE PLAN
WALL TYPE, SEE PLAN
SINGLE CONDUIT/PIPE PENETRATION
UL No: W-L-5044
PIPE/CONDUIT
FORMING MATERIAL
JOINT SEALANT
VERIFY WALL TYPE IN FIELD
JOINT SEALANT
PIPE / CONDUIT
WALL TYPE
SMALL PENETRATIONS IN PARTITIONS
RATED UP TO 2 HOURS
NO TREATMENT REQUIRED FOR UP
TO 1/8" GAP
MAXIMUM GAP 1/4"
MAXIMUM GAP 1/2", FILL TO FULL DEPTH
OF DRYWALL AND STRIKE OFF AT FACE
OF DRYWALL, DO NOT SPREAD BEYOND
OPENING
2'-0" (PER UL)
SHALLOW FIVE SIDED BOX
RATED WALL ASSEMBLY-
SEE PARTITION TYPES FOR
NUMBER OF LAYERS OF
GYPSUM BOARD
ELECTRICAL JUNCTION BOX
16 SQ INCH MAX OPENING
MAX 100 SQ INCHES IN 100 SQ FEET
LAMINATE BACK PIECE
TO WALLBOARD
REQUIRED BOX EXCEEDS 16 SQ INCHES
OR AGGREGATE SUM OF BOXES
EXCEEDS 100 SQ INCHES IN 100 SQ
FEET OF WALL AREA
ADJACENT ELECTRICAL BOXES
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET 4800 MEMORIAL DRIVE
WACO, TX 76711
67A4-20-110
EWMDLO
PENETRATION DETAILS
GI003
A
-2
-1
G I0
/1
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADES
SCALE: NTS
A5
THROUGH PENETRATION FIRESTOP SYSTEM KEY
SCALE: NTS
F6
PENETRATION DETAIL
SCALE: NTS
F3
PENETRATION DETAIL
SCALE: NTS
A9
PENETRATION DETAIL
SCALE: NTS
D9
PENETRATION DETAIL
SCALE: NTS
D6
PENETRATION DETAIL
SCALE: NTS
D3
PENETRATIONS
SCALE: NTS
F9
ELECTRICAL JUNCTION BOX DETAIL
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 12
ELE. EQPT.
B1A100
OFFICE
B1A101
HRMS OFFICE
B1A102
OFFICE
B1A103
OFFICE
B1A104
OFFICE
B1A105
MECHANICAL
B1A106
HRMS
CONFERENCE
STORAGE
B1A107
HRMS OFFICE
B1A108
OFFICE
B1A105A
OFFICE
B1A105B
SERVICE
ROOM
B1B100
WOMEN
B1B101
MEN
B1B102
XEROX/ E-QUIP
B1B104
SWING ROOM
B1B105
HRMS
OFFICE
B1B106
PIV
B1B107
HRMS
CONFERENCE
B1B108
HRMS
OFFICE
B1B109
HRMS
OFFICE
B1B110
ELE. CLO.
B1B111
TEL.
B1B108A
IDF
B1B108B
FX05
FX05
FX02FX01
FX03
B3
FD101
FD08
FD08
CORRIDOR
CB1-2
CORRIDOR
CB1-1
ELEVATOR PUMP
ROOM
B1A100A
STAIR 2
VESTIBULE
B1B102A
VESTIBULE
B1B103A
STAIR 1
1. THE BUILDING IS CURRENTLY PARTIALLY SPRINKLERED. RECOMMENDATION IS TO
REMOVE ALL SPRINKLERS, PIPING AND VALVING BACK TO THE UNDERGROUND
STUB IN AND REPLACE WITH A NEW SYSTEM.
2. STANDPIPES MAY REMAIN, BUT REPLACE FIRE HOSE VALVES WITH NEW.
3. CONTRACTOR TO COORDINATE WITH FIRE DEPARTMENT TO RELOCATE FDC TO A
MORE ACCESSIBLE LOCATION.
SCOPE OF WORK
1. EXISTING SYSTEM TO BE MODIFIED AS INDICATED ON THE PLANS.
2. ATTIC DRY PIPE SYSTEMS CURRENTLY INSTALLED WITH GALVNIZED PIPING SHALL
BE REPLACED WITH BLACK STEEL PIPING. FIRE PROTECTION CONTRACTOR TO
VERIFY EXISTING SYSTEM EQUIPMENT LAYOUT.
3. EQUIPMENT AND PIPING SHOWING EXCESSIVE CORROSION OR DETERIORATION
SHALL BE REPLACED WITH NEW AS INDICATED ON THE PLANS.
4. FIRE PROTECTION CONTRACTOR SHALL FOLLOW NFPA 241 AND THE ILSM WHEN
MODIFYING EXISTING SYSTEMS.
FIRE SUPPRESSION DEMOLITION NOTES
FIRE SUPPRESSION HATCH LEGEND
LIGHT HAZARD
DENSITY: 0.10 GPM/SQFT OVER 1500 SQFT
ORDINARY HAZARD
DENSITY: 0.15 GPM/SQFT OVER 1500 SQFT
HATCH LEGEND
ORDINARY HAZARD
DENSITY: 0.20 GPM/SQFT OVER 2500 SQFT
EXISTING PIPING TO BE DEMOLISHED
EXISTING PIPING TO REMAIN
NEW PIPING
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 12
MHBM
1A100
MHBM
1A101
OFFICE
1A102C
MHBM
1A103
BREAK ROOM
1A104
NURSING
1A105
NURSING
1B100
HAC
1B101
WOMENS
1B102
MENS
1B103
DIRECTOR'S
CONFERENCE
ROOM
1B104
NURSING
CONFERENCE
ROOM
1B105
NURSING
1B106
NURSING
1B107
NURSING
1B108
WORK ROOM
1B108A
OFFICE
1A102A
FX05 FX05FX20
FD08
FD08
VESTIBULE
1B102A
CLOSET
1A105A
CORRIDOR
C1-3 CORRIDOR
C1-2
FOYER
1B109
ELEVATOR
VESTIBULE
1B103A
STAIR 1 STAIR 2
TOILET
1A102B
OFFICE
1A102F
OFFICE
1A102
OFFICE
1A102E
CORRIDOR
C1-1
BASEMENT
0"
DEMOLISH EXISTING PIPE
BACK TO 6" UNDERGROUND
STUB IN
DEMOLISH EXISTING CONTROL
VAVLE AND CHECK VALVE
DEMOLISH PIPE ROUTED TO
FDC INCLUDING THE EXISTING
FDCAND CHECK VALVE
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
PARTIALLY
SPRINKLERED Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET BUILDING 2 - ADMINISTRATIVE
4800 MEMORIAL DRIVE
WACO, TX 76711
024-10124-000
EWMEAG
FIRE SUPPRESSION DEMOLITION
PLAN - BASEMENT LEVEL & LEVEL 1
2-FD101
2 1 4
-1
-0
F D
/2
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADE
KEYNOTE LEGEND
FD08 DEMOLISH EXISTING HOSE VALVE CONNECTIONS. EXISTING STANDPIPES ARE TO
REMAIN.
