This document is a Statement of Work (SOW) for the "598-22-151 B170 FG Chilled Water Piping Replacement" project at the Eugene J. Towbin Memorial Veterans Hospital in North Little Rock, Arkansas.
The project's objective is to replace the fiberglass piping in Building 170 for the chilled water system. The work includes providing all labor, equipment, transportation, materials, quality control, and supervision necessary to conduct the construction in accordance with the project specifications and drawings. The magnitude of construction is between $5,000,000 and $10,000,000, and the project is set aside for 100% Service-Disabled Veteran-Owned Small Businesses (SDVOSB). The North American Industry Classification System (NAICS) code is 238220.
The project timeline includes a pre-proposal site visit, proposal submission, selection, award, post-award kickoff, notice to proceed, and other standard construction activities. The performance period is 365 calendar days after the notice to proceed is issued. Key deliverables include performance and payment bonds, proof of insurance, safety training for personnel, operations and maintenance manuals, record drawings, and a one-year warranty.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| rev 08.29.2024_36C25624R0117.pdf | ||
| 36C25624R0117.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Project No. 598-22-151 B170 FG Chilled Water Piping Replacement Eugene J. Towbin Memorial Veterans Hospital
1. PROJECT OVERVIEW
1.1. The Central Arkansas Veterans Healthcare System (CAVHS) intend to select a contractor to provide professional construction services for the “598-22-151 B170 FG Chilled Water Piping Replacement” at their VAMC facilities in North Little Rock, Arkansas.
1.2. This project is for the replacement the fiberglass piping in B170 Medical Center for the chilled water system.
1.3. Work consists of the contractor providing all labor, equipment, transportation, materials, quality control and supervision necessary to conduct construction in accordance with the project specifications and drawings.
1.4. The magnitude of construction per VAAR Part 836.204 is between $5,000,000.00 and $10,000,000.00. This is a 100% SDVOSB set-aside.
1.5. North American Industrial Classification Standard (NAICS) code assigned to this construction project is 238220.
2. PROJECT ACTIVITIES
2.1. The entire activity of the project will follow the following sequence of events:
a. Pre-proposal Site Visit
b. Request for Proposal Submission
c. Selection
d. Award
e. Post Award Kick-off Meeting
f. Notice to Proceed
g. Bonding & Insurance
h. Submittals
i. Daily Reports
j. Weekly Progress Reports and Weekly Project Schedule
k. Permits (asbestos abetment)
l. Demolition, Construction, Installation and Commissioning
m. Final Inspection
n. Acceptance
o. Operations and Maintenance Manuals
p. AutoCAD Drawings (Design, Construction, As Built)
q. Payment
r. Warranty
3. SCOPE OF WORK
3.1. The Contractor shall provide all necessary services to meet the project objectives and requirements and to provide the required outcome in terms of overall quality, timeliness and documentation. The Contractor shall be responsible for obtaining and coordinating the services of any and all third-party Contractors performing other services on site and other entities as part of the contract to ensure the expected quality, timely, and documented final product.
3.2. Location: Eugene J. Towbin Memorial Veterans Hospital, 2200 Fort Roots Drive, North Little Rock, Arkansas 72114.
3.3. Normal work hours for VA sites are 7:00AM to 4:30PM Monday through Friday except for Federal Holidays. If the Contractor desires to work on Saturday, Sunday, holidays, or outside the project site’s normal working hours the contractor must submit a written request for approval to the Contracting Officer Representative (COR) at least seven (7) working days prior to the proposed start.
3.4. The following legal holidays are observed by this Government Agency:
| New Year’s Day | January 1st | |||
| Martin Luther King's Birthday | Third Monday in January | |||
| Presidents Day | Third Monday in February | |||
| Memorial Day | Last Monday in May | |||
| Juneteenth | Jun 19th | |||
| Independence Day | July 4th | |||
| Labor Day | First Monday in September | |||
| Columbus Day | Second Monday in October | |||
| Veterans Day | November 11th | |||
| Thanksgiving Day | 4th Thursday in November | |||
| Christmas Day | December 25th |
4. DESCRIPTION OF WORK
4.1. The plan is for the replacement the fiberglass piping for the chilled water system at the VA’s Eugene Towbin Facility.
5. DELIVERIES
5.1. The Performance Period for this project is three hundred sixty-five (365) calendar days after receiving the Notice to Proceed.
5.2. The Notice to Proceed will be issued within 30 days after award of the solicitation.
5.3. Performance and Payment bonds: Due prior to Post Award Kick-off meeting.
5.4. Proof of Insurance: Due on Post Award Kick-off meeting.
5.5. All personnel assigned on the project and works on the construction site must complete a one-hour CAVHS Safety training.
6. ACCEPTANCE
6.1. For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” will be provided by the VA upon the completion of all of the following:
6.1.1. The Contractor has demonstrated/verified that the implemented ECMs function as intended at commissioning. All punch list items identified during the commissioning have been resolved.
6.1.2. The Contractor has provided O&M manuals.
6.1.3. The Contractor has provided Record drawings to include a CD with all as builds CAD files and PDF, and one full set on bond paper.
7. CONFIDENTIALITY AND NONDISCLOSURE
7.1. The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by the VA which has been generated by the contractor in the performance of this Order are the exclusive property of the U.S. Government and shall be submitted to the VA-COR at the conclusion of the contract.
7.2. The Contracting Officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.
8. SECURITY.
8.1. All employees of general contractor and subcontractors shall comply with the VA security management program, be identified by through project and employer badges, and restricted from areas of unauthorized access.
8.2. Each Contractor shall be vetted by VA Security and each worker will have their ID issued by VA. Issued ID must be worn at all times.
8.3. General Contractor’s employees shall not enter the project site without appropriate badging/identification. They may also be subject to inspection of their personal effects when entering or leaving the project site.
8.4. No photography of VA premises is allowed without written permission of the Contracting Officer. The Contractor and workforce personnel shall not post or discuss government facility activities on unauthorized public media.
8.5. General Contractor’s employees are subject to rules of CAVHS Medical Center applicable to their conduct. However, the contractor personnel shall not be considered government employees for any purpose under this contract.
8.6. Execute work to interfere as little as possible with normal functioning of CAVHS Medical Center, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required.
8.7. General Contractor (GC) in compliance with FAR 29.303 GC is not normally designated as agents of the Government for the purpose of claiming immunity from State or Local sales or use taxes, that rests with the particular state or local law. Therefore, tax exemption is not available for this project and your pricing should address this matter accordingly.
9.0 CODE REQUIREMENTS.
9.1. The VA will be responsible for obtaining necessary local agency approvals as required.
9.2. All work performed under this contract shall be in accordance with attached specifications and the VA Master Specifications (http://www.cfm.va.gov/til/spec.asp) . Use sections that apply to the scope of work.
9.3. All work shall comply with all local, state, and federal rules and regulations. In the event of a code discrepancy the stricter of the ordinances shall prevail.
10. WARRANTIES.
10.1. One year warranty will begin from the date of project completion or VA beneficial occupancy.
11. PARKING.
11.1. Parking is rigidly controlled throughout the Medical Center. Contractor parking is only allowed in authorized areas. Contractor shall abide by all police requirements. Parking in designated patient parking areas is strictly prohibited. Parking for unloading equipment necessary to perform the work will be authorized in advance of starting the project.