(USS COMSTOCK) Attachment J-7 Schedule Model Review.pdf

PDF 89 KB Posted

Attached to
Request for Proposals (RFP) No. N00024-20-R-4405: USS COMSTOCK FY21 (LSD 45) Docking Selected Restricted Availability (DSRA)
Solicitation number
N00024-20-R-4405
Issued by

View the file

Other files

File Type Posted
N00024.20.R.4405_A0003.zip ZIP file
N00024.20.R.4405_A0003.zip ZIP file
N00024.20.R.4405_A0002.zip ZIP file
N00024.20.R.4405_A0001.zip ZIP file
S attachments.zip ZIP file
(USS COMSTOCK) Attachment J-8 GFM GFP List 19May20.xlsx XLSX spreadsheet
(USS COMSTOCK) Attachment J-5 QASP COM FY21 DSRA.pdf PDF
CDRLs.zip ZIP file
N00024.20.R.4405_COM RFP_05.18.20.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J-7 Schedule Model Review

USS COMSTOCK

Purpose: At A-30 the Lead Maintenance Activity (LMA) shall lead a Schedule Model Review of the Integrated Production Schedule (IPS) with all parties to validate integration requirements. The Schedule Model Review is intended to be a detailed review of all work items to ensure adequate integration into the master schedule and to de-conflict any overlapping activities. The anticipated duration of this meeting is 5-7 days. Hours for Day 1 is 0800-1600 and for Day 2 and following is 0800-1130.

1. Required Attendees:

a. LMA management team

b. Government Project Management Team (NSA)

c. Turnkey Subcontractors

d. Alteration Installation Team (AIT) On Site Installation Coordinators (OSIC)

e. Intermediate Maintenance Facility (IMF) Ship’s Superintendent, if applicable

f. Ship’s Force (one representative from each department, Ship’s Maintenance Officer)

2. Agenda:

Day 1 Work Package Execution Review (WPER) (Government Facilitated)

a. Early Start Candidates (LMA)

b. WAF/Tag Out coordination (LMA)

c. Pier Laydown Plan (LMA)

d. First 100 Hour Plan (NSA)

e. Communications Plan (NSA)

f. Process Control Procedures (PCP) (LMA)

g. Access Cuts (LMA)

h. Fire Prevention and Fire Drill (8010) requirements (NSA)

i. Memorandum of Agreement (MOA) – AIT’s only (NSA)

Day 2 - 7

a. LMA to Present the IPS for review. The IPS shall include (but not limited to) all work associated with the

LMA, subcontractors, AITs, Ship’s Force, and Intermediate Maintenance Activity (IMA).

3. Deliverables:

a. Updated IPS with all maintenance activities fully integrated. (LMA)

b. Early start candidates submitted and approved by the NSA. (LMA)

c. WAF/Tag Out coordination plan established. (LMA)

d. First 100 Hour Plan established. (NSA)

e. Set schedule for all required meetings. (NSA)

f. Pier Laydown Plan submitted for approval by NSA. (LMA)

g. List of Process Control Procedures with projected due dates. (LMA)

h. List of access cuts (if required). (LMA)

i. Fire drill execution date set. (NSA)

j. Detailed review of critical path and top three controlling path items. (LMA)