This document is a kickoff meeting presentation for an Elekta Linac System installation at a VA facility in Lexington, Kentucky scheduled for 2026. The presentation outlines the comprehensive implementation process, roles, responsibilities, and critical requirements for successful installation and commissioning of the radiation therapy treatment system.
The project timeline spans multiple phases beginning with site design finalization and permit acquisition, followed by vault construction with four site inspections (pit inspection approximately five weeks prior to delivery, progress inspection three weeks prior, final inspection one week prior, and transition to installation). The installation phase encompasses five weeks, including customer acceptance during the last three days, followed by MOSAIQ connectivity (three days), commissioning (two weeks), and training (eight to ten days), with clinical operations commencing Wednesday of Phase 1 training. Critical success factors include project ownership and mutual responsibility, primary client contact designation, general contractor coordination, IT infrastructure readiness, milestone adherence, and continuous communication. Elekta is responsible for delivering the Linac system, installation, MOSAIQ connectivity, acceptance documentation, training, and warranty/support initiation upon acceptance. The customer must provide an ELEKTA Ready Vault meeting strict specifications including floor flatness within ±2mm (1/16 inch) around the table pit, proper electrical and mechanical rough-ins, water connections, IT infrastructure with minimum 3MB dedicated network speed, distilled water, control room furnishings, and physics acceptance and commissioning. Standard scope includes PDU, CITB, SF6 and dry nitrogen gases, with optional items such as CCTV, patient intercom systems, green lasers, and graticule options available based on contract inclusions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Non-Confidential Information and Basic Personal Data
Elekta Linac System—Kickoff Meeting VA – Lexington, KY TBD, 2026
• Introductions and sign-in sheet
• Project teams
• Roles and responsibilities
• Critical success factors
• Project scope of supply/project charter
• Implementation process
• Project timeline
• Vault construction review
• Elekta site inspections overview
• Linac system delivery and installation
Meeting Agenda
Roles and Responsibilities
Roles and responsibilities
• Complete project charter, project plan, communication plan
• Scheduling resources
• Conduct kickoff meeting
• Review invoicing plan
• Identify core team
• Review kickoff materials and complete required documentation
• Building access credentials for installation team
• Ensure invoices are reviewed and paid according to purchase and license agreement
• Confirm contract deliverables are delivered
• Confirm site prep completed to Elekta standards
• Confirm rigging path for delivery
• Vault construction is 100% complete prior to final inspection, according to Elekta specifications
• Provide network/physics information prior to progress inspection
• Deliver and rig-in machine • Ensure staging area is clear and free of obstacles
• Ensure Elekta personnel have access to space
• Install Linac and components
• Acceptance testing with physics
• Conduct radiation leakage survey
• Acceptance testing-last 3 days
• Connect MOSAIQ to Linac and update MAC file • Complete connectivity checklist(s) provided by Elekta
• Add sequencer(s)
• Provide IT support as needed
• Perform beam modeling, if purchased • Collect beam data
• Perform beam modeling and quality assurance testing
• Deliver end-user training
• Provide on-site Go Live support
• Complete pre-training checklist
• Assist with scheduling and coordination of end-user training
• Provide Super User and IT support, as needed
• Conduct project close meeting
• Transition customer to support
• Participate in project close meeting
Elekta Customer
Install
Connect to
MOSAIQ
Commission
Close
Inspect
Deliver
Plan and Kickoff
Train and Go Live
Scope of supply: Accessories
Standard
• PDU (shipped to site during construction)
• CITB (shipped to site during construction)
• SF6 and dry nitrogen gases (for Linac install and service)
Optional items (based on contract inclusions)
• CCTV
• Patient intercom system
• Green lasers
• Coded shadow tray
• Open air graticule
• Hook and Latch Graticule
• Requesting service:
• Online: Customer portal; https://community.elekta.com/
• Online self-service center: Access information, tools and resources / Manage your Elekta account & products / Open a non-priority case / Access learning resources / FCO mgmt. & more!
