USNS MERCY (T-AH 19) IBS PWS (31 MAY 2022).doc
DOC document 496 KB Posted
- Attached to
- USNS MERCY (INTEGRATED BRIDGE SYSTEM) Federal contract opportunity
- Solicitation number
- N3220522Q0179
About this file
This performance work statement outlines requirements for an integrated bridge system upgrade aboard the USNS Mercy hospital ship. The Navy seeks engineering and design services to replace outdated navigation equipment, integrate new systems, and modify related spaces. Key requirements include installing a Sperry electronic chart display and information system at multiple workstations, replacing radar and GPS units, upgrading gyrocompasses and repeaters, and consolidating bridge lighting, alarm, and communications systems onto new consoles. The contractor must develop designs, drawings, work items, cost estimates and test procedures for Navy review and ABS/USCG approval before procuring equipment in option year one and installing the integrated bridge system in a later option year at a shipyard. The performance period spans multiple contract options from award through September 2024.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
USNS MERCY (T-AH 19) INTEGRATED BRIDGE SYSTEM AND PILOT HOUSE UPGRADES, DESIGN, BUILD, AND INSTALLATION
Contract:
TBD
Contracting Officer Representative (COR): Jaclyn Schlieper Technical Point of Contact (TPOC): Jaclyn Schlieper Period of Performance:
Base Period: Engineering and Design from “upon award” to September 30, 2023 Option 1: Procurement and Integration from March 1, 2023 to September 30, 2024 Option 2: Installation and Technical Support 90 days between October 1, 2023 to September 30, 2024
1. OVERVIEW:
This item describes the requirements for design, build, installation, and testing of a commercial grade Integrated Bridge System (IBS) including associated upgrades and rearrangement of the Wheelhouse and related spaces. The Base Period of this contract is to be initially awarded for the design with two additional contract options, each to be exercised with subsequent funding. Option 1 will be to perform equipment procurement/fabrication and testing of major system components associated with the design of the initial contract. Option 2 will be for installation of the Integrated Bridge System. System design, fabrication, and installation shall meet applicable American Bureau of Shipping (ABS), US Coast Guard (USCG), International Maritime Organization (IMO), and Institute of Electrical and Electronics Engineers (IEEE) requirements.
2. BACKGROUND:
The USNS Mercy (T-AH 19), hereafter MERCY, is a conversion vessel, originally built as a San Clemente Class, steam propulsion oil tanker, the SS Worth in 1976 by National Steel and Shipbuilding Company (NASSCO). The converted vessel was placed into service in 1986. The primary mission of the MERCY is to provide rapid, flexible, and mobile acute medical and surgical services to support military operations. The vessel also provides mobile surgical hospital services through other U.S. Government agencies for disaster or humanitarian relief.
The existing bridge, console, and ancillary equipment are from the original construction, and were relocated from the aft portion of the ship to the forward house during the conversion. This equipment was identified as obsolete and in need of upgrading during the 2016 Material Readiness Evaluation.
An IBS and rearrangement of the Wheelhouse (04-34-0), related spaces and equipment upgrades are required to allow for Military Sealift Command (MSC) navigation personnel to safely and efficiently operate the vessel. The Wheelhouse will be outfitted with an IBS that meets ABS and USCG requirements and is supportable for twenty years.
3. OBJECTIVE:
To describe the requirements for reconfiguring and upgrading the navigation bridge and supporting systems onboard the MERCY as part of the Service Life Extension Plan (SLEP) to ensure compliance with current and projected regulatory requirements and to suit operation of a civil service mariner (CIVMAR) crewed MSC vessel. The navigation bridge will be outfitted with an IBS meeting ABS MVR, ABS requirements for NBLES, IMO SOLAS Chapter V, USCG CFR’s, IEEE and any associated NAVSEA, MSC, and OPNAV instructions.
3.1. Base Period – Engineering and Design
During this phase, the IBS Contractor will provide engineering and project management to:
3.1.1. Specify required new equipment, components, spare parts and method of integration with reinstalled existing equipment and components.
3.1.2. Maximize the usable space on the bridge, which shall include removal of the bulkhead separating the Wheelhouse (04-34-0) and the Chart Room.
3.1.3. Produce drawings, work specifications, calculations, and cost estimates as required for modification of the spaces for the new configuration of the Wheelhouse (04-34-0) and any other space affected, to include all structural, arrangements and outfitting, electrical, electronics, and mechanical systems required for the upgrade.
3.1.4. Develop training, testing, as well as dock and sea trial procedures to fully demonstrate the functionality of the IBS.
3.1.5. Provide planning products as outlined in Section 6.1, Base Period, for shipboard work.
3.2. Option 1 – Procurement and Integration
3.2.1. During this phase, the IBS Contractor will procure and fabricate all equipment and material to accomplish the modifications, as per MSC approved drawings and specifications as developed by the IBS Contractor in the Base Period (Section 3.1). The system and all components are to be installed in simulated conditions and tested. Contractor will conduct Factory Acceptance Test (FAT) at its facility and demonstrate the procedure developed during the base period for Testing. Components are to be packaged and stored until installation. Contractor to develop spare parts list with list developed by OEM and in accordance with ABS and USCG as required for new system. Contractor will also provide training for operators.
3.3. Option 2 – Installation and Technical Support
3.3.1. During this phase, the IBS Contractor will remove and install the new IBS during a shipyard availability. IBS Contractor will be responsible for final testing of new and modified equipment and systems, and Regulatory Body (ABS and USCG) acceptance including dock and sea trials.
3.3.2. Contractor shall capture any changes to the drawings developed under this specification during Installation as Redlines and update drawings to reflect As-Built Configuration.
3.3.3. Installation and integration of a new commercial IBS meeting ABS MVR, ABS requirements for NBLES, IMO SOLAS Chapter V, USCG CFR’s, IEEE and any associated NAVSEA, MSC, and OPNAV instructions and incorporating the following in the new console(s):
· Navigational Maneuvering and Traffic Monitoring Systems
· Monitoring, Alarm, and Warning Annunciation and Control Systems
· Communications Systems
· Auxiliary, Electrical and Structural Systems
· Electronic and Instrument Control (IC) Circuits
3.3.4. Contractor shall be responsible for all final terminations for all equipment, both inside and outside of the consoles, and will be responsible for OEM acceptance testing. Contractor shall not provide power until authorized by OEM.
3.3.5. Contractor shall be responsible for all testing and crew training.
4. APPLICABLE SPECIFICATIONS
4.1. The new IBS and related navigation systems and equipment shall meet the requirements of this Performance Work Statement (PWS), and current editions as of contract award of ABS MVR, ABS requirements for NBLES, IMO SOLAS Chapter V, USCG, IEEE and any associated NAVSEA, MSC, and OPNAV instructions.
