Upper East Fork Laterals FRS 9 - Technical Specifications 100_.pdf
PDF 2 MB Posted
- Solicitation number
- 2027-002
- Issued by
- Hockley County, Texas
About this file
Upper East Fork Laterals FRS No. 9 Dam Rehabilitation - Technical Specifications
This is a comprehensive technical specifications document for the repair and rehabilitation of Upper East Fork Laterals FRS No. 9, a dam structure located approximately 2.5 miles north of Forney in Kaufman County, Texas. The project is sponsored by Kaufman County Commissioners Court and the Kaufman Van Zandt Soil and Water Conservation District in cooperation with the Texas State Soil and Water Conservation Board. The scope of work includes clearing and grubbing of designated areas, rebuilding upstream and downstream embankment slopes to specified design grades (3H:1V), installation of riprap shoreline wave protection, replacement of a 40-foot downstream segment of corrugated metal pipe (CMP) principal spillway conduit with concrete pipe, construction of a diaphragm drain around the downstream end of the spillway conduit, replacement of the low-level sluice gate and trash rack on the principal spillway riser structure, and regrading of the auxiliary spillway control section. The contract is structured as a unit price contract with a performance period of 202 calendar days, excluding weather days. The contractor must submit a construction progress schedule within 10 days of the Owner-Contractor Agreement, revised submittals 21 days prior to work initiation, and maintain detailed record documents throughout the project. A preconstruction meeting and site mobilization meeting are required, followed by progress meetings not to exceed one per month. An as-built survey prepared by a licensed Texas surveyor and operation and maintenance data in three-ring binders must be submitted prior to final payment.
The technical specifications document establishes detailed requirements for materials, equipment, labor, and construction procedures across 19 drawing sheets and multiple specification sections. The project incorporates Storm Water Pollution Prevention Plan (SWP3) requirements under TPDES General Permit No. TXR150000 due to the site exceeding five acres, with the contractor responsible for submitting an amended SWP3 prior to Notice to Proceed and maintaining copies on-site. Bid items include clearing and grubbing (measured by area), structure removal (lump sum), pollution control (lump sum payment prorated over estimated project months), sediment fence installation (linear feet with 75 percent payment upon completion and 25 percent upon removal), and permanent vegetative cover including seedbed preparation, seeding, mulching, and fertilizer application. Material specifications reference 2024 standards for items including aggregates, Portland cement, steel reinforcement, concrete pipe, plastic pipe, ductile iron pipe, riprap, slide gates, and geotextile. The contractor must obtain all necessary permits, comply with TPDES requirements including bi-weekly sediment control inspections and inspections within 24 hours of rainfall events exceeding 0.5 inches, and provide field engineering services through a registered Texas land surveyor. Payment is based on actual measurements and quantities accepted by the Owner, with final payment contingent upon submission of record documents, as-built surveys, and operation and maintenance manuals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFMQ 2027-002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR DESIGN OF
UPPER EAST FORK LATERALS FRS NO. 9 (TX03381)
KAUFMAN COUNTY, TEXAS
CONSTRUCTION SPECIFICATIONS
SPONSORED BY:
KAUFMAN-COUNTY COMMISSIONERS COURT
AND
KAUFMAN VAN ZANDT SOIL AND WATER CONSERVATION DISTRICT
COOPERATING WITH:
TEXAS STATE SOIL AND WATER CONSERVATION BOARD
SEPTEMBER 2026
vwebber JRC TX Stamp vwebber James Crowder
SEPTEMBER 2026 i
UPPER EAST FORK LATERALS FRS NO. 9
INDEX OF SPECIFICATIONS
REPAIR DESIGN OF
FRS NO. 9
UPPER EAST FORK LATERALS WATERSHED
Construction
Specification No.
Title
Date 1010 Summary of Work 1019 Contract Consideration 1025 Measurement and Payment 1039 Coordination and Meetings 1061 Project Permits 1300 Submittal Procedures 1500 Construction Facilities and Temporary Controls 1600 Material and Equipment 1700 Contract Closeout
2 Clearing and Grubbing 06/24 3 Structure Removal 06/24 5 Pollution Control 06/24 6 Seeding, Sprigging, and Mulching 06/24 7 Construction Surveys 06/24 8 Mobilization and Demobilization 06/24 9 Traffic Control 06/24 10 Water for Construction 06/24 11 Removal of Water 06/24 21 Excavation 06/24 23 Earthfill 06/24 24 Drainfill 06/24 26 Topsoiling 06/24 31 Concrete for Major Structures 06/24 34 Steel Reinforcement 06/24 42 Concrete Pipe Conduits and Drains 06/24 45 Plastic Pipe 06/24 53 Ductile Iron Pipe 06/24 61 Rock for Riprap 06/24 71 Water Control Gates 06/24 81 Metal Fabrication and Installation 06/24 92 Field Fence 06/24 94 Contractor Quality Control 06/24 96 Field Office 06/24 95 Geotextile 06/24 420 Site Preparation 04/25
SEPTEMBER 2026 ii
Material Specification No.