• Speak to representative: Call 855-693-5358 (855-MY-ELEKTA)
• For urgent case please contact the call center and take advantage of Elekta’s remote support team.
• Why opening a case is critical:
• Downtime clock starts when a case is opened / Visibility for the Elekta service team
• Escalation pathway: service region slide (RSM, Sr RSM, Head of Service, Support Manager)
• SLA review
• Entitlements review: Agreed hours, response time, parts coverage, tech refresh (what is covered), etc
• 'Shared Service’ or 'Block of Hours' a review of how these are accessed and consumed
• Afterhours billing rates: Rate sheet
• Holiday coverage
• Planned Maintenance: expectations and scheduling
• MSR: discuss plan for first MSR check in and potential cadence for future meetings
• Local Service Team: Introductions if possible
Service overview https://community.elekta.com/
• Control room chairs
• 10 gal distilled water for filling phantoms and Linac internal cooling loop
• Landline phone in control room
• Live network with IP info—1 static IP
• 24/7 access to vault
Supplied by customer for Linac installation
Project timeline: Linac treatment system
Site design finalized, contractor selected, permits pulled
• Elekta Vault Construction/ Renovation Completed
• Toolbox delivery to site— 2–3 days before Linac delivery; will need to be received by customer and placed in secure location i.e.: Linac vault
• Linac System Delivery—1 day
Vault construction /renovation
• Site Inspections (4)
− Pit Inspection—Generally five weeks prior to delivery, or as soon as concrete is placed
− Progress Inspection—Generally three weeks prior to delivery
− Final inspection—Generally one week prior to delivery − Transition to Installation performed if needed—will review punch list items remaining from final inspection
Clinical Start/1st Patient Treatment—Wednesday of Phase 1 training
1 2 3
456 Installation
• 5 weeks
• Customer Acceptance— Last three days of Linac installation and final invoicing due
• MOSAIQ Connectivity to Elekta Linac—3 days
• Commissioning—2 weeks
• Training—8 to 10 days
One week prior to machine delivery: all site prep requirements must be 100% complete. Go or No Go for Installation (Pass/Fail)
Mobilization of installation activities takes place after the final inspection (toolboxes ship, final arrangements made by riggers and logistics company delivering the equipment, Engineer makes final travel plans)
The Elekta SC will return to site 2 days prior to machine delivery and will confirm completion of any punch list items from final inspection Elekta rigging and installation teams take ownership of the vault the day prior to machine delivery for drilling and vault prep Elekta SC will act as an intermediary/liaison between contractor and Elekta install team for vault access and remaining construction tasks SC will remain onsite until push-in is complete and Hardware Team agrees the remaining construction items are complete or an adequate plan in place
Elekta site inspection overview
Vault slab inspection
All electrical and mechanical rough-ins should be complete, vault door installed, fascia wall roughed in, all laser and camera mounts roughed in
Check Linac table pit and vault slab levelness—pass/fail
Progress inspection Final site inspection Transition to installation
• Kickoff meeting
• Linac enters product cycle
• Linac shipment
• Pre-construction meeting
• Vault construction
• Pit / vault slab inspection
• Progress site inspection
• Final site inspection
• Delivery and rigging of Linac
• Completion of acceptance testing
• Linac service handoff
• Commissioning
• MOSAIQ installation
• Elekta Linac training
• Additional Elekta training (if applicable):
BodyFIX, ABC, Fraxion, etc.
Milestones
Critical success factors
• Project ownership and buy-in—mutual responsibility
• Primary client contact
• General contractor
• IT infrastructure
• Meeting project milestones on time
• Maintaining continuous communication
Failure of the site inspections will result in the installation being pushed to the next available dates, typically 3–4 months later It is very important to stay on schedule!
• Once the Linac acceptance has been completed, the main point of contact on the customers side will receive an email from Experience@elekta.com which contains several questions about the overall project.
• Elekta uses this feedback for process improvement as well as employee evaluation. There is a specific question asking about your experience with your Project Manager which is especially helpful.
• We would ask that you please take the time to respond to this survey. The Project Manager will also follow up with the POC to ensure they received the survey and have no issues accessing it.
Elekta Customer Survey mailto:Experience@elekta.com
The Elekta Linac installation process
Patient treatment, safety, and comfort
A complex system—used in treating serious diseases
• Shielding survey
• Area survey
• Neutron test above 10Mv
• Acceptance of Linac
• Commissioning
• Beam modeling or validation
• MOSAIQ installation acceptance
Physicist involvement
Shielding design and calculations
Shielding design and calculations
The physics pipe location and size is up to the physicist
All shielding design is done by the site physicist of record
All vault penetrations are to be approved by the physicist
• All Elekta items should be incorporated into architectural plans
• Elekta drawings are not for permitting purposes, only for reference
• Use the architectural blue lines
We have two sets of plans— whose plans do we use?
What does Elekta expect?
Observance of tolerances on plans
Elekta is required to calibrate the machine to .3 mm
We require from you 1/16” (2 mm) accuracy
Center of Excellence
Critical dimensions
• All critical dimensions are marked with an asterisk *
• Noted in the NOTES block on each sheet
Absolutely the most difficult part of the job
Critical dimensions +/- 1/16” (2 mm) throughout
The table pit establishes isocenter!
Option #2 Pre-manufactured “leave in place” pit frame
• Frame to be level and square to 1/16” (2 mm)
• 9.25” depth from finished floor
• Not centered on isocenter G/T direction
• Leave steel pit edge proud of concrete by floor covering thickness
Option #1 Field formed with 2”x 2” steel around pit edge
Vault renovation
Vault floor flatness is critical around table pit out 3’
Floor level +/- 2 mm (1/16”) inside and around pit
3/16-inch clearance from finished floor
• Correct location of table pit
• Pit depth = 235 mm
• Raceway location and layout correct
• Vault slab flatness
• Framing for fascia wall
Pit and vault slab inspection Confirm table pit and floor raceway meets all Elekta specifications
Example of long raceway
How do I meet tolerance?
• > 4500 PSI
• > 9” monolithic slab
• No layering
• 9.25” depth and flat to 1/16”
Typical laser location examples ¼” thick aluminum plates on ½” spacers mounted solid to concrete
Fascia wall construction
• Wall must be 48-1/16” from isocenter and parallel
• Opening must be 13’-1.5” centered x 101” tall
• Solid wood header
• 9’ min clearance behind fascia opening
• Both service doors require a set of safety switches
• Minimum door opening 24”
• Doors must open out into treatment room
• NO CLOSURES on service doors allowed
Pre-install deliveries
Toolbox
PDU
Elekta to supply
• PDU
• CITB
• Installers tools
• Gases
• Input: 480 @ 40-amp 3P
• Output: 415 & 220
• Wire size is critical
• 8–10-week lead time
• 2 ea 2-in knockouts in back
• CITB—Client Interface Terminal Box
• Interface from building to Linac
• 4-week lead time minimum (ordered by Site Coordinator)
• Needs two 120-vac circuits
• All connections by electrician
• Fully tested on final inspection
Client interface terminal box (CITB) Supplied by Elekta and wired by Site Electrician
• Qty 6 required
• Beam Off / Motion Stop Positive locking switches
• Wired in series, Run back to Client Interface Panel
Additional electrical items NOT supplied by Elekta
• Fascia Door Switches supplied by Electrician
• Need 2 separate contacts per door!
Elekta requirements for chilled water monitoring
(100 micron)
Pressure gauges 15–60 psi
Temp gauges 59–70⁰
8–14 GPM
Optional chiller switchover panel Water connections, 4 feet to left of ISO center, with temp loop
• Auto city water backup switchover panel
• Chiller controlled
• Filter and gauges included
• External power required
• Still requires external solenoids
• 120vac—Water solenoids 2 ea N.C. and 1 ea N.O. / All spring return
Final water connections by Elekta
• Vault slab / Pit inspection. Check location of pit and fascia wall. Answer questions from subcontractors.
• Progress inspection and Site check. Substantial completion—mechanical and electrical rough in complete. Camera and laser structures in place. Fascia wall constructed.
• Final site check—Vault and Control room 100% complete, dust free, all utilities operational. Permanent power and chiller fully operational. Hard surface of Staging area.
• If the site passes final site check, equipment will be delivered the following week.
• If site check fails, a later date for installation will be determined by the Elekta Project Manager.
Site inspections and expectations To avoid missing customer delivery dates, Elekta Site Coordinators conduct site checks
The Project Manager will hold a call with the Customer, Contractor, and Site Coordinator while we are onsite for any inspection. This will help to review construction progress and determine if there are any deviations from the construction timeline.
Additional contractor expectations
• Finished floor protection in vault (if applicable)
• Water connections on 3rd day of install
• Power connections on 3rd day of install
• Fascia wall trim to cover gap
• Trim table pit floorboards to fit and cover
• Laser Door Holes (if applicable)
NOTE: Elekta is responsible for disposal of crates and packing from Linac delivery
Cabinet
Final inspection—vault condition
How does Elekta get it into the room?
Linac Delivery Day
Delivery and Rigging
Linac Delivery Day Prep-staging area
• 50 crates
• Weather considerations
• Trash removal
Loading the gantry onto the carrier chassis
Door dimensions are critical
The gantry drum is lifted into place
Beam arm is 11’ 7” long— check pathway
Table base anchored in pit
Add table to base unit
Install tabletop
Fit and finishes after Elekta delivery
The fascia panels are supported by a tubular frame, installed by Elekta
Add floor finishes to table pit cover
Add floor covering to boards and center dial
Trim Elekta-supplied floorboards to fit
Typical laser enclosure and mounting plate (Hole to be drilled in door after laser is installed)
Elekta treatment system
• Toolbox delivery—Confirm main contact and address − After final site inspection, dolly incl, 2500 lbs, must be secured
• Equipment rigging and crate disposal − Morning of the delivery
• Installation of Linac
• Installation of MOSAIQ connectivity to Linac
• Acceptance documentation to client physics
• Applications training
• Warranty and service support
− Acceptance is a trigger of warranty and support
Reminder: Elekta responsibility
• ELEKTA Ready Vault − Site inspection expectations − Site inspection checklist − Electrical and mechanical engineering support at installation start
• Distilled water, control room chair, phone
• IT hardware for MOSAIQ system (scheduling workstations, etc.)
• IT network infrastructure
− LAN or Citrix, must be at least 3 MB, dedicated network speed
• Physics acceptance and commissioning (estimated up to 4 weeks)
• IntelliMax network security solutions preparations
• Radiation survey
Reminder: Client responsibility
Next steps
• Staging area/Rigging path review
• Establish communication plan
• Finalize Elekta timeline
• Review invoicing terms and expectations
Thank you
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 17 |
| Slide Number 18 |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |
| Slide Number 23 |
| Slide Number 24 |
| Slide Number 25 |
| Slide Number 26 |
| Slide Number 27 |
| Slide Number 28 |
| Slide Number 29 |
| Slide Number 30 |
| Slide Number 31 |
| Slide Number 32 |
| Slide Number 33 |
| Slide Number 34 |
| Slide Number 35 |
| Slide Number 36 |
| Slide Number 37 |
| Slide Number 38 |
| Slide Number 39 |
| Slide Number 40 |
| Slide Number 41 |
| Slide Number 42 |
| Slide Number 43 |
| Slide Number 44 |
| Slide Number 45 |
| Slide Number 46 |
| Slide Number 47 |
| Slide Number 48 |
| Slide Number 49 |
| Slide Number 50 |
| Fit and finishes after Elekta delivery |
| Slide Number 52 |
| Slide Number 53 |
| Slide Number 54 |
| Slide Number 55 |
| Slide Number 56 |
| Slide Number 57 |
| Slide Number 58 |
| Slide Number 59 |
File details come from the government source that posted it. Updated .