4.2. Reference Documents
* Contractor shall be responsible for providing its own copies of the most current version for all reference material as follows:
4.2.1. ABS Marine Vessel Rules
4.2.2. ABS Guide for Bridge Design and Navigational Equipment/Systems
4.2.3. ABS Guidance Notes on Application of Ergonomics to Marine Systems
4.2.4. ABS Guidance Notes on Ergonomic Design of Navigation Bridges
4.2.5. Code of Federal Regulations (CFR) Title 46 Subchapter I
4.2.6. Not used
4.2.7. COMSCINST 3530.1A 21 November 2017 Military Sealift Command Navigation Policy
4.2.8. National Marine Electronics Association (NMEA) NMEA 0400 Installation Standard, Version 4.00
4.2.9. ASTM D3951 Standard Practice for Commercial Packaging
4.2.10. COMDTPUB P16700.4 NVIC 10-92 CH2 Navigation and Vessel Inspection Circular No. 10-92 Change 2
4.2.11. Not used
4.2.12. IEEE-STD-45 – Recommended Practice for Electrical Installations on Shipboard
4.2.13. ASTM F1166-07 – Standard Practice for Human Engineering Design for Marine Systems, Equipment and Facilities
4.2.14. N0720-008.00-Q Human Machine Interface (HMI) Design Standards
4.2.15. IMO SOLAS Chapter V – Safety of Navigation
4.2.16. Not used
4.2.17. COMDTPUB P P16700.4 – NVIC 8-01 – Navigation and Vessel Inspection Circular No. 8-01, Change 3
4.2.18. SNAME Technical & Research Bulletin 4-16 (2015)
4.2.19. DOD Instruction 8500.01
4.2.20. ABS CyberSafety Volumes 1-5
4.2.21. NIST 800-82 Guide to Industrial Control Systems (ICS) Security
4.3. Government Furnished Information (GFI):
| GFI # |
| SWBS |
| Drawing No. |
| Title |
| Format |
| 4.3.1 |
| 184 |
| 8496160 |
| Foundation Mods MK27F Gyrocompass Install |
| PDF/CAD |
| 4.3.2 |
| 301 |
| 5980580 |
| Arrangement of Wheelhouse |
| PDF/CAD |
| 4.3.3 |
| 301 |
| 8496161 |
| Gyro Compass Install, Arrangement, Mods, MK27F |
| PDF/CAD |
| 4.3.4 |
| 332 |
| 5980541 |
| Lifeboat Floodlight System ISO Wiring Diagram |
| 4.3.5 |
| 401 |
| 390-401-005; S65-05-06 |
| Rudder Angle Indicator Elem & ISO W.D. |
| 4.3.6 |
| 401 |
| 390-401-019; S65-05-11 |
| Fire Detection Sys ISO Wiring Diagram |
| 4.3.7 |
| 402 |
| 5989766 |
| Sound Powered Telephone Block Wiring Diagram |
| 4.3.8 |
| 405 |
| 5989785 |
| Sound Powered Telephone Block Wiring Diagram |
| 4.3.9 |
| 412 |
| 5989804 |
| Dial Telephone Installation Isometric Wiring Diagram |
| 4.3.10 |
| 422 |
| 5980615 |
| Navigation Lighting System ISO and Elem Wiring Diagram |
| 4.3.11 |
| 423 |
| 5980672 |
| RDF, SATNAV and Echo Depth Sounder Sys ISO and Elem WRG Diag |
| 4.3.12 |
| 426 |
| 5980619 |
| Doppler Speed Log System Isometric and Elementary Wiring Diagram |
| 4.3.13 |
| 426 |
| 8496162 |
| Electrical Removals MK27F Gyrocompass Install |
| 4.3.14 |
| 426 |
| 8496163 |
| Electrical Installations Mods, MK27F Gyrocompass Install |
| PDF/CAD |
| 4.3.15 |
| 430 |
| 8391635 |
| 18MC Bridge Communication System Installation |
| PDF/CAD |
| 4.3.16 |
| 436 |
| 5980645 |
| General and Engineers Assistance Alarm Sys ISO Wiring Diag |
| 4.3.17 |
| 436 |
| 5980646 |
| Steering Gear Alarm System Isometric and Elementary Wiring |
| 4.3.18 |
| 436 |
| 5980651 |
| Fire Door Closing Sys ISO & Elem Wiring Diag |
| 4.3.19 |
| 437 |
| 5980661 |
| Throttle Control and Console Intertie |
| 4.3.20 |
| 451 |
| 5980676 |
| Collision Avoidance System Isometric and Elementary Wiring Diagram |
| 4.3.21 |
| 506 |
| 7371790 |
| GPS & Weather Fax Isometric Wiring Diag |
| 4.3.22 |
| 801 |
| 8613785 |
| Booklet of General Plans |
| PDF/CAD |
| 4.3.23 |
| 803 |
| 7079667 |
| Preparation of Selected Record Drawings (SRDS) for Government Owned Ships |
| 4.3.24 |
| 803 |
| 7080803 |
| Preparation of Computer Aided Designed (CAD) Drawings for USNS Ships |
| 4.3.25 |
| 803 |
| 7081122 |
| Rev – General Technical Requirements |
| 4.3.26 |
| 803 |
| 7081124 |
| MSC Work Item Prep Guide |
| 4.3.27 |
| 841 |
| 8387470 |
| USNS Mercy Periodic Safety Test Procedure |
4.3.28
| N0720-9330.6-001PI |
| MSC Design Standard |
4.3.29
| 3232 Ser N00/723 |
| MSC Updated ECDIS Functional Requirements (15 July 16) |
4.3.30
| N0720-113.00-P |
| Military Sealift Command QMS Procedures Manual (dated 13 July 2011) Deck Department and Pilot House Standards for New Construction Large Ships |
4.3.31
| COMSCINST 9000.1c |
| COMSC Instruction – Preparation, Maintenance, and Distribution of Selected Record Plans and Booklets for MSC Ships (USNS) |
| 4.3.32 |
| 433 |
| 5980635 |
| Medical Announcing System CKT “53MC” ISO WRG Diag |
4.3.33
| Ship Drawing Index; USNS Mercy |
| Excel |
4.3.34
| Tech Manual Index; USNS Mercy |
| Excel |
| 4.3.35 |
| 433 |
| 5980682 |
| Emergency Announcing Sys and Flight Crash Alm Elem Wrg Diag 1MC |
4.3.36
| 5980621 Ref 2 |
| ABS Letter dtd. 24 March 2016 |
| 4.3.37 |
| 845 |
| 5890509 |
| SRD Fire Control Plan |
| PDF/CAD |
| 4.3.38 |
| 331 |
| 7487934 |
| Lighting System One-Line Diagram |
| PDF/CAD |
| 4.3.39 |
| 300 |
| 8387571 |
| Electrical Plant Load Analysis |
| PDF/EXCEL/CAD |
| 4.3.40 |
| N/A |
| N/A |
| Other Related Documents Upon Request |
| 4.3.41 |
| 405 |
| 5980776 |
| Antenna Arrangement |
| 4.3.42 |
| 433 |
| 6631558 |
| Emergency Announcing Sys and Flt Crash Alm ISO Wrg Diag 1MC Mercy Only |
4.3.43
| Sperry ECDIS/Radar Survey |
4.3.44
| 390-404-001 |