Title
Date
521 Aggregates for Drainfill and Filters 02/22 522 Aggregates for Portland Cement Concrete 02/22 523 Rock for Riprap 04/22 531 Portland Cement 02/22 532 Supplementary Cementitious Materials 08/23 533 Chemical Admixtures for Concrete 02/22 534 Concrete Curing Compound 05/23 535 Preformed Expansion Joint Filler 02/22 536 Sealing Compound for Joints for Concrete & Concrete
Pipe 04/22
537 Nonmetallic Waterstop 02/22 539 Steel Reinforcement 07/22 542 Concrete Culvert Pipe 02/22 547 Plastic Pipe 04/22 553 Ductile Iron Pipe 02/22 571 Slide Gates 04/22 581 Metal 02/22 591 Field Fencing Material 04/22 592 Geotextile 04/22
SEPTEMBER 2026 iii
There are two types of specifications in this contract: (1) Construction Specifications and (2) Material Specifications. The construction specifications are composed of two parts. The first part is called the closed specification and is the standard NRCS construction specification that begins with the SCOPE and ends with MEASUREMENT AND PAYMENT or PAYMENT. The second part is called the open specification and consists of the ITEMS OF WORK AND CONSTRUCTION DETAILS that are written specifically for this job. Content contained in the open specification serves to revise, replace, or enhance the referenced content contained in the closed specification. Content in the open specification also serves to revise, replace, or enhance the referenced content contained in the Material Specifications.
1. DEFINITIONS:
Contracting Local Organization (CLO) – The organization or agency awarding the contract. CLO is Kaufman County, Texas. Also referred to as the “Owner”.
Contracting Officer (CO) – The person who is designated and authorized to enter into and administer this contract on behalf of the CLO or his/her duly appointed successor or alternate. No other person has authority to act for the Contracting Officer unless such person has been delegated authority by the Contracting Officer in writing.
Government – Texas State Soil and Water Conservation Board (TSSWCB) Engineer - The person or his/her representative who is responsible for determining that the Contractor’s work conforms to the technical requirements as set forth in the drawings and specifications. Also called “Project Engineer” or “Contracting Officer’s Representative” (COR). These duties will be performed by a representative of Schnabel Engineering, LLC.
Government Representative (GR) - Project Engineer or other appointed individual who provides technical representation and/or knowledge to the TSSWCB and/or Contracting Officer during the construction contract.
Inspector – The person who performs daily inspection services for the CLO at the construction site and maintains accurate daily records of the work accomplished and the factors affecting its progress and quality. These duties are to be performed by a representative of Schnabel Engineering, LLC.
Quality Assurance (QA) - CLO Construction Inspector (onsite). These duties are to be performed by a representative of Schnabel Engineering, LLC.
Quality Control (QC) - Contractor's Construction Inspector (on-site)
2. DRAWINGS:
Repair Plans for Upper East Fork Laterals FRS No. 9, Kaufman County, Texas, nineteen (19) sheets.
3. LOCATION:
Upper East Fork Laterals FRS No. 9 is located approximately 2.5 miles north of Forney, Texas in Kaufman County.
4. PERFORMANCE TIME:
Time to be allowed for completion of contract is 202 calendar days (weather days not included).
SUMMARY OF WORK
01010-1
SECTION 01010
24220021.00
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Contract Description.
B. Work by Owner.
C. Contractor Use of Site
D. Work Sequence.
E. Owner Occupancy
1.2 CONTRACT DESCRIPTION
A. Work at the Project includes furnishing all materials, labor, tools and equipment for the repair of
Upper East Fork Laterals FRS No. 9 which shall include but not limited to:
1. Clear, grub and revegetate areas along the upstream slope and between the downstream toe of the embankment to a point that is 20 feet downstream and reinstall fencing;
2. Rebuild upstream slope to original design slope of 3H:1V and flatten downstream slope with earthfill to a 3H:1V slope;
3. Installation of shoreline wave protection in the form of riprap;
4. Replace downstream 40 ft segment of CMP Principal Spillway Conduit with concrete pipe;
5. Construction of a diaphragm drain around the downstream end of the principal spillway conduit;
6. Replacing the low-level sluice gate and trash rack on the principal spillway riser structure;
7. Regrading the Auxiliary Spillway Control Section.
B. Perform Work under a unit price contract with Owner in accordance with Conditions of Contract.
C. Work of the Contract is identified in the following:
1. Repair Design of Upper East Fork Laterals FRS No. 9 – Technical Specifications
2. Repair Design of Upper East Fork Laterals FRS No. 9 – Construction Drawings
1.3 WORK BY OWNER
A. Not Used.
1.4 CONTRACTOR USE OF SITE
A. Access to site shall be limited to designated areas as depicted on the Drawings prepared by
Schnabel Engineering, LLC (Engineer). Contractor to allow site access for Owner and his representatives, to include Engineer.
B. Contractor shall adhere to any and all conditions of the site facility safety and security plan(s).
C. Construction operations shall be limited to areas noted on Drawings.
01010-2
1.5 WORK SEQUENCE
A. Contractor may propose an alternate construction sequence to better suit his means and methods. Any modifications to the sequence listed below shall be submitted to the Engineer for review and approval. The Contractor shall submit his proposed construction sequence within 7 days after notice to proceed.