FX01 EXISTING LOCATION OF MAIN FIRE WATER ENTRANCE.
FX02 EXISTING LOCATION OF MAIN VALVE ASSEMBLY.
FX03 EXISTING LOCATION OF FDC.
FX05 EXISTING LOCATION OF STANDPIPE.
FX20 EXISTING INSPECTOR'S TEST.
SCALE: 1/8" = 1'-0"
A12
BUILDING 2 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL
N TRUE
NORTH
SCALE: 1/8" = 1'-0"
E12
BUILDING 2 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1
SCALE: 1/2" = 1'-0"
B3
EXISTING VALVE ASSEMBLY DETAIL
Russell Snapshot
1. EXISTING SYSTEM TO BE MODIFIED AS INDICATED ON THE PLANS.
2. ATTIC DRY PIPE SYSTEMS CURRENTLY INSTALLED WITH GALVNIZED PIPING SHALL
BE REPLACED WITH BLACK STEEL PIPING. FIRE PROTECTION CONTRACTOR TO
VERIFY EXISTING SYSTEM EQUIPMENT LAYOUT.
3. EQUIPMENT AND PIPING SHOWING EXCESSIVE CORROSION OR DETERIORATION
SHALL BE REPLACED WITH NEW AS INDICATED ON THE PLANS.
4. FIRE PROTECTION CONTRACTOR SHALL FOLLOW NFPA 241 AND THE ILSM WHEN
MODIFYING EXISTING SYSTEMS.
FIRE SUPPRESSION DEMOLITION NOTES
FIRE SUPPRESSION HATCH LEGEND
LIGHT HAZARD
DENSITY: 0.10 GPM/SQFT OVER 1500 SQFT
ORDINARY HAZARD
DENSITY: 0.15 GPM/SQFT OVER 1500 SQFT
HATCH LEGEND
ORDINARY HAZARD
DENSITY: 0.20 GPM/SQFT OVER 2500 SQFT
EXISTING PIPING TO BE DEMOLISHED
EXISTING PIPING TO REMAIN
NEW PIPING
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 12
EQUIPMENT
2A100
MAS
2A101
MAS
2A102
MAS
2A103
CONFERENCE
ROOM
2A104
MAS
2A105A
BREAK ROOM
2A106
WACO
COMPUTER
TRAINING
2A107
RESTROOM
2B100
QS&V (OFF. OF
DIRECTOR)
2B101
NURSING
EDUCATION
ROOM
2B102
QS&V (OFF OF
DIRECTOR)
2B103
QS&V (OFF. OF
DIRECTOR)
2B104
NURSING
2B105
MAS
2A105
NURSING
2A108
NURSING
2A109
QS&V (OFF. OF
DIRECTOR)
2A110
QS&V (OFF. OF
DIRECTOR)
2A111
FX05
FX05
FX20
FD08
FD08
STAIR 2
CORRIDOR
C2-5
CORRIDOR
C2-2
LOBBY
C2-1
ELEVATOR
STAIR 1
CORRIDOR
C2-3
CORRIDOR
C2-4
HAC
2B101
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 12
FD01
FX20
DEMOLISH COMPLETE
EXISTING ATTIC SYSTEM
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
PARTIALLY
SPRINKLERED Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET BUILDING 2 - ADMINISTRATIVE
4800 MEMORIAL DRIVE
WACO, TX 76711
024-10124-000
EWMEAG
FIRE SUPPRESSION DEMOLITION
PLAN - LEVEL 2 & ATTIC
2-FD102
2 2 4
-1
-0
F D
/2
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADE
KEYNOTE LEGEND
FD01 REPLACE ALL DRY SYSTEM COMPONENTS IN ATTIC INCLUDING ANY GALVANIZED
PIPING.
FD08 DEMOLISH EXISTING HOSE VALVE CONNECTIONS. EXISTING STANDPIPES ARE TO
REMAIN.
FX05 EXISTING LOCATION OF STANDPIPE.
FX20 EXISTING INSPECTOR'S TEST.
N TRUE
NORTH
SCALE: 1/8" = 1'-0"
A12
BUILDING 2 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 2
SCALE: 1/8" = 1'-0"
E12
BUILDING 2 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC
Russell Snapshot
ELE. EQPT.
B1A100
OFFICE
B1A101
HRMS OFFICE
B1A102
OFFICE
B1A103
OFFICE
B1A104
OFFICE
B1A105
MECHANICAL
B1A106
HRMS
CONFERENCE
STORAGE
B1A107
HRMS OFFICE
B1A108
OFFICE
B1A105A
OFFICE
B1A105B
SERVICE
ROOM
B1B100
WOMEN
B1B101
MEN
B1B102
XEROX/ E-QUIP
B1B104
SWING ROOM
B1B105
HRMS
OFFICE
B1B106
PIV
B1B107
HRMS
CONFERENCE
B1B108
HRMS
OFFICE
B1B109
HRMS
OFFICE
B1B110
ELE. CLO.
B1B111
TEL.
B1B108A
IDF
B1B108B
FX05
FX05
FX02FX01
FX03
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 12
B3
FX101
FX23FX23
ELEVATOR PUMP
ROOM
B1A100A
CORRIDOR
CB1-1
CORRIDOR
CB1-2
STAIR 2
VESTIBULE
B1B102A
VESTIBULE
B1B103A
STAIR 1
1. THIS FACILITY IS TO BE PROTECTED THROUGHOUT WITH AUTOMATIC FIRE
SPRINKLER SYSTEMS PER THE PROJECT REQUIREMENTS. A WET PIPE SYSTEM
SHALL BE INSTALLED IN ALL CONDITIONED SPACES OF THE BUILDING. A DRY PIPE
SYSTEM SHALL BE INSTALLED IN THE ATTIC AND ANY ADDITIONAL SPACES
EXPOSED TO TEMPERATURES BELOW 40 DEG F.