| NASSCO Plan Omega, RDF, Satl. Navigation & Echo Depth Sounder System Elem. and ISO. W.D. |
| 4.3.45 |
| 300 |
| 5980468 |
| Electrical Install Notes and Typical Methods |
| 4.3.46 |
| 321 |
| 5980470 |
| Power System Isometric Wiring Diagram |
| PDF/CAD |
4.3.47
| 5980621 Ref 1 |
| ABS Letter dtd. 10 March 2016 |
| 4.3.48 |
| 332 |
| 5980556 |
| LTG System 03 LVL and ABV Fr 33-42 |
| PDF/CAD |
| 4.3.49 |
| 433 |
| 5980617 |
| Whistle Control Sys ISO and Elem Wrg Diag |
| 4.3.50 |
| 426 |
| 5980621 |
| Gyro Compass & Gyro Pilot ISO and Elem Erg Diag |
| PDF/CAD |
| 4.3.51 |
| 451 |
| 5980674 |
| Ship Radar Sys Iso and Elem Wrg Diag |
| 4.3.52 |
| 451 |
| 5980678 |
| Search Radar and IFF Sys ISO and Block Wrg Diag |
4.3.53
| MSC Tech Library Guidance – Tech Manual Creation/Modification |
| Word |
| 4.3.54 |
| 432 |
| 5980626 |
| Dial Tel and Shoreline Tel Sys Iso Wrg Diag |
| 4.3.55 |
| 432 |
| 5980629 |
| SP Tel 1JV, 2JV, 4JV, and X10J ISO and Elem Wrg Diag |
| 4.3.56 |
| 432 |
| 5980631 |
| SP Tel CKT 2JZ and X2JZ Iso and Elem Wrg Diag |
| 4.3.57 |
| 432 |
| 5980632 |
| Sp Tel Ckt 1JG and “E” Call ISO and Elem Wrg Diag |
| 4.3.58 |
| 433 |
| 5980634 |
| Emer ANCG Sys and Flt Crash Alm ISO Wrg Diag |
| 4.3.59 |
| 437 |
| 5980636 |
| Capt’s Ready DK Sig Ckt FS Blk and Elem Wrg Diag |
| 4.3.60 |
| 437 |
| 5980638 |
| Elec Clock ISO and Elem Wrg Diag |
| 4.3.61 |
| 436 |
| 5980642 |
| Engr Watch and Deck Call Sys Iso and Elem Wrg Diag |
| 4.3.62 |
| 433 |
| 5980644 |
| Flt Dk ANCG and Helo Intercom and Fog Bell/Gong ISO and Elem Wrg Diag |
| 4.3.63 |
| 436 |
| 5980649 |
| Smoke and Heat Detection Sys ISO Wrg Diag |
| 4.3.64 |
| 436 |
| 5980657 |
| Eng Ord Tlg, Bell Logger, Sft and Pmp Revolution Ind Sys |
| 4.3.65 |
| 437 |
| 5980659 |
| Rudder Angle Ind Sys Iso and Elem Wrg Diag |
| 4.3.66 |
| 150 |
| 5982024 |
| Mods to Existing Deckhouse |
4.3.67
| 390-404-007 |
| Arrangement of Wheelhouse and Bridge Wings |
4.3.68
| 390-400-004 |
| Navigation Console Details |
| 4.3.69 |
| 321 |
| 5980473 |
| Power System Ventilation Fr 60-Fwd |
| 4.3.70 |
| 186 |
| 5980441 |
| Misc Fdns |
| 4.3.71 |
| 171 |
| 5980455 |
| Rework to Main Mast |
| 4.3.72 |
| 422 |
| 5980614 |
| Helo Platf Ltg & Arr |
4.3.73
| 390-112-016 |
| Fdns in wheelhouse, “e” deck & house top |
| 4.3.74 |
| 437 |
| 5980628 |
| Wind Speed & Direction Ind Sys Iso & Elem Wrg Diag |
| 4.3.75 |
| 321 |
| 5980469 |
| Power System Elementary Wiring Diagram |
*To be provided at contract award
PDF/CAD
| 4.3.76 |
| 451 |
| 5980677 |
| Ship Radar Waveguide Arr & Det |
| 4.3.77 |
| 451 |
| 5980680 |
| Ship Radar Waveguide Arr & Det |
| 4.3.78 |
| 436 |
| 5980721 |
| Communication Center Intrusion Alarm Sys Ckt “DL” Iso & Elem Wrg Diag |
| 4.3.79 |
| 180 |
| 5980760 |
| Foundation in Wheelhouse for New Equipment |
| PDF/CAD |
| 4.3.80 |
| 301 |
| 8497639 |
| Integrated Bridge Arr of Wheelhouse and Bridge Wings |
| PDF/CAD |
4.3.81
| 436-100-511 |
| Ripout and Relocation of Foundations Wheelhouse |
4.3.82
| 390-604-019 |
| Joiner Arr Wheelhouse |
4.3.83
| 390-604-024 |
| Window Casings Wheelhouse |
4.3.84
| 390-604-025 |
| Window and Airport Casings |
4.3.85
| 390-604-032 |
| Ceiling Layout Wheelhouse |
4.3.86
| 436-540-896 |
| Composite Arr Pri Fly and Wheelhouse |
| 4.3.87 |
| 512 |
| 8387613 |
| Ventilation and Air Cond Diag |
| PDF/CAD |
| 4.3.88 |
| 264 |
| 8387622 |
| Heating Sys Diag |
| PDF/CAD |
| 4.3.89 |
| 401 |
| 6245487 |
| Comm Ckt 19MC and 1JG Fldk Staging Area, Garage and Ramp Area |
| 4.3.90 |
| 433 |
| 6631550 |
| Medical Announcing Sys Ckt "53MC" ISO Wrg Diag |
| 4.3.91 |
| 433 |
| 8391636 |
| 1MC Emergency Announcing System Upgrade |
| PDF/CAD |
4.3.92
| 705600 |
| Schematic/Wiring Diag ACO Panel - Gyro Compass/Wind System |
4.3.93
| 8496432 |
| 14-048R Electric Clock System Upgrade |
| PDF/CAD |
4.3.94
| Weight and Moment Calculation Sheet |
| Excel |
4.3.95
| Weight and Moment User Guide |
| Word |
4.3.96
| ABS Services |
| Word |
4.3.97
| Engineering Manager Help |
4.3.98
| O2E |
4.3.99
| ABS Service Request Form |
| Excel |
4.3.100
| MSC Electrical Drawing Template |
| CAD |
4.3.101
| MSC Naval Architect Drawing Template |
| CAD |
4.3.102
| MSC Mechanical Drawing Template |
| CAD |
4.3.103
| SECNAV 5512 DON ID Card Base Access Pass |
4.3.104
| ODP Form Blank |
| Excel |
| 4.3.105 |
| 433 |
| 5980683 |
| Medical Announcing Sys CKT “53MC” Elem Wrg Diag |
4.3.106
| 6631918 |
| Communications Block |
4.3.107
QASP
| 4.3.108 |
| 845 |
| 5989201 |
| Trim and Stability Booklet |
4.4. Order of Precedence: In the event of a conflict between specification requirements the following precedence shall be invoked:
4.4.1. This Technical Performance Specification
4.4.2. ABS Marine Vessel Rules
4.4.3. ABS Guide for Bridge Design and Navigational Equipment/Systems
4.4.4. U.S. Coast Guard Regulations
4.4.5. Military Sealift Command QMS Procedures Manual N0720-113.00-P Deck-PH (dated 13 July 2011)
4.4.6. IEEE-STD-45 Recommended Practice for Electrical Installations on Shipboard
4.4.7. COMSCINST 3530.1A 21 November 2017 Military Sealift Command Navigation Policy
4.4.8. MSC General Technical Requirements
4.4.9. In the event of a conflict between technical manual drawings and the below listed GFI detail drawings, the latest revision of the drawing shall apply.