1. Installation of Sediment and Erosion Control devices;
2. Mobilization;
3. Location and protection of utilities;
4. Clearing of Vegetation and Stripping of Topsoil;
5. Replace downstream 40 ft segment of Principal Spillway Conduit;
6. Perform earthwork regrade upstream and downstream embankment slopes;
7. Construct upstream rip rap wave berm;
8. Construct the riprap-lined plunge pool at the downstream end of the proposed principal spillway conduit;
9. Replace the low-level sluice gate and trash rack on the principal spillway riser structure;
10. Regrade the Auxiliary Spillway control section;
11. Topsoil, seed, and maintain seeded areas until turf is established;
12. Cleanup of work limits;
13. Remove Sediment and Erosion Control devices;
14. Demobilization
1.6 OWNER OCCUPANCY
A. Cooperate with Owner to limit conflict and facilitate Owner’s operations.
B. Schedule the Work to accommodate Owner occupancy and use of facilities.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
• END OF SECTION •
CONTRACT CONSIDERATIONS
01019-1
SECTION 01019
A. Cash allowances.
B. Schedule of values.
C. Application for payment.
D. Change procedures.
E. Measurement and payment - unit prices.
1.2 RELATED SECTIONS
A. Section 01600, Material and Equipment: Product substitutions and options.
1.3 CASH ALLOWANCES
1.4 SCHEDULE OF VALUES
A. Submit Schedule of Values for applicable Payment Items in duplicate within 30 days after date of Owner-Contractor Agreement. Use EJCDC 1910-8-E.
B. Format: Identify each item with number and title of major specification Section.
C. Revise schedule to list approved Change Orders, with each Application for Payment.
1.5 APPLICATIONS FOR PAYMENT
A. Submit one electronic copy of each application on form included in the Contract Documents.
B. Content and Format: Utilize list of Payment Items and Schedule of Values for tabulating items in each Application for Payment.
C. Include an updated construction progress schedule.
1.6 CHANGE PROCEDURES
A. The Engineer will advise in writing of minor changes in the Work not involving an adjustment to Contract Sum/Price or Contract Time.
B. The Engineer may issue a Proposal Request or Notice of Change which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid.
Contractor will prepare and submit an estimate within 7 days. Change Notices or Change Orders will be authorized by the contracting officer
C. The Contractor may propose changes by submitting a Request for Change to the Engineer, describing the proposed change and its full effect on the Work. Include a statement
01019-2 describing the reason for the change, and the effect on the Contract Sum/Price and Contract Time with full documentation and a statement describing the effect on Work by other Contractors. Document any requested substitutions in accordance with Section 01600 - Materials and Equipment.
D. Stipulated Sum/Price Change Order: Shall be based on Proposal Request or Notice of
Change (as appropriate) and Contractor's fixed price quotation, or Contractor's request for a Change Order as approved by Contracting Officer.
E. Unit Price Change Order: For Contract Unit Prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not pre-determined, execute Work under a Work Directive Change. Changes in Contract Sum/Price or Contract Time will be computed as specified for Time and Material Change Order.
F. Work Change Directive: Engineer may issue a directive, signed by the CO/Owner, instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Sum/Price or Contract Time. Promptly execute the change.
G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract.
Contracting Officer in consultation with Engineer will determine the change allowable in Contract Sum/Price and Contract Time as provided in the Contract Documents.
H. Maintain detailed records of work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.
I. Execution of Change Orders: Contracting Officer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.
1.7 DEFECT ASSESSMENT
A. Replace the Work, or portions of the Work, not conforming to specified requirements.
B. If, in the opinion of the Engineer, it is not practical to remove and replace the Work, the Engineer will direct an appropriate remedy and/or adjust payment for the defective work.
1.8 MEASUREMENT AND PAYMENT - UNIT PRICES
A. Authority: Measurement methods are delineated in the individual specification sections.
B. Area and Volume Quantities: Contractor shall be responsible for pre- and post-activity surveys used as a basis for measurement. Surveys shall be performed as outlined in CS-7.
Engineer shall be notified at least 24 hours in advance of surveys for measurement.
Compute quantities based on surveyed measurements. Interim Payment Applications may be based on estimated quantities, with final quantities based on survey. The Engineer will review measurements and quantities.
C. Unit Quantities: Quantities and measurements indicated in the Payment Item Form are for
Contract purposes only. Quantities and measurements supplied or placed in the Work shall determine payment.
01019-3
D. Payment Includes: Full compensation for required labor, products, tools, equipment, plant and facilities, transportation, services and incidentals; erection, application or installation of an item of the Work; overhead and profit.
E. Materials Stored on Site: Measurement for payment requires the following:
1. Copies of delivery tickets shall be submitted to the Engineer at the time of delivery to the storage area in order to permit inventory of materials.
2. An invoice from the Supplier shall be furnished to the Engineer for each item or material for which payment is requested.
3. A Certificate of Insurance in the amount of 100% to replacement value of materials or items shall be submitted in conformance with the applicable provisions of the General Conditions covering stored materials and equipment.
Material shall be identified on the Insurance Certificate and the storage location shall be indicated.
F. Payment for Materials stored on site but not incorporated in the Work will be equal to the manufacturer's invoiced amount that is acceptable to the Engineer.
PART 1 PRODUCTS
PART 2 EXECUTION
SECTION 01025
MEASUREMENT AND PAYMENT
01025-1
1.1 SCOPE
A. The Bid Form lists each item of the Project for which payment will be made. No payment shall be made for any items other than those listed on the Bid Form.
