AMENDMENT 0002_ATTACHMENT J -38 _BNC _PAST PERFORMANCE QUESTIONNAIRE

View the file

Other files

File Type Posted
SF_30_AMENDMENT_0006_BNC_USCA18R0158_dtd_11-29-2018.pdf PDF
J_ATTACHMENTS_BNC_AMENDMENT_0006_11-29-18_Redacted.pdf PDF
Amendment_0006_-_Government_response_to_Offeror's_submission_questions_dtd_11-29-18.pdf PDF
AMENDMENT_0006_ATTACHMENT_J-33_BNC_FY19_Procurement_Worksheet.xls XLS spreadsheet
USCA18R0158_Amendment_0005_BNC_Tiered_Pricing.xlsx XLSX spreadsheet
USCA18R0158_Amendment_0005_dtd_11-9-18.pdf PDF
Amendment_0004_-_Government_response_to_Offeror's_submission_questions_dtd_11-6-18.pdf PDF
STATEMENT_OF_WORK_CONTRACT_USCA-08-C-0506.pdf PDF
AMENDMENT_0004_RFP_USCA18R0158_BNC.pdf PDF
Government_response_to_Offeror's_submission_questions_Phase_1_dtd_10-29-2018.pdf PDF
AMENDMENT_0003_RFP_USCA18R0158_BNC.pdf PDF
AMENDMENT_0002_RFP_USCA18R0158_BNC.pdf PDF
Amendment_0001_-_USCA18R0158_-_Attachment_J-37_-_Judiciary_Information_Security_Guidance_and_the_Judiciary_Information_Security_Framework_Documents_for_Reading_Room.pdf PDF
AMENDMENT_0001_-_USCA18R0158_-_BNC.pdf PDF
Attachment_J-37_-_Judiciary_Information_Security_Guidance_and_the_Judiciary_Information_Security_Framework_Documents_for_Reading_Room.pdf PDF
AMENDMENT_0001_-_USCA18R0158_-_BNC.pdf PDF
RFP_USCA18R0158_-_BNC.pdf PDF
Section_J_Attachments_-_BNC_RFP_USCA18R0158.pdf PDF
Figure_1_-_C.2.1_-_Bankruptcy_Noticing_Center_Program_Process_Flow.pdf PDF
ATTACHMENT_J-33_BNC_FY19_Procurement_Worksheet_-_Section_B.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP#USCA18R0158 - AMENDMENT 0002

ATTACHMENT J -38 _BNC _PAST PERFORMANCE QUESTIONNAIRE

Source Selection Information – See Volume 14 Glossary and §150.20

For Official Use Only

Past Performance Questionnaire Template

Instructions:

◊ Sections I and II to be completed by the Offeror/Major Subcontractor and provided to the assessor (Government personnel that had experience with the Offeror/Major Subcontractor on a previous relevant contract). The assessor, in turn, to verify Sections I through III, complete the questionnaire, and submit to the Contracting Office. The Offeror should also submit with its proposal (by the closing date of the Solicitation) copies of Sections I and II of all questionnaires as provided to assessors.

◊ Section II to be validated by the assessor. If any information is incorrect herein, please annotate and provide the correct information accordingly.

◊ Sections III through VII to be completed in their entirety by the assessor.

Message to the assessor: Your feedback is requested on or before: October 1, 2018, 2:00 p.m. Eastern Time, to assist with establishing the performance history for the Contractor named below. In efforts to expedite receipt of the requested information, the Contracting Office respectfully requests that you do not mail hard copies. Instead, please E-mail the completed questionnaire(s) to:

pamela_martin@ao.uscourts.gov.

I. Solicitation Data (for the proposed effort)

Solicitation Number Project/Requirement Enter Project Name/Requirement Title Customer/Agency Enter Project Office Project/Requirement Description

Enter succinct Project/Requirement Description

II. Current or Historical Contract Information

Assessor: The performance data submitted by the Offeror is correct or incorrect.

CONTRACTOR NAME &

ADDRESS:

Contract No Type of Contract Initial Final Contract Value Period of Performance/Delivery Schedule

Project/Requirement Description

Please select from the following as it applies to this contract:

Contracting Role PRIME SUBCONTRACTOR mailto:pamela_martin@ao.uscourts.gov

Termination History Convenience Default N/A

III. Assessor Information

Assessor Name Title Phone Number/Email Address

Identify your role in the contract award or administration and the period of your involvement.

Role Period of Involvement

Procuring Contracting Officer (PCO)

Administrative Contracting Officer (ACO)

Contract Specialist

Contracting Officer’s Representative (COR)

Technical Project Lead/Project Officer

Quality Assurance Specialist

Defense Contract Audit Agency (DCAA) Auditor

Other:

IV. Evaluation Definitions

The following definitions should be used in your assessment of Contractor performance.

EXCEPTIONAL

Performance EXCEEDS MOST contractual requirements to the Government’s benefit. The performance of areas being assessed was accomplished with few minor issues or concerns.

VERY GOOD

Performance EXCEEDS SOME contractual requirements to the Government’s benefit. The performance of areas being assessed was accomplished with few minor issues or concerns, for which the Contractor’s corrective actions were highly effective.

SATISFACTORY

Performance MEETS contractual requirements. The performance of the areas being assessed contains minor issues or concerns, for which corrective actions taken by the Contractor were effective.

MARGINAL

Performance MEETS SOME contractual requirements. The performance of the areas being assessed includes significant problems, issues, or concerns for which corrective actions taken by the Contractor were only somewhat effective.

UNSATISFACTORY

Performance DOES NOT MEET contractual requirement. The performance of the areas being assessed includes serious problems, issues, or concerns for which the Contractor’s corrective actions were ineffective.

NOT APPLICABLE

(N/A)

Performance information not recent or relevant as defined in the Solicitation. Unable to provide assessment.

V. Performance Evaluation

1. Technical Performance

a. What is your OVERALL assessment of the Contractor’s ability to meet the technical requirements?

Exceptional Very Good Satisfactory Marginal Unsatisfactory N/A Technical Performance

Please provide rationale for the assigned rating.

b. Assess the Contractor’s technical performance in the following areas.

Integration Software Development

Testing Training Documentation

All comments are appreciated; however, at a minimum, rationale must be provided for ratings of exceptional or unsatisfactory.

c. Did the Government contribute in any way to any of the technical problems identified in the above assessment? Please explain.

d. Please describe the Offeror’s performance related to phase-in (transition) after contract award.

2. Schedule Performance

a. What is your OVERALL assessment of the Contractor’s ability to meet the schedule?

Please provide rationale for assigned rating.

b. Assess the Contractor’s schedule performance in the following areas.

Exceptional Very Good Satisfactory Marginal Unsatisfactory N/A

Software Data Items Assess the Contractor’s ability to resolve

Problems

d. Please describe any past performance issues, including late deliveries (e.g. reports, notice services).

3. Management

a. What is your OVERALL assessment of the Contractor’s management performance?

Management

b. Assess the Contractor’s management performance in the following areas.

Management Exceptional Very Good

Satisfactory Marginal Unsatisfactory N/A

MANAGEMENT

RESPONSIVENESS—

Timeliness, completeness, and quality of problem identification, proposal submittal, history of cooperative behavior, effective business relations, teamwork AND Customer satisfaction.

SUBCONTRACT

MANAGEMENT—Timely award and management of subcontracts and meeting subcontracting goals for small business, small disadvantaged business, etc.

PROGRAM

MANAGEMENT—

Effectiveness of integration and coordination of all activities required to execute the contract, use of resources, assignment of responsibility, internal coordination and communication, and risk management practices.

MANAGEMENT OF

PERSONNEL—Ability to select, retain, support, and replace personnel with the experience and expertise necessary to accomplish the Government’s requirements within schedule and budget.

INTEGRATED PRODUCT

TEAM MANAGEMENT—

Commitment and participation to the IPT process.

4. Cost Control

a. What is your OVERALL assessment of the Contractor’s ability to forecast, manage, and control costs?

Exceptional Very Good Satisfactory Marginal Unsatisfactory N/A

Cost Control

b. Assess the Contractor’s cost performance in the following areas.

Management Exceptional Very

Good Satisfactory Marginal Unsatisfactory N/A

COST REPORTING—

Accuracy and timeliness of the Contractor’s cost reporting data.

NOTIFICATIONS—

Timeliness of the Contractor’s notifications of costs as required by the Limitation of Cost/Funds Clauses.

RESOLUTION OF COST

PROBLEMS—Commitment to resolve cost issues—may include utilizing principles such as Cost as an

Independent Variable

(CAIV)

ADHERENCE TO COST

TARGETS—Ability to establish and meet the realistic cost targets.

SUBCONTRACT COST

MANAGEMENT— Ability to forecast, negotiate, and control subcontract costs

VI. Overall Rating of Contractor’s performance (technical, schedule, management, and cost) on contract being assessed.

Exceptional Very Good Satisfactory Marginal Unsatisfactory

VII. General Comments:

Assessor’s Signature Date Telephone Number:

E-mail Address:

Contract No
Contract Value
Contracting Role
Assessor Name
EXCEPTIONAL
IV. Evaluation Definitions
The following definitions should be used in your assessment of Contractor performance.
Please provide rationale for assigned rating.
Please provide rationale for assigned rating.
VERY GOOD
SATISFACTORY
MARGINAL
UNSATISFACTORY
NOT APPLICABLE (N/A)
N/A
Marginal
Unsatisfactory
Marginal
Unsatisfactory
Management