4.5. Government Furnished Material: Pending Government approval and the award of Option 2 (Installation) the following materials will be provided during the duration of the shipyard availability:
4.5.1. Office Space – The Government will provide office space with desk and connectivity at the shipyard for up to four contractors.
4.5.2. Conference Facilities – The Government will provide conference facilities at the shipyard for the purpose of conducting meetings and training.
4.5.3. ECDIS, Radars, and the Radio equipment defined in section 6.1.4.60 – 6.1.4.65 of this PWS shall be procured by MSC. IBS contractor shall write the PWS for ECDIS and RADARs, and provide to MSC TPOC for procurement.
4.6. Acronyms
4.6.1. The following is a list of acronyms used in this document and all appendices:
· A/C – Air Conditioning
· ABS – American Bureau of Shipping
· AIS – Automatic Identification System
· ASTM – American Society for Testing and Materials
· BD – Business Days
· CAD – Computer Aided Design
· CDRL – Contract Data Requirements List
· CFR – Code of Federal Regulations
· CIVMAR – Civil Service Mariner
· COR – MSC Contracting Officer Representative
· CPU – Central Processing Unit
· CUI – Controlled Unclassified Information
· DFARS – Defense Federal Acquisition Regulation Supplement
· DGPS – Differential Global Positioning System
· DNC – Digital Nautical Charts
· DSC – Digitally Selective Calling
· DWG – AutoCAD Drawing Format
· ECDIS – Electronic Chart Display and Information System
· ENC – Electronic Navigational Charts
· EOT – Engine Order Telegraph
· SLEP – Service Life Extension Program
· FAR – Federal Acquisition Regulation
· FAT – Factory Acceptance Testing
· GFI – Government Furnished Information
· GFM – Government Furnished Material
· GMDSS – Global Maritime Distress and Safety System
· GPS – Global Positioning System
· HVAC – Heating, Ventilation, and Air Conditioning
· HZ - Hertz
· IAW – In Accordance With
· IBS – Integrated Bridge System (Also used in conjunction with the IBS Console and IBS Equipment)
· IEEE – Institute of Electrical and Electronics Engineers
· IFF – Identification, Friend or Foe
· IHO – International Hydrographic Organization
· ILS – Integrated Logistics Support
· IMO – International Maritime Organization
· INS – Integrated Navigation Systems
· ITAR – International Traffic in Arms Regulations
· KO – Kick-Off Meeting
· LAN – Local Area Network
· LED – Light Emitting Diode
· LIC – List of Instruments and Control Signals
· LOS – Line of Sight
· MCCS – Machinery Centralized Control System
· MS - Microsoft
· MSC – U.S. Navy Military Sealift Command
· MSCREP – Military Sealift Command Representative
· MTBF – Mean Time Between Failure
· MVR – Marine Vessel Rules
· N/A – Not Applicable
· NASSCO – National Steel and Shipbuilding Company
· NAVSEA – Naval Sea Systems Command
· NAVTEX – Navigational Telex
· NBLES – Navigation Bridge Layout and Equipment/Systems
· NSN – National Stock Number
· NVIC – Navigation and Vessel Inspection Circular
· OEM – Original Equipment Manufacturer
· OPNAV – Office of the Chief of Naval Operations
· PDF – Adobe Portable Document Format
· PDR – Preliminary Design Review
· PIT – Platform Information Technology
· PLC – Programmable Logic Controller
· POA&M – Plan of Action and Milestones
· PRS – Performance Requirements Summary
· PSI – pounds per square inch
· PWS – Performance Work Statement
· QA – Quality Assurance
· QASP – Quality Assurance Surveillance Plan
· QMS – Quality Management System
· RIO – Remote Input/output
· RNC – Raster Navigational Charts
· ROS – Reduced Operating Status
· RPM – Revolutions Per Minute
· SOLAS – Safety of Life at Sea
· SOVT – System Operational Verification Test
· SOW – Statement of Work
· SRD – Selected Record Drawings
· TBD – To Be Determined
· TOD – Tactical Ocean Data
· TPOC – Technical Point of Contact
· UHF – Ultra-High Frequency
· UPS – Uninterruptable Power Supply
· USCG – United States Coast Guard
· USN – United States Navy
· USNS – United Stated Naval Ship
· VAC – Voltage, Alternating Current
· VDR – Voyage Data Recorder
· VHF – Very-High Frequency
· REINSTALL- This term shall mean to relocate as required and to reinstall the equipment including any re-fabrication required for new location including any foundations, cabling or associated components of the system.
5. DESIGN CONDITIONS
5.1. Equipment installed under this contract shall retain full rated capabilities when operating under the environmental conditions listed below. The IBS Contractor shall be responsible for designing modifications of the existing navigation and communications systems as necessary to meet the conditions listed in this section and as required by equipment vendors selected by the IBS Contractor.