B. Required items of work and incidentals necessary for the satisfactory completion of the work which are not specifically listed in the Bid Form, and which are not specified to be measured or to be included in one of the items listed in the Bid Form, shall be considered as incidental to the work. The Contractor shall prepare the Bid accordingly.
C. Work includes furnishing all labor, equipment, tools and materials, which are not furnished by the Owner and performing all operations required to complete the work satisfactorily, in place, as specified and as indicated within the Contract Documents.
D. Measurement and payment criteria are applicable to portions of the Work performed under a unit price payment method.
E. Measurement and payment criteria are applicable to portions of the Work performed under a lump sum payment method.
F. Measurement of quantities.
G. Payment of allowances.
H. Defect assessment and non-payment for rejected work.
1.2 AUTHORITY
A. Measurement and payment methods delineated in the individual specification sections complement the criteria of this section. In the event of conflict, the requirements of the individual specification section shall govern.
B. The Engineer will review measurements and quantities.
1.4 ADDITIONAL WORK AND EXCAVATION LIMITS
A. Approximate limits of excavation for most work are shown on the Drawings, or described in the applicable Specification Sections. Where approximate limits of excavation are not shown on the Drawings, or described in the applicable Specification Sections, the limits of excavation are assumed to be:
1. Excavations shall extend to the base of any structure, or bedding for piping, or to the base of subgrade as shown on the Drawings.
2. Excavation will extend horizontally beyond the footprint of the structure, or the projected footprint of piping, two feet. Excavation in soil will be sloped at 2H:1V unless otherwise noted on the Drawings. Excavation in sound rock may be sloped up to 0.25H:1V when the rock will sustain that slope in a stable condition. Excavation in partially weathered rock will be sloped at 1.5H:IV. Flatter slopes may be utilized by Contractor for safety or operational concerns. However, flatter excavation slopes will not be compensated.
01025-2
3. Excavation required for construction of embankment is to be in accordance with Parts
1.4.A.1,1.4.A.2. as well as the Excavation Plan in the Drawings. The Excavation Plan shown in the Drawings is to be considered a “guide” for the Contractor and represent the planned payable limits of excavation.
1.5 MEASUREMENT OF QUANTITIES
A. Measurement for excavation or removal of materials will be performed with materials in place before work starts. Measurement will be made from the top of the ground, layer, or existing surface to the top of the next layer, or approved excavation limit.
B. Measurement for backfilling, placement, or installation of materials will be performed after materials in place after work is completed. Measurement will be made from the limit of approved lines shown on the Drawings or authorized by the Engineer.
C. Measurement for area computations will be made in the horizontal projection of the actual surface area. No allowances in the measurement for area computations will be made for slopes, undulations, depressions, or any otherwise un-level surfaces.
D. Measurement of items that are measured by the linear foot will be made in the horizontal projection of the actual base or foundation. No allowances in the measurement for linear foot computations will be made for slopes or any otherwise un-level bases or foundations.
1.6 PAYMENT FOR UNIT PRICE ITEMS
A. Payment Includes: Full compensation for all required labor, products, tools, equipment, plant, transportation, services and incidentals; erection, application or installation of an item of the Work; overhead and profit.
B. Payment shall also fully compensate the Contractor for any other work, which is not specified or shown, but which is necessary to complete the Work that is specified or shown.
C. Individual specification sections may list materials, or work included for payment under the Unit Price Bid. Payment shall include, but not be limited to, materials or work listed.
D. Final payment for work governed by unit prices will be made on the basis of the actual measurements and quantities accepted by the Owner multiplied by the unit price for Work which is incorporated in or made necessary by the Work.
1.7 PAYMENT FOR LUMP SUM ITEMS
A. Payment includes: Full compensation for all required labor, products, tools, equipment, plant, transportation, services and incidentals; erection, application, installation, or testing of an item of the Work; overhead and profit.
B. Payment shall also fully compensate the Contractor for any other work, which is not specified or shown, but which is necessary to complete the Work that is specified or shown.
C. Individual specification sections may list materials, or work included for payment under the lump sum Bid. Payment shall include, but not be limited to, materials or work listed.
D. Contractor shall submit a schedule of values within 7 days after Notice to proceed.
1.8 DEFECT ASSESSMENT
01025-3
A. Replace the Work, or portions of the Work, not conforming to specified requirements at no additional cost to Owner.
B. If, in the opinion of the Engineer, it is not practical to remove and replace the Work, the
Engineer will require one of the following remedies:
1. The defective Work may remain, but the unit sum/price will be adjusted to a new sum/price at the discretion of the Engineer and authorized by the CLO/owner.
2. The defective Work will be partially repaired to the instructions of the Engineer, and the unit sum/price will be adjusted to a new sum/price at the discretion of the Engineer and authorized by the CLO/owner.
C. The individual specification sections may modify these options or may identify a specific formula or percentage sum/price reduction.