2. THE DESIGN AND INSTALLATION OF THE FIRE SUPPRESSION SYSTEMS SHALL BE
IN ACCORDANCE WITH NFPA 13 (2019 EDITION), NFPA 14 (2019 EDITION), THE VA
DESIGN MANUAL AND THE CONTRACT DOCUMENTS.
3. THESE DRAWINGS ARE SCHEMATIC IN NATURE. ALL PIPE ROUTING AND DETAILS
SHOWN SHALL BE CONFIRMED BY THE FIRE PROTECTION CONTRACTOR AND
FULLY COORDINATED WITH ALL DISCIPLINES. THE FIRE PROTECTION
CONTRACTOR SHALL FURNISH COMPLETE CONSTRUCTION SHOP DRAWINGS
SHOWING ALL SPRINKLERS, PIPE, VALVE AND DRAIN LOCATIONS.
4. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR COORDINATING ALL PHASING
OF THE PROJECT. ALL SPRINKLER SYSTEMS MUST REMAIN IN SERVICE AT ALL
TIMES WHEN BUILDING IS OCCUPIED. FOLLOW ILSM PROTOCOLS FOR
SHUTDOWNS.
5. WIRING OF EQUIPMENT AND DEVICES IS BY DIVISION 26.
6. PAINTING, PATCHING AND REPAIR OF EXISTING FINISHES IS BY OTHERS.
7. EXISTING SPRINKLER SYSTEMS SHALL BE MODIFIED AS INDICATED ON THE
DOCUMENTS.
8. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED IN ACCORDANCE
WITH NFPA 13.
9. THE MAXIMUM COVERAGE PER SPRINKLER IS 225 SQUARE FEET FOR LIGHT
HAZARD AREAS AND 130 SQUARE FEET FOR ORDINARY HAZARD AREAS.
10. INSPECTOR'S TEST VALVES SHALL BELOCATED NO MORE THAN 7'-0 ABOVE
FINISHED FLOOR.
11. ALL HANGERS SHALL BE PROVIDED AND INSTALLED IN ACCORDANCE WITH NFPA
13.
12. ALL VALVES (DRAIN, INSPECTOR'S TEST, CONTROL) SHALL BE IDENTIFIED AS
REQUIRED BY NFPA 13.
13. PROVISIONS FOR DRAINING OF SPRINKLER PIPING SHALL BE PROVIDED IN
ACCORDANCE WITH NFPA 13.
14. PROVIDE MEANS TO TEST FORWARD FLOW THROUGH THE BACKFLOW
PREVENTER IN ACCORDANCE WITH NFPA 13 16.14.5.
15. ALL MAIN DRAINS AND REMOTE TEST CONNECTIONS SHALL DISCHARGE TO A SAFE
LOCATION OUTSIDE THE BUILDING. IF UNABLE TO PIPE TO THE OUTSIDE, THEY
SHALL BE PIPED TO AN INTERIOR DRAIN CAPABLE OF HANDLING THE FULL FLOW.
16. SPRINKLER TEMPERATURE RATINGS NEAR HEAT SOURCES SHALL BE IN
ACCORDANCE WITH NFPA 13.
17. COMMUNICATION AND MECHANICAL ROOMS OR SIMILAR SHALL BE PROTECTED
USING INTERMEDIATE TEMPERATURE SPRINKLERS.
18. PIPING 2" AND LESS IN DIAMETER SHALL BE BLACK STEEL, SCHEDULE 40. PIPE
GREATER THAN 2" SHALL BE BLACK STEEL, SCHEDULE 10. DRY PIPE SYSTEMS
SHALL BE BLACK STEEL, SCHEDULE 40 PIPING WITH NITROGEN IN LIEU OF
COMPRESSED AIR WHERE NOTED ON THE DRAWINGS.
19. TO AID IN PREVENTION OF INTERNAL PIPE CORROSION, INSTALL AUTOMATIC AIR
VENTING NEAR A HIGH POINT ON EACH SYSTEM AS REQUIRED BY NFPA 13.
20. THE CONTRACTOR SHALL PERFORM A HYDRANT FLOW TEST PRIOR TO SYSTEM
CALCULATION TO DETERMINE AVAILABLE WATER PRESSURE AND FLOW. THE
CONTRACTOR SHALL USE THE FOLLOWING FLOW TEST AND DATA FOUND ON
SHEET FX001 AS THE BASIS OF DESIGN UNLESS THE CONFIRMING FLOW TEST
DATA IS WORSE.
FIRE SUPPRESSION GENERAL NOTES
FIRE SUPPRESSION HATCH LEGEND
LIGHT HAZARD
DENSITY: 0.10 GPM/SQFT OVER 1500 SQFT
ORDINARY HAZARD
DENSITY: 0.15 GPM/SQFT OVER 1500 SQFT
HATCH LEGEND
ORDINARY HAZARD
DENSITY: 0.20 GPM/SQFT OVER 2500 SQFT
EXISTING PIPING TO BE DEMOLISHED
EXISTING PIPING TO REMAIN
NEW PIPING
MHBM
1A100
MHBM
1A101
OFFICE
1A102C
MHBM
1A103
BREAK ROOM
1A104
NURSING
1A105
NURSING
1B100
HAC
1B101
WOMENS
1B102
MENS
1B103
DIRECTOR'S
CONFERENCE
ROOM
1B104
NURSING
CONFERENCE
ROOM
1B105
NURSING
1B106
NURSING
1B107
NURSING
1B108
WORK ROOM
1B108A
OFFICE
1A102A
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 12
FX05
FX05
FX20
FX23FX23
STAIR 2
ELEVATOR
FOYER
1B109
CORRIDOR
C1-2
CORRIDOR
C1-3
OFFICE
1A102
OFFICE
1A102E
OFFICE
1A102F
TOILET
1A102B
STAIR 1
CORRIDOR
C1-1
CLOSET
1A105A
VESTIBULE
1B102A
VESTIBULE
1B103A
BASEMENT
0"
TO FDC
PROVIDE NEW 4"
BACKFLOW PREVENTER
PROVIDE NEW 4"
CONTROL VALVE
PROVIDE NEW 4" CHECK
VALVE
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
FULLY
SPRINKLERED Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET BUILDING 2 - ADMINISTRATIVE
4800 MEMORIAL DRIVE
WACO, TX 76711
024-10124-000
EWMEAG
FIRE SUPPRESSION PLAN -
BASEMENT LEVEL & LEVEL 1
2-FX101
2 3 4
-1
-0
F X
/2
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADE
SCALE: 1/8" = 1'-0"
A12
BUILDING 2 - FIRE SUPPRESSION PLAN - BASEMENT LEVEL
KEYNOTE LEGEND
FX01 EXISTING LOCATION OF MAIN FIRE WATER ENTRANCE.