· Weather ambient air temperatures of 0°F minimum to 95°F dry and 82°F wet bulb
· Seawater temperatures of 30°F minimum to 95°F maximum
· Barometric Pressure of 14.7 psi (1 Bar)
· Systems and equipment exposed to the weather shall withstand a wind loading of 0.22 lb/in2 of projected area and snow and ice loading of 0.06 lb/in2.
· Equipment installed under this contract shall be designed to operate satisfactorily under the Athwartships and Fore-and-Aft Design Angles of Inclination shown in Reference 4.2.1, Chapter 4-1-1, Table 7.
· The Wheelhouse (04-34-0) and related spaces are air conditioned to maintain a temperature not to exceed 80ºF.
· Modifications to the Wheelhouse (04-34-0) and related spaces shall be designed to maintain conditioned space temperatures in accordance with Reference 4.2.18.
6. SPECIFIC TASKS
6.1. BASE PERIOD – ENGINEERING AND DESIGN
The IBS Contractor shall be responsible for performing the necessary engineering and design to accomplish the provision, fabrication, removals, installation, commissioning operation and certification of the IBS and Compartment Upgrades (as described in this Section) in accordance with applicable ABS, USCG, IMO, IEEE and vendor requirements. The term IBS, Integrated Bridge System, collectively refers to the equipment, consoles, systems, features and functions that facilitate the safe operation of the vessel and systems as described in this PWS.
The IBS contractor shall certify that the new equipment and systems to be procured and installed are current and commercially available production models and have a documented supportability plan for a minimum of 20 years of satisfactory operation and maintenance. Additionally, the system shall be certified to be in continued production for a minimum period of 5 years after installation.
In accordance with this technical specification, the IBS Contractor shall develop detailed engineering drawings, calculations, equipment specifications, work items, equipment lists and test procedures to install the equipment and systems necessary to implement the IBS and Wheelhouse Upgrades. The design shall provide safe and efficient navigation of the vessel during all operational conditions and evolutions. As part of the Base Period contract, the IBS Contractor will be responsible for performing the following specific tasks:
6.1.1. Integrated Master Schedule (CDRL A004): The IBS Contractor shall develop a detailed Plan of Action and Milestones (POA&M). The POA&M shall consist of a timeline showing activities from contract award to the end of the Base Period including task start times, duration and how these tasks support the delivery dates and review periods associated with contract deliverables. A draft version of this POA&M shall be submitted to MSC for review 5 BD prior to Kick-Off (KO) Meeting. 5 BD after the KO Meeting, a revised POA&M reflecting any changes agreed on in the KO meeting shall be submitted to MSC. The POA&M shall be updated weekly to reflect actual progress and submitted with the monthly progress reports and action Item tracker (CDRL A006 A006) to MSC. Near the end of the Base Period, the POA&M CDRL A004 shall be revised to include the procurement and integration schedule CDRL B008 showing general sequence of the material procurement and integrations associated with this contract to the end of Option 1. Near the end of Option 1, the POA&M shall be revised to include the installation and technical support schedule CDRL C001 showing general sequence of the installation and technical support tasks associated with this contract to the end of the contract. The POA&M will serve as a metric to gauge the IBS Contractor’s schedule performance and shall be updated weekly to reflect actual progress.
6.1.2. Kick-Off (KO) Meeting: The IBS Contractor shall conduct a KO meeting with MSC, all IBS Contractor team members and key personnel. The IBS Contractor shall contact the Technical Point of Contact (TPOC) and arrange the date and location of the meeting. The IBS Contractor shall submit minutes from the meeting and the revised POA&M for MSC review and approval.
6.1.3. Shipcheck(s): The IBS Contractor shall conduct a minimum of two shipchecks of USNS Mercy (T-AH 19) in order to gather information necessary to design and accomplish IBS and Wheelhouse Upgrades. The Contractor shall complete Sperry ECDIS/RADAR (CDRL A008) survey during shipcheck and submit to MSC for review against ECDIS/RADAR procurement specification for the purpose of determining equipment needed. The Sperry ECDIS/RADAR survey will be provided as GFI 4.3.43. The first shipcheck will be to gather information in support of the Wheelhouse (04-34-0), Communications Suite (03-37-2) and related space reconfiguration and upgrades, steering gear control systems modifications and the IBS installations and integrations.
During the shipcheck(s), the Contractor shall take shipcheck notes (CDRL A003) that physically and dimensionally verify the existing ship conditions including structure, piping, ducting, cableways, power panels, load centers, radio tie-ins, structure, arrangements, and affected equipment necessary to complete all design deliverables listed in Section 3.1. The Contractor shall verify and document the existing wiring hook-up. The Contractor shall also perform a dimensional verification of ship structure in way of modifications and record for incorporation into design packages. All permanent and temporary interferences in way of structure, penetrations, piping, HVAC and electrical installations shall be recorded in detail. MSC TPOC will be present during the ship check to assist contractors with location of equipment, provide technical detail, and act as liaison between Contractor and ship’s force.
The second shipcheck will be performed to validate these modifications and upgrade designs prior to submission to ABS. The IBS Contractor shall assume both shipchecks will take place on the west coast. All shipchecks will be scheduled with the MSC Contracting Officer’s Representative (COR). MSC COR will coordinate the shipchecks with Mercy’s Port Engineer, Chief Engineer and crew to ensure that ships force can support and schedule any system outages required for a complete shipcheck. MSC Representatives will be present during the shipcheck to assist as necessary. Contractor is responsible for meeting all access requirements for both the location and the vessel.
6.1.3.1. Shipcheck Plan (CDRL A001): Two business days prior to each pre-shipcheck meeting, the IBS Contractor shall provide a shipcheck plan detailing the spaces and systems to be investigated and including a recommended schedule to accomplish the plan.
6.1.3.2. Pre-Shipcheck Meeting: The IBS Contractor shall schedule a pre-shipcheck teleconference at least five business days prior to shipcheck. MSC and the IBS Contractor’s shipcheck team shall be in attendance. At a minimum, all key personnel shall be members of the shipcheck team. The purpose of this teleconference is to discuss the IBS Contractor’s shipcheck plan, confirm shipcheck team members, cover ship access requirements, and discuss any other shipcheck related details.
6.1.3.3. Shipcheck (No.1): IBS Contractor shall assume that the vessel will be available for a 3-week period. IBS Contractor shall assume that all shipchecks will be pier-side. For planning purposes and if the vessel is underway during a portion of the shipcheck, onboard berthing will be provided for IBS Contractor personnel. Contractor shall be responsible for gas freeing any spaces required during shipcheck.