D. The authority of the Engineer or Owner to assess the defect and identify payment adjustment is final.
1.9 REGARDING-PAYMENT FOR REJECTED PRODUCTS
A. Payment will not be made for any of the following:
1. Products wasted or disposed of in a manner that is not acceptable.
2. Products determined as unacceptable before or after placement.
3. Products not completely unloaded from the transporting vehicle.
4. Products placed beyond the lines and levels of the required Work.
5. Products remaining on hand after completion of the Work.
6. Loading, hauling, and disposing of rejected, waste or excess products.
PART 4 MEASUREMENT AND PAYMENT
SECTION 01039
COORDINATION AND MEETINGS
01039-1
SECTION 01039
COORDINATION AND MEETINGS
A. Coordination and project conditions.
B. Field engineering.
C. Preconstruction meeting.
D. Site mobilization meeting.
E. Progress meetings.
F. Preparatory meetings.
1.3 COORDINATION AND PROJECT CONDITIONS
A. Coordinate scheduling, submittals, and Work of the various sections of the Project to ensure efficient and orderly sequence of construction of interdependent project elements, with provisions for accommodating items installed later.
B. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial
Completion.
C. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, if required by Owner and Engineer, to minimize disruption of Owner's activities.
1.4 FIELD ENGINEERING
A. Employ a Land Surveyor registered in the State of Texas and acceptable to Engineer.
B. Contractor shall locate and protect survey control and reference points.
C. Control datum for survey is that shown on Contract Drawings or will be provided prior to start of construction.
D. Verify set-backs and easements; confirm drawing dimensions and elevations; confirm utility locations.
E. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.
F. Submit a copy of site drawing and certificate signed by the Land Surveyor that the elevations and
01039-2 locations of the Work are in conformance with the Contract Documents.
1.5 PRECONSTRUCTION MEETING
A. Owner will schedule a meeting after Notice of Award.
B. Attendance Required: Owner, Engineer, Prime Contractor, Key Subcontractors (Conventional Concrete, Earthfill) if work not being performed by Prime Contractor.
C. Agenda:
1. Submission of executed bonds and insurance certificates.
2. Distribution of Contract Documents.
3. Submission of list of Subcontractors, schedule of values, and progress schedule.
4. Designation of personnel representing the parties in Contract, the Land Surveyor, and the
Engineer.
5. Procedures and processing of field decisions, submittals, substitutions, applications for payment, proposal requests, Change Orders, and Contract closeout procedures.
6. Scheduling.
D. Engineer will record minutes and distribute copies to participants within ten working days after meeting.
1.6 SITE MOBILIZATION MEETING
A. Engineer or Owner will schedule a meeting at the Project site prior to Contractor occupancy.
B. Attendance Required: Owner, Engineer, Prime Contractor, Key Subcontractors (Conventional Concrete, Earthfill) Contractor's Superintendent.
C. Agenda:
1. Use of premises by Owner and Contractor.
2. Owner's requirements.
3. Protection of utilities.
4. Survey and project layout.
5. Security and housekeeping procedures.
6. Schedules.
7. Application for payment procedures.
8. Procedures for testing.
9. Procedures for maintaining record documents.
D. Engineer will record minutes and distribute copies to participants within ten working days after meeting.
1.7 PROGRESS MEETINGS
A. Submit agenda items and attend meetings throughout progress of the Work not exceeding one per month.
B. Engineer will make arrangements for meetings, prepare agenda with copies for participants and will preside at meetings.
C. Attendance Required: Job superintendent, key Subcontractors and Suppliers, Owner and
01039-3
Engineer, as appropriate to agenda topics for each meeting.
D. Agenda:
1. Review minutes of previous meetings.
2. Review of Work progress.
3. Field observations, problems, and decisions.
4. Identification of problems which impede planned progress.
5. Review of submittals' schedule and status of submittals.
6. Review of off-site fabrication and delivery schedules.
7. Review of erosion and sedimentation controls.
8. Maintenance of progress schedule.
9. Corrective measures to regain projected schedules.
10. Planned progress during succeeding work period.
11. Coordination of projected progress.
12. Maintenance of quality and work standards.
13. Effect of proposed changes on progress schedule and coordination.
14. Other business relating to Work.
E. Engineer will record minutes and distribute copies within ten working days after meeting to participants.
1.8 PREPARATORY MEETINGS
A. Where identified as a definable feature of work or requested by the Engineer, Contractor shall convene preparatory meetings at Project site prior to commencing work of a specific section.
B. At a minimum, definable features of work shall include:
1) Foundation excavation and preparation.
2) Conventional Concrete Placement
3) Earthfill Placement
C. Require attendance of parties directly affecting, or affected by, Work of specific section. As a minimum this shall include the site superintendent, foreman for the work, and any Subcontractor representative. Prior to each, meeting the Contractor and Engineer will agree on who needs to be present.
D. Contractor shall coordinate scheduling of the meeting with the Engineer.
E. Contractor shall prepare agenda and preside at meeting unless the meeting was scheduled at the request of the Engineer.
F. Contractor shall record minutes and distribute copies to participants within ten working days after meeting, with one copy distributed to the Owner.
01039-4
SECTION 01061
PROJECT PERMITS
01061-1
SECTION 01061
PROJECT PERMITS
1.1 SCOPE
A. Comply with all permits issued for this project.
1.2 SUBMITTALS
A. Submittals shall be in accordance with this section and Section 01300: Submittals.
3.1 PROJECT PERMITS
A. The Owner has obtained or has been approved for applicable permits.
B. Copies of all permits obtained by the Contractor shall be displayed on site in Contractor’s and
Engineer’s office.
3.2 PROJECT PERMIT COMPLIANCE
A. The Contractor shall be fully responsible for compliance with all terms of all project permits in the execution of his work.
