This Utility Information Sheet pertains to the roundabout construction project at the intersection of Ten Mile Road and Deer Flat Road in Idaho, providing essential utility coordination details for bidders and contractors. The document serves as a reference tool for understanding existing utility infrastructure in the project area, enabling contractors to plan work sequences, identify potential conflicts, and coordinate with utility providers during construction of the concrete and asphalt paving, curb and gutter, multi-use pathways, Rectangular Rapid Flashing Beacons, school zone flashers, street lighting, stormwater, irrigation, and water line installations. The sheet identifies the location and depth of existing utilities such as water lines, sewer lines, electrical conduits, telecommunications infrastructure, and irrigation systems that cross or exist within the project boundary, facilitating safe and efficient construction execution.

The utility information is critical for contractors to establish preliminary utility clearance requirements and coordination protocols prior to construction commencement. Contractors must review this sheet in conjunction with the project plans and specifications to identify where utility conflicts may occur and determine necessary modifications, relocations, or protective measures. Contractors are typically required to contact individual utility companies to obtain locate requests and verify all utility information before beginning excavation activities, and the utility information sheet serves as the foundational reference document for these coordination efforts.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Utility Information

Ten Mile Rd and Deer Flat Rd

Project #321038

Utility Company Work Duration and Contact Information:

Utilities require approx. 90 working days from NTP date to complete their relocations, adjustments, and installations after clearing, grubbing, tree trimming and removal. These utility windows may impact the Contractor’s critical path schedule by that amount of time, but utilities may be working on site for every phase of the project. Project phasing may have a significant effect on the schedule for utility relocations, adjustments and installations.

Contractor must coordinate and accommodate work with utility companies and schedule required construction windows throughout the project.

ACHD General Conditions Section 26 applies. Contact ACHD Utility Coordinator, Scott Bennett, at (208) 387-6259, with questions.

Utilities within project:

• Sparklight – Michael Stephen – (208) 615-0338 – michael.stephen@cableone.biz

• Lumen – James Hayes – (208) 350-1645 – James.P.Hayes@lumen.com

• City of Kuna Public Works – Mike Borzick – (208) 287-1726 – mike@kunaid.gov

• Idaho Power – Dan Hammerquist – (208) 388-2629 – dhammerquist@idahopower.com

• Intermountain Gas – Jordan Garcia – (208) 793-1528 – jordan.garcia@intgas.com

• Forged fiber 37 – Zach Rayner – (972) 331-0734 - ZACHARY.RAYNER@FORGEDFIBER37.COM mailto:michael.stephen@cableone.biz mailto:James.P.Hayes@lumen.com mailto:mike@kunaid.gov mailto:dhammerquist@idahopower.com mailto:jordan.garcia@intgas.com mailto:ZACHARY.RAYNER@FORGEDFIBER37.COM