6.1.3.4. Shipcheck (No.2): IBS Contractor shall assume that the vessel will be available for a 2-week period. IBS Contractor shall assume that all shipchecks will be pier side. For planning purposes and if the ship is underway during a portion of the shipcheck, onboard berthing will be provided for IBS Contractor personnel. Contractor shall be responsible for gas freeing any spaces required during shipcheck.
6.1.3.5. Shipcheck Notes (CDRL A003): The Contractor shall provide daily Ship Check Notes throughout the duration of the shipcheck(s). The Ship Check Notes shall be consolidated at the end of each day and forwarded electronically to the TPOC. The Contractor shall meet each morning with the TPOC to discuss the Ship Check Notes from the previous day and to discuss the work plan for each day. This daily meeting will address any questions or concerns from the day before as well as lay out requirements for that day. The Contractor shall discuss its notes with the TPOC and conduct a brief walk-through of the areas to be worked that day to ensure all of the necessary information is being collected.
6.1.3.6. Shipcheck Meeting: The Contractor shall conduct a meeting on the first day of the shipcheck and brief the TPOC and ship’s crew on the schedule. The Contractor shall conduct a meeting on the last day of the shipcheck(s) to summarize the ship check events and to discuss any outstanding concerns. The Contractor shall review all the Ship Check Notes and conduct a complete walk-through of all the areas addressed in this PWS. The purpose of the walk-through is to ensure all the necessary information has been collected to develop the required work packages. It is the responsibility of the Contractor to ensure that all information needed to complete this requirement has been gathered during the shipcheck(s). The review and monitoring by the Government does not relieve the Contractor from this responsibility.
6.1.3.7. Shipcheck Report (CDRL A002): IBS Contractor shall develop a shipcheck report and submit to MSC within 10 BD after each shipcheck is completed. The report in MS Word format shall state who attended the shipcheck, the dates and duration of the shipcheck and information gathered during the shipcheck. The report shall include a list of comments and recommendations regarding the design from the information gained during the shipcheck and include any proposed changes to the original design scope, concerns about existing equipment capacity, arrangement, condition, etc. The report shall detail the findings of the shipcheck, actions taken during the shipcheck, and all pertinent photos. The report shall provide a complete list of all current bridge equipment, its condition, and which items shall be retained. The report is to include existing ship condition and any reservations, deficiencies, or anticipated problems in developing the work package. The report shall document all decisions and assumptions made during the shipcheck. All photos shall be organized in a PowerPoint presentation with one photo per slide and a short description accompanying each photo.
6.1.3.8. Post-Shipcheck Meeting: The IBS Contractor shall host a post-shipcheck teleconference one week after contractor delivers shipcheck report to MSC, and shall be prepared to discuss with MSC the information gathered in the Shipcheck Report, the plans for each space, and the organization of work packages. All IBS Contractor shipcheck team members and key personnel shall be in attendance.
6.1.4. System Design: The IBS system design (CDRL A010) shall incorporate the following tasks:
6.1.4.1. The IBS Contractor shall design a fully Integrated Bridge System to be installed on a CIVMAR operated bridge, which will allow for the safe navigation and operation of the vessel. This IBS will replace the current navigation bridge consoles.
6.1.4.2. All user-operated IBS interface screens shall be a minimum of 23 inches when measured diagonally. Additionally, the screens shall be capable of displaying the correct ratio to display ECDIS/RADAR without distortion. The Contractor shall install thirteen (13) screens with the capability of displaying and controlling ECDIS and Radars.
6.1.4.3. As part of the design, all equipment utilizing an antenna of any kind shall include the replacement of the antennas with new current model IMO type approved, including foundation, mounting hardware, kick pipe, power and communication cables, and cable transits. Locate all new antennas to limit the potential of local interference.
6.1.4.4. The IBS contractor shall certify that the new equipment and systems to be procured and installed are current and commercially available production models and have a documented supportability plan for a minimum of 20 years of satisfactory operation and maintenance. Additionally, the system shall be certified to be in continued production for a minimum period of 5 years after installation.
6.1.4.5. The IBS shall be certified in accordance with Reference 4.2.1 and achieve a classification of NBLES (Navigational Bridge Layout Equipment/Systems) as specified in Reference 4.2.2. In addition, the IBS shall meet the performance requirements of Reference 4.2.15.
6.1.4.6. Design documentation shall be submitted to show the integration of new components with the existing system, to include updated Lighting One Line Diagram (CDRL A025) system design and a new Failure Mode and Effects Analysis (CDRL A022) of the IBS.
6.1.4.7. Information/data sheets for all main components to be used, ABS type approval certificates for equipment to be provided, or the contractor’s plan to obtain ABS approval, shall be provided under Option Period 1 as described below.
Navigational Systems and Route Planning
6.1.4.8. The IBS Contractor shall install a new IMO/USCG compliant and OPNAV approved Sperry ECDIS (provided as GFM in para 4.5.3), that will consist of five (5) fully operational nodes at all multifunction displays and control stations. Upon MSC receipt of the Sperry ECDIS/Radar survey (CDRL A008) after the shipcheck, MSC will provide the technical documentation for the contractor to complete drawings. IBS Contractor shall be responsible for writing the Task Order to procure the ECDIS. The equipment, tech manuals, and dock & sea trial test procedure will be delivered as GFI/GFM after award. System shall be designed with Total Watch (IBS Contractor Furnished and Installed) for ECDIS and Radar. Primary and backup ECDIS must be fed from separate power sources. ECDIS cables to any other Equipment or Power Cables is not GFM and IBS Contractor to prove. Nodes shall be installed in the following locations:
· IBS Console – (Primary Node to be located centerline as close as possible)
· IBS Console– (Backup Node)
· Route Planning Workstation Console
· Mate-on-Watch Navigation Station Console
· Captain’s Office (shall be password protected)
6.1.4.9. Additionally, the IBS Contractor shall procure and install eight (8) mimic screens of the IBS Console primary node. Mimic screens shall be installed in the following locations:
· Captain’s Cabin
· Captain’s Console
· Port Bridge Wing
· Starboard Bridge Wing
· Near forward center window on swivel arm
· IBS Console (more than 1 can be located in the IBS Console)
· Machinery Centralized Control System (MCCS) in the EOS
6.1.4.10. The ECDIS processing units and nodes shall be remotely located. Contractor shall propose a suitable location, in consultation with MSC COR. Contractor shall install a lock on the door and take other appropriate measures to meet the requirements for housing the ECDIS Components. ECDIS components shall be rack-mounted with dedicated UPS units (IBS Contractor Furnished and Installed) for each.
6.1.4.11. ECDIS installations will be capable of protecting track data as Controlled Unclassified Information (CUI) in accordance with USN guidelines.
6.1.4.12. The ECDIS system shall have the ability to display an overlay of the 3cm X-band and 10cm S-band radars. The Radars shall also have the ability to display ECDIS track lines.