B. By submission of his Bid, the Contractor acknowledges that he will comply with the terms of the permits in the execution of his work.
4.1 MEASUREMENT
A. All work required in this section will not be measured for payment.
4.2 PAYMENT
A. Compensation to the Contractor for all work required in this section shall be included in the prices bid in the Bid Form for other items of work. No separate payment to the Contractor will be made for any of the work required in this section.
SECTION 01300
SUBMITTAL PROCEDURES
01300-1
SECTION 01300
A. Submittal procedures.
B. Construction Progress Schedules.
C. Proposed Products list.
D. Submittals of Product Data, Shop Drawings, Samples, Test Reports, Certificates.
E. Manufacturer's instructions.
F. Manufacturer's field reports.
G. Erection drawings.
H. Construction photographs.
A. Section 01700, Contract Closeout: Contract warranties, bonds, manufacturers' certificates, and closeout submittals.
1.3 SUBMITTAL PROCEDURES
A. Transmit each submittal by due date referenced in the individual Specification sections.
B. Sequentially number the transmittal form. Mark revised submittals with original number and a sequential alphabetic suffix.
C. Identify Project, Contractor, Subcontractor or Supplier; pertinent drawing and detail number, and specification section number, as appropriate.
D. Apply Contractor's stamp, signed or initialed, certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents.
E. Schedule Submittals to expedite the Project, and deliver to Engineer via electronic mail (email).
Coordinate submission of related items.
F. For each submittal review, submittal shall be delivered to the Engineer at least 21 days prior to the work listed in the Submittal being initiated unless specifically stated otherwise in the Contractor’s Documents.
G. Identify variations from Contract Documents and Product or system limitations.
H. Provide space for Contractor and Engineer review stamps.
01300-2
I. When revised for resubmission, identify all changes made since previous submission.
J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.
K. Submittals not requested will not be recognized or processed.
1.4 CONSTRUCTION PROGRESS SCHEDULES
A. Submit initial schedule within 10 days after date of Owner-Contractor Agreement.
B. Revise and resubmit as required.
C. Submit revised schedules with each Application for Payment, identifying changes since previous version.
D. Submit a horizontal bar chart with separate line for each major portion of Work or operation, identifying first work day of each week.
E. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.
F. Indicate estimated percentage of completion for each item of Work at each submission.
G. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates.
H. Submit a look ahead schedule of planned work monthly.
1.5 SUBMITTALS OF PRODUCT DATA, SHOP DRAWINGS, OR SAMPLES
A. Submittals For Review:
1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01700 - Contract Closeout.
B. Submittals For Information:
1. Submitted for the Engineer's knowledge for the Owner.
C. Submittals For Project Close-out:
1. Submitted for the Owner's benefit during and after project completion.
D. Submittal Quantities:
1. Product Data: Submit the number of copies which the Contractor requires, plus 1 electronic copy which will be retained by the Engineer and distributed to the Owner.
2. Shop Drawings: Submit the number of copies which the Contractor requires, plus 1
01300-3 electronic copy which will be retained by the Engineer.
3. Samples: Submit quantity as identified in the individual specification sections, or one sample (to be retained by the Engineer) if no quantity is specified.
E. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.
F. After review, distribute in accordance with the Submittal Procedures article above and provide copies for record documents described in Section 01700 - Contract Closeout.
1.6 TEST REPORTS
A. Submit for the Engineer's knowledge or for the Owner, in quantities specified for Product Data.
B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
1.7 CERTIFICATES AND WARRANTIES
A. When specified in individual specification sections, submit certification and warranty information by the manufacturer, installation/application Subcontractor, or the Contractor to Engineer, in quantities specified for Product Data.
B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.
1.8 MANUFACTURER'S INSTRUCTIONS
A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, adjusting, and finishing, to Engineer for delivery to owner in quantities specified for Product Data.
B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
1.9 MANUFACTURER’S FIELD REPORTS
A. Submit reports for Engineer’s benefit.
B. Submit report in duplicate within 48 hours of observation to Engineer for information.
C. Submit for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.
1.10 CONSTRUCTION PHOTOGRAPHS
A. Submit a minimum of 20 dated photographs and a minimum of 8 drone aerial photographs on a thumb drive or other secure data transfer methods with each progress payment application.
01300-4
SECTION 01500
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
01500-1
SECTION 01500
A. Temporary Utilities: Electricity, lighting, heat, ventilation, telephone service, water, and sanitary facilities.
B. Temporary Controls: Barriers, enclosures and fencing, traffic controls, erosion and sediment controls, and protection of the Work.
C. Construction Facilities: Access roads, parking, cleaning, project signage, trash collection and temporary buildings.
A. Section 01700, Contract Closeout: Final cleaning
1.3 TEMPORARY ELECTRICITY
A. Cost: By Contractor; arrange, provide and pay for power service required from utility source.
B. Complement existing power service capacity and characteristics as required.
C. Provide power outlets for construction operations, with branch wiring and distribution boxes located as required. Provide flexible power cords as required.
D. Provide main service disconnect and over-current protection at convenient location.
E. Provide adequate distribution equipment, wiring, and outlets to provide single phase branch circuits for power and lighting.
1.4 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES
A. Provide and maintain lighting for construction operations to achieve a minimum lighting level of 2 watt/sq ft.
B. Provide and maintain 1 watt/sq ft lighting to exterior staging and storage areas after dark for security purposes.
C. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps as required.
D. Maintain lighting and provide routine repairs.
1.5 TELEPHONE, FAX AND INTERNET SERVICE
A. Provide, maintain, and pay for telephone, fax, and high-speed internet service and wireless network with a minimum upload speed as designated in CS-96 - Field Office to field office and
01500-2
Engineer's field office at time of project mobilization. Engineer’s office shall have dedicated internet service separate from the Contractor’s field office to limit interference.
1.6 TEMPORARY WATER SERVICE
A. Provide, maintain and pay for suitable quality water service required for construction operations at time of project mobilization.
1.7 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.
B. At end of construction, return facilities to same or better condition as originally found.
1.8 WEATHER SERIVICE
A. Provide and maintain a rain gauge capable of reading from 0.1 inches to at least 6 inches.
B. Provide and maintain a thermometer suitable for outdoor use. Thermometer shall be capable of recording daily high and low temperatures.
1.9 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations.
B. Provide protection for plants and trees designated to remain. Replace damaged plants and trees.
C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.
1.10 FENCING
A. Construction: Contractor's option.
1.11 PROTECTION OF INSTALLED WORK
A. Protect installed Work and provide special protection where specified in individual specification sections.
B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to prevent damage.
1.12 SECURITY
A. Provide security and facilities to protect Work from unauthorized entry, vandalism, or theft.
1.13 ACCESS ROADS
A. Construct and maintain temporary roads accessing public thoroughfares to serve construction
01500-3 area.
B. Extend and relocate as Work progress requires. Provide detours necessary for unimpeded traffic flow.
C. Existing on-site roads within construction limits (defined by temporary barriers on Drawings) may be used for construction traffic.
D. Provide all necessary traffic control devices required by TXDOT and the County.
1.14 PARKING
A. Provide temporary gravel surface parking areas to accommodate construction personnel.
B. When site space is not adequate, provide additional off-site parking in close vicinity to the project site.
C. Do not allow vehicle parking on existing pavement outside of construction limits.
D. Designate parking spaces for the Owner and Engineer as outlined in CS-96-Field Office.
1.15 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.
1.16 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary utilities, equipment, facilities, materials, prior to Substantial Completion inspection.
B. Clean and repair damage caused by installation or use of temporary work.
C. If an off-site location is used for concrete production, any damage to surface roadways shall be repaired by the Contractor. Prior to start of construction, Contractor shall conduct a video review of the current roadway conditions. Video shall be provided to Owner and Engineer prior to start of construction.
1.17 UTILITY VEHICLE
A. Provide, maintain and pay for 4x4 utility vehicle, with dump bed, capable of safely transporting 4 persons on the construction site
B. Pay for fuel for utility vehicle
C. Pay for all insurance, maintenance, repairs, and other operating expenses for utility vehicle.
01500-4
4.1 MEASUREMENT
A. All work and associated costs in this section will not be measured for payment.
4.2 PAYMENT
Not Used
SECTION 01600
MATERIAL AND EQUIPMENT
01600-1
SECTION 01600
MATERIAL AND EQUIPMENT
A. Transportation and handling.
B. Storage and protection.
C. Product options.
D. Substitutions.
A. Instructions to Bidders: Product options and substitution procedures.
B. Section 01400, Quality Control: Product quality monitoring.
1.3 TRANSPORTATION AND HANDLING
A. Transport and handle Products in accordance with manufacturer’s and Supplier’s instructions.
B. Promptly inspect shipments to ensure that Products comply with requirements, quantities are correct, and Products are undamaged.
C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.
1.4 STORAGE AND PROTECTION
A. Store and protect Products in accordance with manufacturers' instructions.
B. Store with seals and labels intact and legible.
C. Store sensitive Products in weather tight, climate controlled, enclosures in an environment favorable to Product.
D. For exterior storage of fabricated Products, place on sloped supports above ground.
E. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.
F. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of Products.
G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.
01600-2
H. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.
I. Arrange storage of Products to permit access for inspection. Periodically inspect to verify
Products are undamaged and are maintained in acceptable condition.
1.5 PRODUCT OPTIONS
A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.
B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.
C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:
Submit a request for substitution for any manufacturer not named in accordance with the following article.
1.6 SUBSTITUTIONS
A. Engineer will consider requests for Substitutions only within 30 days after date established in Notice to Proceed.
B. Substitutions may be considered when a Product becomes unavailable through no fault of the
Contractor.
C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.
D. A request constitutes a representation that the Contractor:
1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.
2. Will provide the same warranty for the Substitution as for the specified Product.
3. Will coordinate installation and make changes to other Work which may be required for the
Work to be complete with no additional cost to Owner.
4. Waives claims for additional costs or time extension which may subsequently become apparent.
5. Will reimburse TSSWCB for review or redesign services associated with re-approval by authorities with approval of contracting officer.
E. Substitutions will not be considered when they are indicated or implied on shop drawing or product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.
F. Substitution Submittal Procedure:
1. Submit request for Substitution for consideration. Limit each request to one proposed
Substitution.
2. Submit shop drawings, product data, and certified test results attesting to the proposed
Product equivalence. Burden of proof is on proposer.
3. Engineer will notify Contractor in writing of decision to accept or reject request.
01600-3
SECTION 01700
CONTRACT CLOSEOUT
01700-1
SECTION 01700
A. Closeout procedures.
B. Final cleaning.
C. Adjusting.
D. Project record documents.
E. Operation and maintenance data.
F. Spare parts and maintenance Products.
G. Warranties and bonds.
H. Maintenance service.
A. Section 01500, Construction Facilities and Temporary Controls: Progress cleaning
1.3 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.
B. Provide submittals to Engineer that are required by governing or other authorities.
C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.
D. Provide Record Drawings.
E. Provide As-Built Survey prepared by approved Surveyor upon completion of the project.
1.4 FINAL CLEANING
A. Execute final cleaning prior to final project assessment.
B. Clean site; sweep paved areas, rake clean landscaped surfaces.
C. Remove waste and surplus materials, rubbish, and construction facilities and properly dispose of in designated areas.
01700-2
1.5 ADJUSTING
1.6 PROJECT RECORD DOCUMENTS
A. Maintain on site one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Submittals.
5. Change Orders and other modifications to the Contract.
6. Reviewed Shop Drawings, Product Data, and Samples.
7. Manufacturer's instructions for assembly, installation, and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress.
E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:
1. Manufacturer's name and product.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and modifications.
F. Record Drawings: Legibly mark each item to record actual construction including, but not limited to the items listed in CS-007 Construction Surveys Section 09.
G. As-Built Survey: Upon final completion of project, Contractor shall submit a survey of the completed works within the limits shown on the Contract Drawings. The survey shall be prepared and sealed by a Surveyor licensed in the State of Texas. The survey shall include all proposed structures and features as depicted on the Contract Drawings. The as-built survey shall include sufficient spot elevations to verify compliance with design intent. The as-built survey shall include topographic contours with a maximum 1-foot interval.
H. Submit documents to Engineer with request for final Application for Payment.
1.7 OPERATION AND MAINTENANCE DATA
A. Submit data bound in 8-1/2 x 11 inch text pages, three D side ring binders with durable plastic covers.
B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.
01700-3
C. Internally subdivide the binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.
D. Contents: Prepare a Table of Contents for each volume, with each Product or system description identified, in three parts as follows:
1. Part 1: Directory, listing names, addresses, and telephone numbers of Engineer, Contractor, Subcontractors, and major equipment Suppliers.
2. Part 2: Operation and maintenance instructions. For each category, identify names, addresses, and telephone numbers of Subcontractors and Suppliers. Identify the following:
a. Significant design criteria.
b. List of equipment.
c. Parts list for each component.
d. Operating instructions.
e. Maintenance instructions for equipment and systems.
3. Part 3: Project documents and certificates, including the following:
a. Shop Drawings and product data.
b. Certificates.
c. Originals of warranties and bonds.
E. Submit one draft copy of completed volume 15 days prior to final inspection. This copy will be reviewed and returned after final inspection with Engineer comments. Revise content of all document sets as required prior to final submission.
F. Submit two sets of revised final volumes, within 10 days after receipt of Engineer review comments.
1.8 SPARE PARTS AND MAINTENANCE PRODUCTS
1.9 WARRANTIES AND BONDS
A. Provide notarized copies.
B. Execute and assemble transferable warranty documents from Subcontractors, Suppliers, and manufacturers.
C. Provide Table of Contents and assemble in three D side ring binder with durable plastic cover.
D. Submit prior to final Application for Payment.
E. For items of Work delayed beyond date of Substantial Completion, provide updated submittal within 10 days after acceptance, listing date of acceptance as start of warranty period.
1.10 MAINTENANCE SERVICE
A. Mow all grassed areas within 10 days of Contract closeout.
01700-4
B. Operate gate(s) in the presence of Owner and Engineer.
210 H 642 CS 2 (June 2024) CS 2-1
Construction Specification 2 — Clearing and Grubbing Title 210 – Engineering Part 642 – Specifications for Construction Contracts Subpart B – National Construction Specifications June 2024
A. Scope
1. The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.
B. Protection of Existing Vegetation
1. Protect trees and other vegetation designated to remain undisturbed from damage throughout the duration of the construction period. Any damages resulting from the contractor’s operations or neglect must be repaired by the contractor.
2. Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic must not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions must be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
3. Any cuts, skins, scrapes, or bruises to the bark of the vegetation must be carefully trimmed, and local nursery-accepted procedures must be used to seal damaged bark.
4. Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction must be cut off at the base of the damaged limb or branch, flush with the adjacent limb or tree trunk. All roots 1 inch or larger in diameter that are cut, broken, or otherwise severed during construction operations must have the ends smoothly cut perpendicular to the root. Roots exposed during excavation or other operations must be covered with moist earth or backfilled as soon as possible to prevent the roots from drying out.
C. Marking
1. The limits of the areas to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunk about 6 feet above the ground surface.
D. Clearing and Grubbing
1. Clear all trees not marked for preservation and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger must be grubbed out to a depth of at least 2 feet below
210 H 642 CS 2 (June 2024) CS 2-2 the subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.
E. Disposal
1. Dispose of all materials cleared and grubbed from the designated areas at locations shown on the drawings or in a manner specified in Section G.
This is the start of the file's text. The full file is on GovTribe.