FX02 EXISTING LOCATION OF MAIN VALVE ASSEMBLY.
FX03 EXISTING LOCATION OF FDC.
FX05 EXISTING LOCATION OF STANDPIPE.
FX20 EXISTING INSPECTOR'S TEST.
FX23 PROVIDE NEW HOSE VALVE CONNECTION TO EXISTING 4" STANDPIPE.
N TRUE
NORTH
SCALE: 1/8" = 1'-0"
E12
BUILDING 2 - FIRE SUPPRESSION PLAN - LEVEL 1
SCALE: 1/2" = 1'-0"
B3
NEW VALVE ASSEMBLY DETAIL
Russell Snapshot
1. THIS FACILITY IS TO BE PROTECTED THROUGHOUT WITH AUTOMATIC FIRE
SPRINKLER SYSTEMS PER THE PROJECT REQUIREMENTS. A WET PIPE SYSTEM
SHALL BE INSTALLED IN ALL CONDITIONED SPACES OF THE BUILDING. A DRY PIPE
SYSTEM SHALL BE INSTALLED IN THE ATTIC AND ANY ADDITIONAL SPACES
EXPOSED TO TEMPERATURES BELOW 40 DEG F.
2. THE DESIGN AND INSTALLATION OF THE FIRE SUPPRESSION SYSTEMS SHALL BE
IN ACCORDANCE WITH NFPA 13 (2019 EDITION), NFPA 14 (2019 EDITION), THE VA
DESIGN MANUAL AND THE CONTRACT DOCUMENTS.
3. THESE DRAWINGS ARE SCHEMATIC IN NATURE. ALL PIPE ROUTING AND DETAILS
SHOWN SHALL BE CONFIRMED BY THE FIRE PROTECTION CONTRACTOR AND
FULLY COORDINATED WITH ALL DISCIPLINES. THE FIRE PROTECTION
CONTRACTOR SHALL FURNISH COMPLETE CONSTRUCTION SHOP DRAWINGS
SHOWING ALL SPRINKLERS, PIPE, VALVE AND DRAIN LOCATIONS.
4. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR COORDINATING ALL PHASING
OF THE PROJECT. ALL SPRINKLER SYSTEMS MUST REMAIN IN SERVICE AT ALL
TIMES WHEN BUILDING IS OCCUPIED. FOLLOW ILSM PROTOCOLS FOR
SHUTDOWNS.
5. WIRING OF EQUIPMENT AND DEVICES IS BY DIVISION 26.
6. PAINTING, PATCHING AND REPAIR OF EXISTING FINISHES IS BY OTHERS.
7. EXISTING SPRINKLER SYSTEMS SHALL BE MODIFIED AS INDICATED ON THE
DOCUMENTS.
8. SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY CALCULATED IN ACCORDANCE
WITH NFPA 13.
9. THE MAXIMUM COVERAGE PER SPRINKLER IS 225 SQUARE FEET FOR LIGHT
HAZARD AREAS AND 130 SQUARE FEET FOR ORDINARY HAZARD AREAS.
10. INSPECTOR'S TEST VALVES SHALL BELOCATED NO MORE THAN 7'-0 ABOVE
FINISHED FLOOR.
11. ALL HANGERS SHALL BE PROVIDED AND INSTALLED IN ACCORDANCE WITH NFPA
13.
12. ALL VALVES (DRAIN, INSPECTOR'S TEST, CONTROL) SHALL BE IDENTIFIED AS
REQUIRED BY NFPA 13.
13. PROVISIONS FOR DRAINING OF SPRINKLER PIPING SHALL BE PROVIDED IN
ACCORDANCE WITH NFPA 13.
14. PROVIDE MEANS TO TEST FORWARD FLOW THROUGH THE BACKFLOW
PREVENTER IN ACCORDANCE WITH NFPA 13 16.14.5.
15. ALL MAIN DRAINS AND REMOTE TEST CONNECTIONS SHALL DISCHARGE TO A SAFE
LOCATION OUTSIDE THE BUILDING. IF UNABLE TO PIPE TO THE OUTSIDE, THEY
SHALL BE PIPED TO AN INTERIOR DRAIN CAPABLE OF HANDLING THE FULL FLOW.
16. SPRINKLER TEMPERATURE RATINGS NEAR HEAT SOURCES SHALL BE IN
ACCORDANCE WITH NFPA 13.
17. COMMUNICATION AND MECHANICAL ROOMS OR SIMILAR SHALL BE PROTECTED
USING INTERMEDIATE TEMPERATURE SPRINKLERS.
18. PIPING 2" AND LESS IN DIAMETER SHALL BE BLACK STEEL, SCHEDULE 40. PIPE
GREATER THAN 2" SHALL BE BLACK STEEL, SCHEDULE 10. DRY PIPE SYSTEMS
SHALL BE BLACK STEEL, SCHEDULE 40 PIPING WITH NITROGEN IN LIEU OF
COMPRESSED AIR WHERE NOTED ON THE DRAWINGS.
19. TO AID IN PREVENTION OF INTERNAL PIPE CORROSION, INSTALL AUTOMATIC AIR
VENTING NEAR A HIGH POINT ON EACH SYSTEM AS REQUIRED BY NFPA 13.
20. THE CONTRACTOR SHALL PERFORM A HYDRANT FLOW TEST PRIOR TO SYSTEM
CALCULATION TO DETERMINE AVAILABLE WATER PRESSURE AND FLOW. THE
CONTRACTOR SHALL USE THE FOLLOWING FLOW TEST AND DATA FOUND ON
SHEET FX001 AS THE BASIS OF DESIGN UNLESS THE CONFIRMING FLOW TEST
DATA IS WORSE.
FIRE SUPPRESSION GENERAL NOTES
FIRE SUPPRESSION HATCH LEGEND
LIGHT HAZARD
DENSITY: 0.10 GPM/SQFT OVER 1500 SQFT
ORDINARY HAZARD
DENSITY: 0.15 GPM/SQFT OVER 1500 SQFT
HATCH LEGEND
ORDINARY HAZARD
DENSITY: 0.20 GPM/SQFT OVER 2500 SQFT
EXISTING PIPING TO BE DEMOLISHED
EXISTING PIPING TO REMAIN
NEW PIPING
EQUIPMENT
2A100
MAS
2A101
MAS
2A102
MAS
2A103
CONFERENCE
ROOM
2A104
MAS
2A105A
BREAK ROOM
2A106
WACO
COMPUTER
TRAINING
2A107
RESTROOM
2B100
QS&V (OFF. OF
DIRECTOR)
2B101
NURSING
EDUCATION
ROOM
2B102
QS&V (OFF OF
DIRECTOR)
2B103
QS&V (OFF. OF
DIRECTOR)
2B104
NURSING
2B105
MAS
2A105
NURSING
2A108
NURSING
2A109
QS&V (OFF. OF
DIRECTOR)
2A110
QS&V (OFF. OF
DIRECTOR)
2A111
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 12
FX05
FX05
FX23
FX23
STAIR 2STAIR 1
HAC
2B101
ELEVATOR
LOBBY
C2-1
CORRIDOR
C2-5
CORRIDOR
C2-2
CORRIDOR
C2-3
CORRIDOR
C2-4
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9 10 11 12
FD01
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
FULLY
SPRINKLERED Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET BUILDING 2 - ADMINISTRATIVE
4800 MEMORIAL DRIVE
WACO, TX 76711
024-10124-000
EWMEAG
FIRE SUPPRESSION PLAN - LEVEL 2
& ATTIC
2-FX102
2 4 4
-1
-0
F X
/2
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADE
KEYNOTE LEGEND
FD01 REPLACE ALL DRY SYSTEM COMPONENTS IN ATTIC INCLUDING ANY GALVANIZED
PIPING.
FX05 EXISTING LOCATION OF STANDPIPE.
FX23 PROVIDE NEW HOSE VALVE CONNECTION TO EXISTING 4" STANDPIPE.
N TRUE
NORTH
SCALE: 1/8" = 1'-0"
A12
BUILDING 2 - FIRE SUPPRESSION PLAN - LEVEL 2
SCALE: 1/8" = 1'-0"
E12
BUILDING 2 - FIRE SUPPRESSION PLAN - ATTIC
Russell Snapshot
UP
UP
UP
1 2 3 5
6 7 8 9 10 11 12
13 14 15
A
B
C
D
E
F
G
H
I
J
K
L
M
ELECTRICAL
BA130
WOMEN
RESTROOM
BA125B
NURSING OFFICE
CB15
MENS
RESTROOM
BA125A
WAITING AREA
CB2B
CORRIDOR
CB5
HOUSEKEEPING
BA166
WOMEN
RESTROOM
BA164
CORRIDOR
CB23
STORAGE,
GENERAL
BA139
COFFEE BAR
BA173
CONTROLLED
NARCOTICS
BB104
ELECTRICAL
ROOM
BA172
PHARMACIST
BA169
PHARMACY
BB104A
EXAM ROOM
BA117
DIABETICS/
TELERETINAL
IMAGING
BA112
EXAM ROOM
BA109
HAC
BB102
PHARMACY
BREAK ROOM
BB103
PATIENT REP
BA170
MECHANICAL
ROOM
BA171
EMS STORAGE
BB100
MED SUPPLY
STORAGE
BA115
AMBULANCE
ENTRANCE
CB2C
RESTROOM
BA110
TREATMENT
ROOM
BA106
TREATMENT
ROOM
BA107
EXAM ROOM
BA111
EXAM ROOM
BA113
AMBULATORY
CARE DESK
BA114
EXAM ROOM
BA153
MEANS TEST
BA101B
PROCESSING/REGISTRATION
BA101C
VET ID CARD
BA101A
WAITING AREA
CB2A
MENS
RESTROOM
BA168
PRIMARY CARE
OFFICE
BA163
CAFE
BB101
CLEAN LINEN
CB-18A
SOILED LINEN
CB-18B
PHARMACY HELP
LINE
BB103B
EXAM ROOM
BA161
PHARMACY
BA162
CORRIDOR
CB2
CORRIDOR
CB20
CORRIDOR
CB10
CORRIDOR
CB17
CORRIDOR
CB11
CORRIDOR
CB8
CORRIDOR
CB16
ELEVATOR
LOBBY
CB-18
ELEVATOR
MACHINE ROOM
BA100
STAIR 2
BAS2
STORAGE
NO
LABEL
SUB BSMT
ACCESS
VIDEO ROOM
BA105
CHASE
BB100A
STAIR 6
BAS6
STAIR 5
BAS5
TREATMENT
ROOM
BA157
EXAM ROOM
BA160
EXAM ROOM
BA156
EXAM ROOM
BA159
DISPOSITION
AREA
BA123
SOCIAL WORKER
BA129
OFFICE
BA124
EXAM ROOM
BA121
MAROON TEAM
CHECK-IN DESK
BA122
WAITING AREA
BA149
NURSING
INTERVEIW
ROOM
BA152
UNISEX
RESTROOM
BA145B
CORRIDOR
CB14
IMAGING
RECEPTION
BA146
EXAM ROOM
BA155
WAITING AREA
2 EXAM ROOM
BA154
FORM STORAGE
SUPERVISOR
BA103
OFFICE
BA116
INFORMATION
RECEPTIONIST
BA101
ELECTRICAL
BA119
COMMUNICATIONS
CLOSET
BA120
CLINIC MANAGER
BA118
CLEAN LINEN
ROOM
BA103-3
EXAM ROOM
BA104
SOILED UTILITY
BA103-2
STORAGE,
EQUIPMENT
BA103-1OXYGEN
BA103-4
EXAM ROOM
BA167
HOUSEKEEPING
BA127
NURSE
BA126
STAFF LOUNGE
BA125
VESTIBULE
CB1
MULTI PURPOSE
ROOM
BA165
CORRIDOR
CB3
NURSE LOCKER
ROOM
BA128
WAITING AREA
CORRIDOR
XXX
PROGRAM CLERK
BA132
NURSE MANAGER
BA131
MENS
RESTROOM
BA137
OFFICE
BA133
NUTRITION
CLINIC DIETITION
BA129A
WAITING AREA
B13A
CORRIDOR
CB12
PATIENT FUNDS
BA138
TRAVEL
BA134
WOMENS
RESTROOM
BA136
STAIR 1
BAS1
SUB BASEMENT
ACCESS
AGENT CASHIER
BA135
CORRIDOR
CB13
ULTRASOUND
BA147A
IMAGING
EDUCATION
BA144 STORAGE,
GENERAL
TECH OFFICE
BA143
CT SCAN
BA145
IMAGING
MANAGEMENT
BA148
CT CONTROL
BA145A
IMAGING OFFICE
BA142
X-RAY IMAGING
BA140
VESTIBULE
9 DIGITAL
PROCESSING
BA141A
X-RAY IMAGING
BA141
RESTROOM
BA140A
TOILET
BA163A
BUILDING 4 BUILDING 202
FX07
FD02
DEMOLISH RISER
MOUNTED
COMPRESSOR AND
REPLACE WITH FREE
STANDING TANK
WITH NITROGEN
SYSTEM
FD04
ZONE 1
ZONE BOUNDARY
ZONE 1
ZONE 2
EXISTING BASEMENT LEVEL
ZONE 1 SPRINKLER
CONTROL VALVE.
EXISTING BASEMENT LEVEL
ZONE 2 SPRINKLER
CONTROL VALVE.
DEMOLISH 4" DRY
PIPE MAIN BACK TO
DRY PIPE VALVE
SUPPLYING ATTIC
SYSTEMS.
EXISTING 4" WET MAIN TO
REMAIN
F5
FD101
STORAGE,
GENERAL
BA139
FX20
FX20
1. EXISTING SYSTEM TO BE MODIFIED AS INDICATED ON THE PLANS.
2. ATTIC DRY PIPE SYSTEMS CURRENTLY INSTALLED WITH GALVNIZED PIPING SHALL
BE REPLACED WITH BLACK STEEL PIPING. FIRE PROTECTION CONTRACTOR TO
VERIFY EXISTING SYSTEM EQUIPMENT LAYOUT.
3. EQUIPMENT AND PIPING SHOWING EXCESSIVE CORROSION OR DETERIORATION
SHALL BE REPLACED WITH NEW AS INDICATED ON THE PLANS.
4. FIRE PROTECTION CONTRACTOR SHALL FOLLOW NFPA 241 AND THE ILSM WHEN
MODIFYING EXISTING SYSTEMS.
FIRE SUPPRESSION DEMOLITION NOTES
1. RECOMMEND FULL REPLACEMENT OF VALVE ASSEMBLY FROM THE
UNDERGROUND STUB IN AS INDICATED ON THE PLANS.
2. RECOMMEND NITROGEN SYSTEM FOR DRY SYSTEMS.
3. RECOMMEND FULL ATTIC REPLACEMENT BACK TO THE DRY PIPE VALVE.
4. REPLACE ALL QUICK RESPONSE SPRINKLERS DATED 20 YEARS AND OLDER
MATCHING TYPE AND LOCATION.
SCOPE OF WORK
BASEMENT
0"
L
6" UNDERGROUND STUB IN
FIRE SUPPRESSION HATCH LEGEND
LIGHT HAZARD
DENSITY: 0.10 GPM/SQFT OVER 1500 SQFT
ORDINARY HAZARD
DENSITY: 0.15 GPM/SQFT OVER 1500 SQFT
HATCH LEGEND
ORDINARY HAZARD
DENSITY: 0.20 GPM/SQFT OVER 2500 SQFT
EXISTING PIPING TO BE DEMOLISHED
EXISTING PIPING TO REMAIN
NEW PIPING
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1 /2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
FULLY
SPRINKLERED Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET BUILDING 4 - OUTPATIENT CLINIC
4800 MEMORIAL DRIVE
WACO, TX 76711
024-10124-000
EWMEAG
FIRE SUPPRESSION DEMOLITION
PLAN - BASEMENT LEVEL
4-FD101
4 1 6
-1
-0
F D
/2
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADES
KEYNOTE LEGEND
FD02 EXISTING LOCATION OF MAIN VALVE ASSEMBLY. REPLACE THE MAIN VALVE
ASSEMBLY FROM THE UNDERGROUND FLANGE.
FD04 REPLACE ALL SPRINKLER HEADS AGED 20 YEARS AND OLDER PER NFPA 25.
FX07 EXISTING LOCATION OF FREE-STANDING FDC.
FX20 EXISTING INSPECTOR'S TEST.
SCALE: 1/8" = 1'-0"
A13
BUILDING 4 - FIRE SUPPRESSION DEMOLITION PLAN - BASEMENT LEVEL NTRUE
NORTH
SCALE: 1/2" = 1'-0"
F5
EXISTING MAIN VALVE ASSEMBLY DETAIL
Russell Snapshot
DN
DN
DN
DN
DN
DN
DN
UP
UP
1 2 3 5
6 7 8 9 10 11 12
13 14 15
A
B
C
D
E
F
G
H
I
J
K
L
M
MEN'S LOCKER
1A100A
MEN'S
RESTROOM
1A100B
OFFICE
1A107A
OFFICE
1A104
CORRIDOR
1A106C
OFFICE
1A107
OFFICE
1A104A
BIOSAFETY
LOUNGE
1A100
PHLEBOTOMY
SUPPLY ROOM
1A-157A
ELEVATOR MACH.
ROOM
1A156
HEMATOLOGY
1A157F
WOMEN'S
LOCKER
1A100C
WOMEN'S
RESTROOM
1A100D
SERVER ROOM
1A106
HOUSEKEEPING
1A128
EXAM ROOM
1A114
SERVER ROOM
FOYER
OFFICE/EXAM
1A103A
SPD CLOSET
1A129
LIQUID NITROGEN
1A151
SERVER ROOM
1A105
STORAGE
STORAGE
CHEMISTRY
1A157E
URINALYSIS
1A157H
LEVEL 3 LAB
SUITE
1A157
PCR LAB
1A157I
LAB OFFICE
1A157L
DECONTAMINATION
ROOM
1A157K
COPY/STORAGE
1A126A
CLINIC
RECEPTION
1A126
ELECTRICAL
CLOSET
1A109
CORRIDOR
C1-7
STAIR 4
1S4
GLUCOSE METER
CLINIC
1A122
OFFICE/EXAM
1A103
SECRETARY
1A-157C
TOXICOLOGY
1A157G
CORRIDOR
DEIONIZED
WATER
1A-157B
HOUSEKEEPING
1A157R
ANCILLARY
TESTING OFFICE
1A157P
ANCILLARY
TESTING
1A157N STAIR 2
1S2
LIFT
MANAGER'S
OFFICE
1A157D
VIEWING ROOM
1A157J1
STERILE/SOLUTION
PREP
1A157M
MYCOBACTERIOLOGY
ROOM
1A157J2
MYCOLOGY
1A157J3
CORRIDOR
C1 10
CORRIDOR
C1 12
WAITING
C1 1C
WAITING
C1 8A
CORRIDOR
C1 8
STAIR 3
1S3
CORRIDOR
C1 13
WAITING
C1
11D
WORKROOM
1A145C
CORRIDOR
C1 11
COMMUNICATIONS
CLOSET
1A134A
EXAM ROOM
1A135
TELEPHONE
CLOSET
1A110A
EXAM ROOM
1A149
SOILED
UTILITY/LINEN
1A150
CLEAN LINEN
1A130
OFFICE/EXAM
1A146
RESTROOM
1A148
GROUP
CLINIC/EXAM
1A152
LAB COLLECTION
AREA
1A127
CORRIDOR
RESTROOM
1A127A
EXAM ROOM
1A152A
STORAGE
CLOSET
1A145A
HEALTH
TECHNICIAN
1A144
SPEECH/LANGUAGE
PATHOLOGIST
1A143
WAITING ROOM
C1
13A
HEARING AID
REPAIR
1A140
HEARING
AID/EVOKED
RESPONSE
TESTING
1A142
CLINICAL
AUDIOLOGIST
1A141
OFFICE/EXAM
1A147
PULMONARY
FUNCTION
1A145
OFFICE/EQUPT.
STORAGE
1A145B
FIRE SIGNAL
CLOSET
1A133
RECEPTION
CUBICLE
C1
11C
RECEPTION
CUBICLE
C1-151
ELECTRICAL
CLOSET
1A134
EKG ROOM
1A132
STAIR 1
1S1
STAIR 5
1S5
STAIR 6
1S6
ATTIC ACCESS
1A108
WOMEN'S
RESTROOM
1A102
MEN'S
RESTROOM
1A101
RESTROOM
154A
PROCEDURE
ROOM
1A154
EXAM ROOM
1A153
CORRIDOR
C1
CORRIDOR
C1 9
SOUND BOOTH
1A
SOUND BOOTH
SOUND BOOTH
CORRIDOR
ELEVATOR
LOBBY
C1 1A
ELEVATOR
LOBBY
C1 8C
CORRIDOR
C1 14
CORRIDOR
C1 6
CORRIDOR
C1 2
CORRIDOR
C1 1
STORAGE ROOM
1A117
EXAM ROOM
1A116
NURSE
1A119
PHYSICIAN
WORK/CONF
ROOM
1A121
OFFICE/EXAM
1A113
TREATMENT
ROOM
1A136
AUDIOLOGIST
BOOTH 2
1A137
PHYSICIAN EXAM
ROOM
1A118
EXAM ROOM
1A124
NURSE
1A125
EXAM ROOM
1A155
MEN'S
RESTROOM
1A123
EMPLOYEE
BREAK ROOM
1A110
EXAM ROOM
1A115
WOMEN'S
RESTROOM
1A120
OFFICE/EXAM
1A111
NURSES/TREATMENT
ROOM
1A112
ATTIC ACCESS
ATTIC ACCESS
FD04
BUILDING 4 BUILDING 202
ZONE BOUNDARY
ZONE 3
ZONE 4
4" DRY PIPE
SUPPLY TO
ATTIC.
DRY PIPE ROUTED
TO ATTIC ABOVE.
DRY PIPE ROUTED
TO ATTIC ABOVE.
EXISTING LEVEL 1 ZONE
3 SPRINKLER ZONE
CONTROL VALVE.
EXISTING LEVEL 1
ZONE 2 SPRINKLER
ZONE CONTROL
VALVE.
FX20
FX20 FX20
1. EXISTING SYSTEM TO BE MODIFIED AS INDICATED ON THE PLANS.
2. ATTIC DRY PIPE SYSTEMS CURRENTLY INSTALLED WITH GALVNIZED PIPING SHALL
BE REPLACED WITH BLACK STEEL PIPING. FIRE PROTECTION CONTRACTOR TO
VERIFY EXISTING SYSTEM EQUIPMENT LAYOUT.
3. EQUIPMENT AND PIPING SHOWING EXCESSIVE CORROSION OR DETERIORATION
SHALL BE REPLACED WITH NEW AS INDICATED ON THE PLANS.
4. FIRE PROTECTION CONTRACTOR SHALL FOLLOW NFPA 241 AND THE ILSM WHEN
MODIFYING EXISTING SYSTEMS.
FIRE SUPPRESSION DEMOLITION NOTES
FIRE SUPPRESSION HATCH LEGEND
LIGHT HAZARD
DENSITY: 0.10 GPM/SQFT OVER 1500 SQFT
ORDINARY HAZARD
DENSITY: 0.15 GPM/SQFT OVER 1500 SQFT
HATCH LEGEND
ORDINARY HAZARD
DENSITY: 0.20 GPM/SQFT OVER 2500 SQFT
EXISTING PIPING TO BE DEMOLISHED
EXISTING PIPING TO REMAIN
NEW PIPING
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1 /2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
FULLY
SPRINKLERED Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET BUILDING 4 - OUTPATIENT CLINIC
4800 MEMORIAL DRIVE
WACO, TX 76711
024-10124-000
EWMEAG
FIRE SUPPRESSION DEMOLITION
PLAN - LEVEL 1
4-FD102
4 2 6
-1
-0
F D
/2
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADES
KEYNOTE LEGEND
FD04 REPLACE ALL SPRINKLER HEADS AGED 20 YEARS AND OLDER PER NFPA 25.
FX20 EXISTING INSPECTOR'S TEST.
SCALE: 1/8" = 1'-0"
A13
BUILDING 4 - FIRE SUPPRESSION DEMOLITION PLAN - LEVEL 1
NTRUE
NORTH
Russell Snapshot
2. ATTIC DRY PIPE SYSTEMS CURRENTLY INSTALLED WITH GALVNIZED PIPING SHALL
BE REPLACED WITH BLACK STEEL PIPING. FIRE PROTECTION CONTRACTOR TO
VERIFY EXISTING SYSTEM EQUIPMENT LAYOUT.
3. EQUIPMENT AND PIPING SHOWING EXCESSIVE CORROSION OR DETERIORATION
SHALL BE REPLACED WITH NEW AS INDICATED ON THE PLANS.
4. FIRE PROTECTION CONTRACTOR SHALL FOLLOW NFPA 241 AND THE ILSM WHEN
MODIFYING EXISTING SYSTEMS.
FIRE SUPPRESSION DEMOLITION NOTES
1 2 3 5
6 7 8 9 10 11 12
13 14 15
A
B
C
D
E
F
G
H
I
J
K
L
M
FD03
FD03
EXISTING PENTHOUSE
ZONE 5 SPRINKLER
CONTROL VALVE.
ZONE 5
PENTHOUSE
FIRE SUPPRESSION HATCH LEGEND
LIGHT HAZARD
DENSITY: 0.10 GPM/SQFT OVER 1500 SQFT
ORDINARY HAZARD
DENSITY: 0.15 GPM/SQFT OVER 1500 SQFT
HATCH LEGEND
ORDINARY HAZARD
DENSITY: 0.20 GPM/SQFT OVER 2500 SQFT
EXISTING PIPING TO BE DEMOLISHED
EXISTING PIPING TO REMAIN
NEW PIPING
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1 /2
FIRE PROTECTION:
LEO A DALY
730 Second Avenue South Suite 1300 Minneapolis, MN 612.338.8741 POC: Melisa Rodriguez
ARCHITECT:
CB DESIGN GROUP
421 KING ST., SUITE 301
ALEXANDRIA, VA 22314
POC: WES BRIDGES
703.772.4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
I
J
12345678910111213141516
FULLY
SPRINKLERED Drawing of
ELECTRICAL:
HUITT-ZOLLARS
500 West 7th Street, Suite 300, Fort Worth, TX 817.335.3000, POC: Jeff Roberts
06/25/2021
100% BID SET BUILDING 4 - OUTPATIENT CLINIC
4800 MEMORIAL DRIVE
WACO, TX 76711
024-10124-000
EWMEAG
FIRE SUPPRESSION DEMOLITION
PLAN - ATTIC
4-FD103
4 3 6
-1
-0
F D
/2
/2
.p d f
WACO VA MEDICAL CENTER - FIRE
SUPPRESSION CAMPUS UPGRADES
KEYNOTE LEGEND
FD03 REPLACE EXISTING SPRINKLERS, BRANCH LINES, MAINS AND FITTINGS.
NTRUE
NORTH
SCALE: 1/8" = 1'-0"
A14
BUILDING 4 - FIRE SUPPRESSION DEMOLITION PLAN - ATTIC
Russell Snapshot
UP
UP
ELECTRICAL
BA130
WOMEN
RESTROOM
BA125B
NURSING OFFICE
CB15
MENS
RESTROOM
BA125A
WAITING AREA
CB2B
CORRIDOR
CB5
HOUSEKEEPING
BA166
WOMEN
RESTROOM
BA164
CORRIDOR
CB23
STORAGE,
GENERAL
BA139
COFFEE BAR
BA173
CONTROLLED
NARCOTICS
BB104
ELECTRICAL
ROOM
BA172
PHARMACIST
BA169
PHARMACY
BB104A
EXAM ROOM
BA117
DIABETICS/
TELERETINAL
IMAGING
BA112
EXAM ROOM
BA109
HAC
BB102
PHARMACY
BREAK ROOM
BB103
PATIENT REP
BA170
MECHANICAL
ROOM
BA171
EMS STORAGE
BB100
MED SUPPLY
STORAGE
BA115
AMBULANCE
ENTRANCE
CB2C
RESTROOM
BA110
TREATMENT
ROOM
BA106
TREATMENT
ROOM
BA107
EXAM ROOM
BA111
EXAM ROOM
BA113
AMBULATORY
CARE DESK
BA114
EXAM ROOM
BA153
MEANS TEST
BA101B
PROCESSING/REGISTRATION
BA101C
VET ID CARD
BA101A
WAITING AREA
CB2A
MENS
RESTROOM
BA168
PRIMARY CARE
OFFICE
BA163
CAFE
BB101
CLEAN LINEN
CB-18A
SOILED LINEN
CB-18B
PHARMACY HELP
LINE
BB103B
EXAM ROOM
BA161
PHARMACY
BA162
CORRIDOR
CB2
CORRIDOR
CB20
CORRIDOR
CB10
CORRIDOR
CB17
CORRIDOR
CB11
CORRIDOR
CB8
CORRIDOR
CB16
ELEVATOR
LOBBY
CB-18
ELEVATOR
MACHINE ROOM
BA100
STAIR 2
BAS2
STORAGE
NO
LABEL
SUB BSMT
ACCESS
VIDEO ROOM
BA105
CHASE
BB100A
STAIR 6
BAS6
STAIR 5
BAS5
TREATMENT
ROOM
BA157
EXAM ROOM
BA160
EXAM ROOM
BA156
EXAM ROOM
BA159
DISPOSITION
AREA
BA123
SOCIAL WORKER
BA129
OFFICE
BA124
EXAM ROOM
BA121
MAROON TEAM
CHECK-IN DESK
BA122
WAITING AREA
BA149
NURSING
INTERVEIW
ROOM
BA152
UNISEX
RESTROOM
BA145B
This is the start of the file's text. The full file is on GovTribe.