6.1.4.13. The ECDIS will be configured to receive and display NAVTEX message data and warnings, and depth.
6.1.4.14. The ECDIS shall have the ability to access and read electronic charts as follows:
· Official, government-approved Electronic Navigational Charts (ENC) in IHO S-57 format
· Official, government-approved Raster Navigational Charts (RNC)
· NGA produced Digital Nautical Charts (DNC)
· Tactical Ocean Data Op Area Charts (TOD 0)
· Procurement of new ECDIS systems shall feature upgrade capability to adopt future IHO S-100 standards.
6.1.4.15. Remove and reinstall RD-30 Remote Display Data Organizers to display depth, heading, and speed at the following locations:
· Mate-on-Watch Station
· Route Planning Workstation Console
· Centerline above the forward window
· Purchase 1 additional for the Captain’s Console
6.1.4.16. The Port and Starboard bridge wing console stations equipment to be replaced or relocated shall include, but is not limited to, the following:
· ECDIS (with radar overlay, depth indicator and anemometer)
· GPS (or display on ECDIS)
· Gyrocompass repeaters with Pelorous stands and an azimuth
· Rate of Turn Indicator
· Rudder Angle Indicator
· Rudder Course and RPM Board
· Shaft Speed RPM Indicator
· Steering Controls (at minimum on port side)
· Throttle Controls with electric shaft option
· Combined Air/Steam Whistle control
· Search light and Morse Lamp controls
· VDR Microphone
· Bridge Wing Communications Circuit JL
· Sound Powered Telephone X10J Refuel at Sea Station
· Sound Powered Telephone 1JV Ship Control and Maneuvering
· EOT repeater
· Speed Over Ground
· VHF Remote Headset
· Single Audio System (SAS) “RHMS” Secure Red Telephone
· Binocular with stand– shall not interfere with the direct line of sight between bridge wing conning station and wheelhouse.
6.1.4.17. The IBS Contractor shall replace the currently installed GPS systems (antenna, displays, and cabling). The Contractor shall install commercial IMO approved GPS units with minimum twelve (12) outputs. Integrate new GPS System(s) with navigation equipment. GPS system shall have an automatic switch over. Remove the WRN-6 and all associated components.
6.1.4.18. Replace the gyrocompass system and repeaters. Contractors shall update GFI 4.3.1, 4.3.3, 4.3.13, and 4.3.14, revise drawings to install (2) IMO approved Fiber Optic Gyros (FOGs) with a 5-year warranty and a service cycle of 5 years minimum. FOGs must be supportable for 15 years. The gyros shall be roll, pitch, and heave capable. The new IBS shall be configured to have the option to select the data signal from either gyrocompass at the steering station. Contractor shall update this GFI to reflect relocating the new gyrocompass Master units from their proposed location to the Search Radar & Tacan Equipment Room (03-36-2).
6.1.4.18.1. The existing gyro repeaters shall be replaced with new digital IMO type approved commercial gyro repeaters with radial rate of turn indication and served by the new Gyro Compasses. The digital repeaters shall be installed the following locations:
· Above Bridge Center Window visible from Steering Stand
· IBS Console
· Route Planning Workstation Console
· Mate-on-Watch Navigation Station Console
· Captain’s Console
· Steering Gear Room (Port and Starboard Side)
· Port and Starboard Bridge Wing
6.1.4.19. Relocate existing magnetic compass and periscope to be viewable at the steering station.
6.1.4.20. The IBS Contractor shall identify and delineate line-by-line all equipment components which require GPS and gyrocompass inputs, including the glide slope indicator, and allow sufficient outputs for the future Machinery Centralized Control System (MCCS) automation upgrade.
6.1.4.21. IBS Contractor shall replace the rudder angle indicators at all current locations found throughout the vessel, including bridge wings, with new current model IMO approved commercial rudder angle digital signal indicators with zero (0) rudder angle at the twelve (12) o’clock position. Additionally, rudder angle indicators shall be installed in the following locations:
· Above Bridge Center Window visible from Steering Stand
· IBS Console
· Route Planning Workstation Console
· Mate-on-Watch Navigation Station Console
· Captain’s Console
· Steering Gear Room (Port and Starboard Side)
· Port and Starboard Bridge Wing
Provide a separate block & elementary wiring diagram for this circuit.
6.1.4.22. A 360-degree viewable rudder angle indicator shall also be installed in the overhead above the steering station and within clear view of all workstations. Indication range shall be shown on all sides of this unit. In addition, two separate indications shall be provided to display helm order as well as actual rudder angle.
6.1.4.23. Replace the Rate of Turn Indicators (ROTI) at all current locations found throughout the vessel, including bridge wings with new current model IMO type approved. Additionally, rate of turn indicators shall be installed in the following consoles:
· Above Bridge Center Window visible from Steering Stand
· IBS Console
· Route Planning Workstation Console
· Mate-on-Watch Navigation Station Console
· Captain’s Console
· Steering Gear Room (Port and Starboard Side)
· Port and Starboard Bridge Wing
6.1.4.24. Relocate existing course and RPM board.
6.1.4.25. Replace speed log gate valve at hull. Remove existing Sperry Speed Log Gate Valve and replace with Furuno transducer gate valve (DS-786). Structural modifications to the space/hull with be required. Re-install existing transducer and cable through new valve and connect to system. Speed log shall feed all the existing equipment that requires speed input. Distance log displays shall be installed on the Mate-on-Watch and Route Planning Workstations. All synchro speed indicating repeaters shall be replaced with ones capable of receiving a digital signal. Contractor shall update GFI 4.3.12 to renew the speed log. Replace displays with ones capable of receiving a digital signal at the following locations:
· Wheelhouse centerline forward viewable from the steering stand
· Mate-on-Watch Navigation Station Console
· Route Planning Workstation Console
· Port Bridge Wing
· Starboard Bridge Wing
6.1.4.26. Replace the shaft speed RPM indicators and tachometer with new current model IMO type approved commercial indicators and tachometer throughout the vessel, to include in the following locations:
· Wheelhouse centerline forward
· Port Bridge Wing
· Starboard Bridge Wing
· Steering Gear Room
6.1.4.27. Remove two (2) Raytheon Fathometer gate valves and associated transducers at hull. Install one (1) Furuno Fathometer gate valve (GV-50B-6B), 50 kHz transducer and associated cabling at location of original installation. Install one (1) Furuno Fathometer gate valve (GV-200B-8B), 200 kHz transducer and associated cabling at location of original installation. Structural modifications to the compartment/hull will be required. Connect both systems to existing Furuno head units on bridge. The depth sounding system shall provide data feeds into the new IBS, Navigation Equipment, and MCCS. Contractor shall update fathometer reference drawing to reflect final configuration. Government has provided GFI 4.3.11 and 4.3.44 for information purposes only.
6.1.4.28. Provide a new current model IMO approved course recorder to be integrated in to the IBS.
6.1.4.29. Relocate Captain’s Chair and replace with a new Captain’s chair and install a new console.
6.1.4.30. Replace the non-electrical/non-electronic navigation aids including barometer and clinometers with new current model IMO type approved to be integrated into the new Wheelhouse Arrangements.
6.1.4.31. Provide a new current model IMO type approved Voyage Data Recorder (VDR) System. The VDR shall be integrated into the IBS and the MCCS and receive data feeds from each and all signals required by IMO regulations. Maintain existing additional salient characteristics above those required for IMO compliance including ability to record bridge to bridge VHF radio audio signals from pilot house and helo flight control stations radios. VDR shall be of the float free type. Remove existing SVDR System.
6.1.4.32. Retain and relocate as required the Pilot plug for the Automated Identification System (AIS) and receptacle in the work area for the pilot on the port forward side of the bridge. Provide a new pilot workstation.
6.1.4.33. Replace existing Automatic Identification System (AIS) system with new current model IMO type approved with commercial AIS tactical software package. Provide data feed to the new IBS. The own-ship data transmit shall be easily and quickly switchable from the transmit mode to the non-transmit mode.
6.1.4.34. Relocate the Navigational Telex (NAVTEX) system. Relocate the Furuno DFAC FAX-207.
6.1.4.35. Replace Long Running Intercept X-Tracking (LRIT) mini Sat-C Inmarsat System with new current model IMO type approved model.
6.1.4.36. IBS Contractor shall install three radar systems that shall be fully integrated into the IBS and configured so that either of the two (2) X-band 3cm or one (1) S-band 10cm signals can be selected and controlled at each of the IBS Multi-Function Workstations. Upon MSC receipt of Sperry ECDIS/Radar survey after the shipcheck, MSC will provide technical documentation for the contractor to complete the drawings. IBS Contractor shall be responsible for writing the PWS to procure the Radars.
6.1.4.36.1. Install new primary and secondary current model IMO type approved commercial X-Band radar system. The antenna shall be positioned such that all angles abaft of the beam are visible at all times and that, with the other X-band radar system, 360-degree coverage is provided.
6.1.4.36.2. Install a new current model IMO approved commercial S-band Radar System. The antenna shall be positioned such that 360-degree coverage is provided at all times.
6.1.4.36.3. All displays shall be able to combine the signals of the two X-band radars. This operation shall not degrade the presentation of the radar source selected as primary.
6.1.4.36.4. The Radars shall also have the ability to display ECDIS track lines.
6.1.4.37. Replace the steering stand with a new current model IMO type approved system. The steering stand shall include a steering order telegraph, off-course alarm, motor failure alarm, steering gear failure alarm, low oil level alarm, and pump controller/selector and be located to ensure maximum possible visibility.
6.1.4.38. Replace the Engine Order Telegraph (EOT) and throttle controls with a new current model IMO type approved combination EOT/Throttle Control with an electric shaft, single handle, integrated throttle controls at the steering station, bridge wings and in EOS. The OEM for the existing EOT/Throttle Control is TMS; contractor shall be responsible for interfacing with the OEM for replacing the EOT/Throttle Control. The EOT shall display commercial orders. EOT shall be of the mechanical type.
6.1.4.39. Provide a new current model IMO type approved emergency EOT with one repeater in the IBS console and one in the MCCS.
6.1.4.40. Provide a new current model IMO approved Commercial Helm Order and Rudder Angle Indicator Combination Unit to be located on the port and starboard side of the Steering Gear Room & (1) in wheelhouse.
Monitoring and Alarms Systems
6.1.4.41. Existing monitoring and warning systems and alarm annunciation and control shall be integrated into the IBS. Annunciation and control of alarms as follows shall be located at the steering station console in a centralized and easily accessible position:
· Steering Gear Monitoring
· Pump Switching Control
· Bus Failure Alarm Signals
· Gyro System Failure Alarm to include annunciation, acknowledgement, and silencing
6.1.4.42. Not used.
6.1.4.43. Remove and reinstall fire detection system.
6.1.4.44. A Damage Control Station shall be incorporated into the IBS with the following list of alarm monitoring and warning systems, alarm annunciation, control, and acknowledgement:
· Fire Door Control
· Flooding Alarm System
· Watertight door monitoring and control
6.1.4.45. System shall allow for 20% additional inputs/outputs for expansion and for future connections.
6.1.4.46. Install new water temperature system with a new current model IMO type approved with a repeater located on the IBS console and the Mate-on-Watch Navigation Station Console and Route Planning Workstation Console. The water temperature system shall provide a data feed into the new IBS.
6.1.4.47. Replace the existing electronic signaling systems for the following equipment including, but not limited to the general alarm actuator, automatic and manual maneuvering, fog and distress bells/gongs, integrated air/steam whistle with selector, Morse signaling light, horn and hailer with new current model IMO type approved commercial systems and incorporated into the new IBS console.
6.1.4.48. Provide programmed buttons that sound alarms for the following, but not limited to Steering failure, Man Overboard, collision, chemical attack, helo crash and wave-off alarms. Interface alarms with the helo tower.
6.1.4.49. Relocate Collision, General Alarm, and Chemical Alarm contact switches to the new IBS console.
6.1.4.50. Replace Navigation and Signal Light Control Panel with controls and locate on the new IBS Console.
6.1.4.51. Relocate bridge FS Green and Red Ready Deck Lights, with switch reinstalled in the Captain’s Console. Relocate aircraft wave-off panel currently on the joiner bulkhead to the Captain’s Console.
6.1.4.52. Relocate 2 outlets for Aldis lamps at current locations on vessel.
6.1.4.53. Relocate existing Ship Security Alert System (SSAS) base unit and any associated buttons throughout the wheelhouse areas.
6.1.4.54. Relocate existing RADIAC that is currently on the forward bulkhead, starboard side.
6.1.4.55. The vessel currently has 2 wind systems. The IBS contractor shall replace both wind systems with the most current model NAVAIR approved weather monitoring system with flight capability, a remote display for the helo tower, and the ability to monitor the following parameters, at a minimum:
· Wind Direction
· Wind Speed
· Atmospheric Pressure
· Ambient Temperature
· Humidity
· Relative Humidity
· Dew Point All components of the system shall be replaced including the wind birds, indicators, wiring, ACO Panel, Transmitters, terminal boxes, bridge and helicopter control station displays. A minimum of two transmitters and two wind birds shall be provided. The wind birds, indicators, and display units will be provided as GFE.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .