This document is an extensive Air Balance Summary Sheet detailing comprehensive ventilation system testing across multiple buildings and floors at the Bruce W. Carter Veterans Affairs Medical Center. The testing, performed in April 2023, systematically evaluated air pressure, air changes, supply, return, and exhaust rates in various clinical and research spaces including operating rooms, patient rooms, laboratories, clinics, and specialized research areas.

The detailed testing revealed numerous rooms failing air balance requirements, with issues including taped-off exhaust grilles, offline fume hoods, improper air pressure differentials, and inconsistent air exchange rates. The summary covers buildings including main medical center facilities, animal research spaces, and multiple clinical sites such as Broward, Pembroke, Hollywood, and Deerfield Clinics. The testing was likely conducted in preparation for the VA Healthcare System's 5-Year Testing and Balancing of Ventilation System solicitation (36C24825Q0173), which seeks to ensure proper ventilation and air quality across their medical facilities. Specific areas of concern included research laboratories, operating rooms, patient rooms, and specialized clinical spaces where precise air handling is critical for patient and research safety.

View the file

Other files

File Type Posted
SCHEDULE SITE VISIT.docx DOCX document
36C24825Q0173 0002_1.docx DOCX document
Combined Synopsis 2025.docx DOCX document
36C24825Q0173_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1st FL & Other Areas

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/21/23

1ST FLOOR & OTHER AREAS
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS or FAIL
Room Volume Cu. Ft.NEG. POS. EQUAL NRCODE Req'dDesignActualDesignActualDesignActualDesignActualDesignActual
Room #Room DescriptionArea Sq. Ft.Ceiling Height
B1214STORAGE ENT (P/TMP/RH)1827.51,3650.0024.0N/A6.819300.00N/A155N/A0N/A0N/A155PASS*Exhaust grille taped off
B1208STORAGE DERM (P/TMP/RH)598.04680.0024.0N/A38.4618000.00N/A300N/A0N/A0N/A300PASS*Exhaust grille taped off
C8038C803 Podiatry (P/TMP/RH)1099.09810.0014.0N/A3.363300.00N/A55N/A0N/A18N/A37FAIL
1E128AUDIOLOGY CONTROL RM557.34020.0016.0N/A15.846360.00N/A106N/A0N/A0N/A106PASS
1E128AUDIOLOGY BOOTH496.6321-0.0016.0N/A2.800.00N/A0N/A0N/A15N/A-15FAIL*No airflow
1E017TRIAGE ROOM1698.31,3940.0036.0N/A10.5410620.00N/A177N/A245N/A0N/A-68PASS
1B147SUPPLY ROOM909.08100.0114.0N/A8.306720.00N/A112N/A0N/A0N/A112PASS
1A-106 A-LPHARMACY--15,7130.01510.0N/A13.09205620.00N/A3,427N/A0N/A871N/A2,556PASS
CLC204RESEARCH6208.55,2700.0026.0N/A11.1358680.00N/A978N/A0N/A397N/A581PASS
CLC205RESEARCH1528.51,2920.0066.0N/A13.7917820.00N/A297N/A0N/A0N/A297PASS*No return / exhaust grilles
CLC305DENTAL OPERATORY1798.01,4320.0016.0N/A5.077260.00N/A121N/A0N/A108N/A13FAIL
D912VISION2428.01,9320.0026.0N/A3.606960.00N/A116N/A21N/A0N/A95FAIL
D912AOFFICE1138.0900-0.0016.0N/A2.601920.00N/A32N/A39N/A0N/A-7FAIL
13

Total Rooms = 13

Grand Total of Rooms Tested = 287 Will include 15 rooms testing, if needed. For Total of 302 Rooms.

Highly Critical Rooms =71
Lower Critical Rooms = 216

2nd FL AUDIOLOGY

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/21/23

AUDIOLOGY LEVEL 2
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume Cu. Ft. NEG. POS. EQUAL NR CODE Req'd Design Actual Design Actual Design Actual Design Actual Design Actual

Room # Room Description Area Sq. Ft. Ceiling Height

2A151RECEPTION2818.02,2440.0034.0N/A3.267320.00N/A122N/A0N/A0N/A122FAIL*Exhaust grille taped off
2A151AAUDIOLOGY1249.51,1760.0026.0N/A5.726720.00N/A112N/A0N/A0N/A112FAIL
2A151BAUDIOLOGY / SPEECH1988.01,5840.0006.0N/A1.211920.00N/A32N/A52N/A0N/A-20FAIL
2A151CAUDIOLOGY / SPEECH1219.01,0890.0016.0N/A2.262460.00N/A41N/A18N/A0N/A23FAIL
2A151DAUDIOLOGY / SPEECH1109.09900.0016.0N/A3.763720.00N/A62N/A22N/A0N/A40FAIL
2A151EAUDIOLOGY / SPEECH1108.08800.0026.0N/A2.862520.00N/A42N/A21N/A0N/A21FAIL
2A151FAUDIOLOGY / SPEECH1018.08100.0026.0N/A3.332700.00N/A45N/A15N/A0N/A30FAIL
2A151GAUDIOLOGY / SPEECH988.07800.0016.0N/A2.541980.00N/A33N/A13N/A0N/A20FAIL
2A151HAUDIOLOGY / SPEECH1538.01,2240.0056.0N/A4.125040.00N/A84N/A24N/A0N/A60FAIL
2A151 G1BOOTH 1 CONTROL RM807.35800.0006.0N/A1.861080.00N/A18N/A0N/A0N/A18FAIL
2A151 G2BOOTH 1776.55010.0006.0N/A0.72360.00N/A6N/A0N/A0N/A6FAIL
2A151 G4BOOTH 2 CONTROL RM807.35800.0006.0N/A1.761020.00N/A17N/A0N/A0N/A17FAIL
2A151 G3BOOTH 2786.55070.0006.0N/A0.47240.00N/A4N/A0N/A0N/A4FAIL
2A151 G6BOOTH 3 CONTROL RM446.52860.0006.0N/A0.84240.00N/A4N/A0N/A0N/A4FAIL
2A151 G5BOOTH 3546.53480.0006.0N/A2.59900.00N/A15N/A0N/A0N/A15FAIL
2A157CSUPPLY ROOM2027.81,5660.0024.0N/A3.645700.00N/A95N/A0N/A0N/A95FAIL
16

Total Rooms = 16

2ND FL DENTAL

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/19/23

DENTAL LEVEL 2
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS or FAIL
Room Volume
Cu. Ft.NEG.

POS.

EQUAL

NR CODE Req'd Design Actual Design Actual Design Actual Design Actual Design Actual

Room # Room Description Area Sq. Ft. Ceiling Height

2A150 C3DENTAL OPERATORY1448.81,2600.0066.0N/A5.006300.00N/A105N/A0N/A0N/A105FAIL
2A150 C6DENTAL OPERATORY1267.89770.0006.0N/A1.471440.00N/A24N/A0N/A17N/A7FAIL
2A150 C9DENTAL OPERATORY1268.01,0080.0016.0N/A2.262280.00N/A38N/A0N/A14N/A24FAIL
2A150 C10DENTAL OPERATORY1268.01,0080.0016.0N/A1.961980.00N/A33N/A0N/A17N/A16FAIL
2A150 C12STAFF PERIODONTIST1388.81,2080.0146.0N/A11.2813620.00N/A227N/A0N/A71N/A156PASS
2A150 C2DENTAL OPERATORY1259.01,1250.0016.0N/A2.132400.00N/A40N/A0N/A20N/A20FAIL
2A150 C5DENTAL OPERATORY1267.59450.0016.0N/A1.841740.00N/A29N/A0N/A16N/A13FAIL
2A150 14DENTAL OPERATORY988.07840.0556.0N/A10.648340.00N/A139N/A0N/A0N/A139PASS
2A150 12DENTAL OPERATORY968.07680.0086.0N/A6.334860.00N/A81N/A0N/A18N/A63PASS
2A150 10DENTAL OPERATORY968.07680.0026.0N/A13.2010140.00N/A169N/A0N/A155N/A14PASS
2A150 B4DENTAL OPERATORY1108.08800.0126.0N/A12.2010740.00N/A179N/A0N/A20N/A159PASS
2A152MEDICAL SURGICAL SUPPLY RM2508.02,0000.0054.0N/A2.224440.00N/A74N/A0N/A15N/A59FAIL
2A153DENTAL HYGIENIST1318.01,0480.0036.0N/A7.167500.00N/A125N/A0N/A0N/A125PASS
2A150C11DENTAL OPERATORY1278.01,0160.0016.0N/A1.181200.00N/A20N/A0N/A29N/A-9FAIL
2A150 11DENTAL OPERATORY968.07680.0086.0N/A7.505760.00N/A96N/A0N/A21N/A75PASS
2A150 13DENTAL OPERATORY968.07680.0116.0N/A9.777500.00N/A125N/A0N/A18N/A107PASS
2A150 B2DENTAL OPERATORY1168.09280.0296.0N/A10.159420.00N/A157N/A0N/A15N/A142PASS
2A150 B8EQUIPMENT ROOM689.0612-0.0016.0N/A2.751680.00N/A28N/A0N/A39N/A-11FAIL*Exhaust grille taped off
2A150 B9ORAL SURGERY2108.01,6800.01915.0N/A9.1115300.00N/A255N/A0N/A35N/A220FAIL
19

Total Rooms = 19

2ND FL RESEARCH

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/18/23

RESEARCH BRAVO SIDE LEVEL 2
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS or FAIL
Room Volume
Cu. Ft.NEG.

POS.

NR CODE Req'd Design Actual Design Actual Design Actual Design Actual Design Actual

Room # Room Description Area Sq. Ft. Ceiling Height

2B112COPIER ROOM807.8620-0.0016.0N/A0.000.00N/A51N/A83N/A0N/A-32FAIL
2B11OFFICE858.8744-0.0026.0N/A6.134560.00N/A0N/A0N/A76N/A-76PASS
2B110MANAGEMENT1388.31,1390.0036.0N/A8.8510080.00N/A168N/A67N/A0N/A101PASS
2B109PHSYSIOLOGY LAB2129.01,9080.0406.0N/A10.3519740.00N/A329N/A0N/A0N/A329PASS
2B106NEUROCHEMISTRY2039.01,8270.0006.0N/A16.5830300.00N/A505N/A0N/A375N/A130PASS
2B104RESEARCH OFFICE2148.51,8190.0246.0N/A10.3918900.00N/A315N/A0N/A54N/A261PASS
2B105RESEARCH DATA917.5683-0.0116.0N/A0.000.00N/A0N/A78N/A0N/A-78FAIL
2B103MOLECULAR BIO LAB3518.32,8960.0306.0N/A8.4124360.00N/A406N/A0N/A25N/A381PASS
2B102RESEARCH FILE25711.02,827-0.0236.0N/A5.6916080.00N/A85N/A0N/A268N/A-183FAIL
2B115IRB CHAIR1058.0840-0.0046.0N/A9.147680.00N/A81N/A0N/A128N/A-47PASS
2B130SPINAL CORD PHARM LAB3328.82,9050.0076.0N/A17.1049680.00N/A828N/A0N/A285N/A543PASS
2B132LAB2448.01,952-0.0096.0N/A17.0633300.00N/A371N/A0N/A555N/A-184PASS
2B133OFFICE3339.02,9970.0036.0N/A11.9935940.00N/A599N/A145N/A0N/A454PASS
2B133ARESEARCH LAB1169.01,0440.0016.0N/A6.957260.00N/A121N/A0N/A55N/A66PASS
2B133BOFFICE1078.89360.0056.0N/A22.4921060.00N/A351N/A0N/A0N/A351PASS
2B131LAB868.87530.0006.0N/A25.5919260.00N/A321N/A105N/A100N/A116PASS
2B129SPINAL CORD PHARM LAB4508.53,8250.0306.0N/A14.9857300.00N/A955N/A0N/A49N/A906PASS
2B127ONCOLOGY RESEARCH8869.07,9740.0386.0N/A4.3634740.00N/A579N/A0N/A76N/A503FAIL*Fume hood is offline
2B126RESEARCH OFFICE1069.09540.0006.0N/A6.736420.00N/A107N/A0N/A0N/A107PASS
2B125RESEARCH OFFICE3289.02,9520.0566.0N/A13.0538520.00N/A642N/A0N/A0N/A642PASS*Fume hood is offline
2B117CLINICAL LAB2628.82,2930.0156.0N/A16.1036900.00N/A615N/A0N/A375N/A240PASS
2B118ONCOLOGY RESEARCH LAB2269.02,0340.0156.0N/A13.3327120.00N/A452N/A0N/A0N/A452PASS*Fume hood is offline
2B120AGLASS WASH2809.02,5200.00010.0N/A12.2430840.00N/A514N/A0N/A655N/A-141PASS
2B120GLASS WASH748.0592-0.01610.0N/A0.000.00N/A110N/A0N/A0N/A110FAIL*Washer units offline
24

Total Rooms = 24

2ND FL RESEARCH (2)

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/18/23

RESEARCH BRAVO SIDE LEVEL 2
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG.

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

2B108OFFICE938.57910.0006.0N/A19.13N/A252N/A136N/A0N/A116PASS
2B107OFFICE938.57910.0056.0N/A24.97N/A329N/A253N/A0N/A76PASS
2B101PULMONARY RESEARCH3288.52,7880.0046.0N/A9.36N/A435N/A55N/A0N/A380PASS*Fume hood is offline
2B128BIOCHEMISTRY879.07830.0566.0N/A2.53N/A33N/A0N/A0N/A33FAIL
2B128ABIOCHEMISTRY2629.02,3580.0026.0N/A11.65N/A458N/A55N/A0N/A403PASS*Fume hood is offline
2B128BBIOCHEMISTRY448.03520.0066.0N/A18.75N/A110N/A0N/A0N/A110PASS
2B128CBIOCHEMISTRY1479.01,3230.0036.0N/A12.70N/A280N/A85N/A0N/A195PASS*Fume hood is offline
2B128C1BIOCHEMISTRY758.86560.0116.0N/A17.55N/A192N/A100N/A0N/A92PASS
2B123RESEARCH LAB1659.01,4850.0226.0N/A13.74N/A340N/A0N/A195N/A145PASS
2B124TISSUE CULTURE418.03280.0016.0N/A0.00N/A0N/A40N/A0N/A-40FAIL
2B125AOFFICE848.06720.0556.0N/A59.55N/A667N/A25N/A0N/A642PASS*Fume hood is offline
2B127BOFFICE1128.08960.0016.0N/A14.80N/A221N/A0N/A0N/A221PASS
2B118ACOMMON LAB1409.01,2600.0006.0N/A9.52N/A200N/A404N/A0N/A-204PASS
2B118BCOMMON LAB1209.01,0800.0006.0N/A1.11N/A20N/A151N/A0N/A-131FAIL
14

Total Rooms =14

2ND FL RESEARCH (3)

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/17/23

RESEARCH ALPHA SIDE LEVEL 2
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG.

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

2A127BIOCHEMICAL LAB--39000.0006.0N/A0.95N/A62N/A0N/A0N/A62FAIL
2A126BIOCHEMISTRY LAB--34300.0006.0N/A4.76N/A272N/A0N/A0N/A272FAIL*Fume hood is offline
2A103RESEARCH FINANCIAL--32930.0016.0N/A2.24N/A123N/A0N/A47N/A76FAIL
2A102RESEARCH ADMIN--12540.0026.0N/A4.59N/A96N/A0N/A0N/A96FAIL
2A102ACHIEF--10250.0016.0N/A4.68N/A80N/A0N/A0N/A80FAIL
2A102BSCIENCE INF. OFFICE--13800.0016.0N/A3.91N/A90N/A0N/A0N/A90FAIL
2A104AMALE TOILET--9050.0016.0N/A3.25N/A49N/A0N/A80N/A-31FAIL
2A125WOMENS LOCKERS--9260.0016.0N/A5.83N/A90N/A0N/A105N/A-15FAIL
2A125AWOMENS TOILET--7500.0016.0N/A8.00N/A100N/A0N/A109N/A-9PASS
2A1052ND FLOOR--6400.0056.0N/A6.28N/A67N/A0N/A0N/A67PASS
2A104MENS LOCKERS--7800.0016.0N/A3.08N/A40N/A0N/A99N/A-59FAIL
2A110CONFERENCE ROOM--24750.0026.0N/A2.04N/A84N/A0N/A25N/A59FAIL
2A128BIOCHEMISTRY LAB--35120.0006.0N/A2.08N/A122N/A0N/A0N/A122FAIL*Fume hood is offline
2A121HISTOLOGY RESEARCH LAB--42000.0016.0N/A0.00N/A0N/A0N/A0N/A0FAIL*Diffusers capped off
2A123ENDO, POLYP, CAN, INST--12000.0026.0N/A5.00N/A100N/A0N/A0N/A100FAIL*Exhaust register taped off
2A123AOFFICE--1313-0.0016.0N/A0.00N/A0N/A0N/A0N/A0FAIL*Exhaust register taped off
2A129LABORATORY OFFICE--43330.0016.0N/A1.59N/A115N/A0N/A0N/A115FAIL
2A130RESEARCH BUDGET OFFICE--37130.0066.0N/A2.49N/A154N/A0N/A0N/A154FAIL
2A120IMMUNOLOGY RESEARCH--14800.0016.0N/A9.32N/A230N/A0N/A0N/A230PASS
2A120A2ND FLOOR--1800.0006.0N/A0.00N/A0N/A0N/A90N/A-90FAIL
2A120B2ND FLOOR--16000.0006.0N/A13.13N/A350N/A0N/A0N/A350PASS
M2512ND FLOOR--20660.0036.0N/A13.65N/A470N/A0N/A0N/A470PASS
22

Total Rooms = 22

2ND FL RESEARCH (4)

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/17/23

RESEARCH ALPHA SIDE LEVEL 2
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS or FAIL
Room Volume Cu. Ft.NEG.

POS.

NR CODE Req'd Design Actual Design Actual Design Actual Design Actual Design Actual

Room # Room Description Area Sq. Ft. Ceiling Height

2A124OFFICE--19080.0026.0N/A8.74N/A278N/A0N/A0N/A278PASS
2A111HISTOPATOLOGY LAB--4593-0.0016.0N/A0.56N/A398N/A0N/A43N/A355FAIL*Fume hood is offline
2A108RESEARCH LAB--40200.0016.0N/A0.76N/A51N/A0N/A79N/A-28FAIL*Fume hood is offline
2A107RESEARCH LAB--45300.0146.0N/A5.66N/A427N/A0N/A0N/A427FAIL*Fume hood is offline
2A106GULF WAR ILLNESS--8400.0056.0N/A12.86N/A180N/A0N/A0N/A180PASS
2A114CELL CRYPTOPRESERVATION--39450.0146.0N/A6.31N/A415N/A0N/A55N/A360PASS
2A122TISSUE CULTURE RESEARCH--21000.0346.0N/A14.91N/A522N/A0N/A0N/A522PASS*Fume hood is offline
2A122ATISSUE CULTURE RESEARCH--23450.0016.0N/A5.88N/A230N/A0N/A0N/A230FAIL*Fume hood is offline
2A115LAB--40750.0036.0N/A5.01N/A340N/A0N/A75N/A265FAIL
2A118CLINICAL LAB--7860.0016.0N/A3.89N/A51N/A0N/A0N/A51FAIL
2A116IMMUNOLOGY LAB--9840.0066.0N/A9.76N/A160N/A0N/A80N/A80PASS
11

Total Rooms = 11

ADD ISO RM

AIR BALANCE SUMMARY SHEET

PROJECT NAME: DATE:

ADDITIONASL ISOLATION ROOMS
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS or FAIL
Room Volume Cu. Ft.NEG.

POS.

NR CODE Req'd Design Actual Design Actual Design Actual Design Actual Design Actual

Room # Room Description Area Sq. Ft. Ceiling Height

B126-1HEMO BED STA--63900.04120.0N/A20.61N/A2,19500N/A990N/A1,205PASS
B127-1HEMO BED STA--63900.04120.0N/A20.61N/A2,19500N/A991N/A1,204PASS
B128-1HEMO BED STA--63900.04120.0N/A20.61N/A2,19500N/A992N/A1,203PASS
C302A4MICU PT BED--57610.01820.0N/A16.46N/A1,58000N/A1,108N/A472FAIL
C302A5PCU PT BED--57610.01820.0N/A16.46N/A1,58000N/A1,109N/A471FAIL
C302A6PCU PT BED--57610.01820.0N/A16.46N/A1,58000N/A1,110N/A470FAIL
1.00E+78ED PT BED--57610.01820.0N/A16.46N/A1,58000N/A1,111N/A469FAIL
1.00E+78ED PT BED--57610.01820.0N/A16.46N/A1,58000N/A1,112N/A468FAIL
8

Total Rooms = 8

3RD FL OR

AIR BALANCE SUMMARY SHEET

PROJECT NAME: DATE:

3RD FLOOR OR's
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS or FAIL
Room Volume Cu. Ft.NEG.

POS.

NR CODE Req'd Design Actual Design Actual Design Actual Design Actual Design Actual

Room # Room Description Area Sq. Ft. Ceiling Height

OR-1 (B354)OPERATING ROOM--63900.04120.0N/A20.61N/A2,19500N/A990N/A1,205PASS
OR-2 (B351)OPERATING ROOM--67700.03920.0N/A20.43N/A2,30500N/A855N/A1,450PASS
OR-3 (B340)OPERATING ROOM--51500.03520.0N/A27.73N/A2,38000N/A1,235N/A1,145PASS
OR-4 (B342)OPERATING ROOM--54500.05720.0N/A26.43N/A2,40100N/A908N/A1,493PASS
OR-5 (B344)OPERATING ROOM--77400.05720.0N/A20.58N/A2,65500N/A1,155N/A1,500PASS
OR-6 (B347)OPERATING ROOM--76200.06920.0N/A20.51N/A2,60500N/A278N/A2,327PASS
OR-7 (B348)OPERATING ROOM--76500.03220.0N/A20.02N/A2,55200N/A1,109N/A1,443PASS
SUPPORT ORSUPPORT OR 1 to 4--5630-0.0024.0N/A4.38N/A39800N/A411N/A-13PASS
OR-8OPERATING ROOM--57610.01820.0N/A16.46N/A1,58000N/A1,108N/A472FAIL
OR-9OPERATING ROOM--52540.04820.0N/A16.62N/A1,45500N/A178N/A1,277FAIL
B331PACU--18292-0.0014.0N/A3.92N/A87100N/A1,195N/A-324FAIL
B331BBED 10--1018-0.01520.0N/A10.61N/A6700N/A180N/A-113FAIL
OR-10 (B337B)OPERATING ROOM--39320.01320.0N/A23.00N/A1,50700N/A700N/A807PASS
OR-11 (B337A)OPERATING ROOM--21870.01520.0N/A44.58N/A1,62500N/A1,255N/A370PASS
B346CSUPPORT OR 5 & 6--1312-0.0034.0N/A8.19N/A10800N/A179N/A-71PASS
15

Total Rooms = 15

3RD FL LAB

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/21/23

3RD FLOOR
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG.

POS.

NR CODE Req'd Design Actual Design Actual Design Actual Design Actual Design Actual

Room # Room Description Area Sq. Ft. Ceiling Height

A305LABORATORY AREA9,9398.584,4820.0546.0N/A7.69N/A10,821N/AN/A5,507N/A5,314PASS
A305QCOPY & FILE ROOM2238.81,9510.0364.0N/A5.97N/A194N/AN/A232N/A-38PASS
A306AREADING ROOM638.85510.0144.0N/A30.91N/A284N/AN/A165N/A119PASS
A305ABLOOD DRAWING879.0783-0.0146.0N/A14.41N/A139N/AN/A188N/A-49PASS
A305KN/A3687.82,8520.0154.0N/A19.61N/A932N/AN/A0N/A932PASS*No exhaust / return grilles
B325BSPS PREP AREA1,3999.012,591-0.0064N/A0.12N/A915N/AN/A25N/A890FAIL*No fume hood or other exhaust equipment found
B325ESPS STERILIZATION RM7138.05,704010N/A6.89N/A655N/AN/A1,339N/A-684FAIL*Door not installed
B325SPS PASS THRU2528.02,0160.0014N/A0.00N/A0N/AN/A10N/A-10FAIL
A305PFILES1758.01,4000.0004N/A5.96N/A139N/AN/A130N/A9PASS
A305MELECTRON MICROSCOPE1898.01,5120.0004N/A7.78N/A196N/AN/A293N/A-97PASS
A305NGROSSING2278.01,8160.0044N/A21.57N/A653N/AN/A55N/A598PASS
B325SPS OR ENTRANCE2768.02,20804N/A0.00N/A0N/AN/A15N/A-15FAIL
B325D5DECONTAMINATION8508.06,800-0.0116.0N/A9.75N/A215N/AN/A1,105N/A-890PASS
B317AMEDICATION PREP.1128.08960.0056.0N/A19.75N/A295N/AN/A119N/A176PASS*Room under construction
14
*Doors removed from several sps areas

Total Rooms = 14

12C WING

AIR BALANCE SUMMARY SHEET

PROJECT NAME:BRUCE W CARTER VETERANS AFFAIR MEDICAL CENTERDATE:4/17/23
TEST & BALANCE - BUILDING 1
PATIENT ROOMS LEVEL 12
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS or FAIL
Room Volume Cu. Ft.NEG. POS. EQUAL NRCODE Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

C1201APATIENT ROOM1717.51,283EQUAL4.0N/A0.00N/A0N/A0N/A0N/A0FAIL*Under construction
C1202PATIENT ROOM1667.51,245EQUAL4.0N/A2.84N/A39N/A59N/A58N/A-78FAIL
C1206PATIENT ROOM1577.51,178EQUAL4.0N/A4.94N/A97N/A55N/A55N/A-13PASS
C1207PATIENT ROOM1717.51,283EQUAL4.0N/A2.20N/A25N/A42N/A47N/A-64FAIL
C1208PATIENT ROOM1727.51,290EQUAL4.0N/A5.35N/A115N/A38N/A70N/A7PASS
C1209PATIENT ROOM1687.51,260EQUAL4.0N/A1.76N/A37N/A22N/A38N/A-23FAIL
C1210PATIENT ROOM1697.51,268EQUAL4.0N/A1.85N/A21N/A39N/A15N/A-33FAIL
C1211PATIENT ROOM1687.51,260EQUAL4.0N/A7.48N/A157N/A35N/A36N/A86PASS
C1212PATIENT ROOM1697.51,268EQUAL4.0N/A0.71N/A0N/A0N/A15N/A-15FAIL
C1213PATIENT ROOM1707.51,275EQUAL4.0N/A2.07N/A44N/A25N/A30N/A-11FAIL
C1214PATIENT ROOM1687.51,260EQUAL4.0N/A8.90N/A25N/A187N/A44N/A-206PASS
C1215PATIENT ROOM1677.51,253EQUAL4.0N/A7.66N/A18N/A160N/A10N/A-152PASS
C1216PATIENT ROOM1667.51,245EQUAL4.0N/A20.77N/A0N/A431N/A12N/A-443PASS*No supply grille installed
C1217PATIENT ROOM1667.51,245EQUAL4.0N/A6.89N/A36N/A143N/A18N/A-125PASS
C1218PATIENT ROOM1657.51,238EQUAL4.0N/A3.30N/A40N/A68N/A20N/A-48FAIL
C1219PATIENT ROOM1667.51,245EQUAL4.0N/A5.54N/A55N/A115N/A15N/A-75PASS
C1220PATIENT ROOM1677.51,253EQUAL4.0N/A2.16N/A18N/A45N/A10N/A-37FAIL
C1221PATIENT ROOM1647.51,230EQUAL4.0N/A21.85N/A25N/A448N/A18N/A-441PASS
C1222PATIENT ROOM1667.51,245EQUAL4.0N/A13.64N/A33N/A283N/A35N/A-285PASS
19

Total Rooms = 19

12D WING

AIR BALANCE SUMMARY SHEET

PROJECT NAME:BRUCE W CARTER VETERANS AFFAIR MEDICAL CENTERDATE:4/17/23
TEST & BALANCE - BUILDING 1
PATIENT ROOMS LEVEL 11
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS or FAIL
Room Volume Cu. Ft.NEG. POS. EQUAL NRCODE Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

D1202PATIENT ROOM1707.51,275EQUAL4.0N/A1.32N/A28N/A35N/A48N/A-55FAIL
D1203PATIENT ROOM1687.51,260EQUAL4.0N/A4.86N/A102N/A22N/A96N/A-16PASS
D1204PATIENT ROOM1597.51,193EQUAL4.0N/A15.60N/A310N/A18N/A15N/A277PASS
D1205PATIENT ROOM1717.51,283EQUAL4.0N/A10.53N/A225N/A55N/A55N/A115PASS
D1206PATIENT ROOM1697.51,268EQUAL4.0N/A0.47N/A10N/A0N/A10N/A0FAIL
D1207PATIENT ROOM1687.51,260EQUAL4.0N/A4.14N/A87N/A65N/A14N/A8PASS
D1208PATIENT ROOM1697.51,268EQUAL4.0N/A5.11N/A108N/A72N/A20N/A16PASS
D1209PATIENT ROOM1687.51,260EQUAL4.0N/A4.10N/A55N/A86N/A0N/A-31PASS
D1210PATIENT ROOM1697.51,268EQUAL4.0N/A8.85N/A187N/A112N/A0N/A75PASS
D1211PATIENT ROOM1707.51,275EQUAL4.0N/A3.06N/A65N/A46N/A26N/A-7FAIL
D1212PATIENT ROOM1687.51,260EQUAL4.0N/A2.14N/A45N/A45N/A10N/A-10FAIL
D1213PATIENT ROOM1677.51,253EQUAL4.0N/A0.00N/A0N/A0N/A0N/A0FAIL*Under construction
D1214PATIENT ROOM1667.51,245EQUAL4.0N/A3.18N/A25N/A66N/A55N/A-96FAIL
D1215PATIENT ROOM1667.51,245EQUAL4.0N/A2.31N/A48N/A40N/A60N/A-52FAIL
D1216PATIENT ROOM1657.51,238EQUAL4.0N/A5.09N/A0N/A45N/A105N/A-150PASS
15

Total Rooms = 15

ANIMAL RESEARCH 1ST FL

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/14/23

BLDG. 7 ANIMAL RESEARCH 1ST FLOOR
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

115STORAGE ROOM--13360.0024.0N/A4.54N/A101N/A0N/A89N/A12PASS
117STORAGE ROOM--1215-0.0024.0N/A4.59N/A88N/A0N/A93N/A-5PASS
120NECROPSY--16380.00115.0N/A1.83N/A50N/A0N/A45N/A5FAIL
123STORAGE ROOM--1215-0.2004.0N/A27.46N/A63N/A0N/A556N/A-493PASS*Temporary AC unit installed in exhaust
124PROCEDURE LAB--12750.00115.0N/A4.09N/A87N/A0N/A35N/A52FAIL
126VETERINARIAN--12750.0014.0N/A3.11N/A66N/A0N/A15N/A51FAIL
127SUPERVISOR--13360.0014.0N/A2.60N/A58N/A0N/A0N/A58FAIL
128ANIMAL RECEIVING--24570.00610.0N/A2.10N/A86N/A0N/A36N/A50FAIL
136ANIMAL WARD--47250.00215.0N/A2.97N/A234N/A0N/A190N/A44FAIL*Temporary AC unit installed in exhaust
139PROCEDURE LAB--2457-0.03515.0N/A16.02N/A261N/A0N/A656N/A-395PASS
116ANIMAL WARD--47250.00015.0N/A2.68N/A211N/A0N/A212N/A-1FAIL
110OPERATING ROOM--24750.00715.0N/A3.88N/A160N/A0N/A0N/A160FAIL
108OPERATING ROOM--24740.00615.0N/A4.00N/A165N/A0N/A69N/A96FAIL
109PRE-OPERATION ROOM--10800.0004.0N/A4.50N/A81N/A0N/A61N/A20PASS
107POST-OPERATION ROOM--10800.00010.0N/A4.61N/A83N/A0N/A67N/A16FAIL
106CONFERENCE ROOM--2079-0.0014.0N/A2.91N/A56N/A0N/A101N/A-45FAIL
149STORAGE ROOM--2457-0.0044.0N/A6.03N/A245N/A0N/A247N/A-2PASS
148STORAGE ROOM--11700.0334.0N/A3.85N/A75N/A0N/A36N/A39FAIL
148ASTORAGE ROOM--11700.0024.0N/A5.03N/A98N/A0N/A76N/A22PASS
147STORAGE ROOM--2268-0.0064.0N/A4.68N/A109N/A0N/A177N/A-68PASS*Diffuser taped off
144PROCEDURE LAB--2457-0.00415.0N/A12.94N/A246N/A0N/A530N/A-284FAIL
143ANIMAL WARD--24570.00115.0N/A4.96N/A203N/A0N/A152N/A51FAIL
22

Total Rooms = 22

ANIMAL RESEARCH 1ST FL (2)

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/13/23

BLDG. 7 ANIMAL RESEARCH 1ST FLOOR
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

142PROCEDURAL ROOM--24570.00415.0N/A4.74N/A194N/A0N/A129N/A65FAIL
140ANIMAL WARD--2457-0.00215.0N/A2.71N/A270N/A0N/A277N/A-7FAIL
138STORAGE ROOM--24570.0004.0N/A1.86N/A76N/A0N/A111N/A-35FAIL*Light removed from ceiling, creating large opening
137CAGE WASHING ROOM--25470.05520.0N/A14.96N/A635N/A0N/A0N/A635FAIL*Autoclave down for repair. Large opening in ceiling
125QUARANTINE--8890.00815.0N/A13.36N/A198N/A0N/A101N/A97FAIL
122FEED ROOM--5250.0014.0N/A7.43N/A65N/A0N/A0N/A65PASS
121STORAGE ROOM--5510.0164.0N/A22.76N/A209N/A0N/A0N/A209PASS
112STORAGE ROOM--24520.0004.0N/A5.16N/A211N/A0N/A161N/A50PASS
111AUTOCLAVE--10660.0024.0N/A8.11N/A144N/A0N/A88N/A56PASS
N/AOR WASHING ROOM--891-0.0044.0N/A16.84N/A190N/A0N/A250N/A-60PASS
135CLEAN CAGE ROOM--40610.0556.0N/A9.09N/A615N/A0N/A0N/A615PASS*Cage wash under repair. Unable to take measurement
134LOUNGE--1179-0.0226.0N/A1.22N/A0N/A0N/A24N/A-24FAIL
CORRIDOR1ST FLOOR--153000.0074.0N/A2.00N/A510N/A0N/A0N/A510FAIL
NOTE: 1*:13

Total Rooms = 13

ANIMAL RESEARCH 3RD FL

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/12/23

BLDG. 7 ANIMAL RESEARCH 3RD FLOOR
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

307TISSUE CULTURE--13840.00115.0N/A4.77N/A110N/A0N/A175N/A-65FAIL
308PHYSIOLOGICAL LAB--3369-0.01915.0N/A10.93N/A304N/A0N/A614N/A-310FAIL
309PHYSIOLOGICAL LAB--33800.00115.0N/A7.49N/A422N/A0N/A675N/A-253FAIL
312BIOCHEMICAL LAB--33770.00215.0N/A5.54N/A312N/A0N/A738N/A-426FAIL
313BIOCHEMICAL LAB--33770.00015.0N/A3.86N/A217N/A0N/A731N/A-514FAIL
316RESEARCH LAB--33770.00815.0N/A4.12N/A232N/A0N/A712N/A-480FAIL
318BIOCHEMICAL LAB--33220.00515.0N/A3.38N/A187N/A0N/A0N/A187FAIL*Fume hood not working
324NEPHROLOGY RESEARCH--35410.02215.0N/A5.98N/A353N/A0N/A877N/A-524FAIL
321PHYSIOLOGICAL LAB--1734-0.00115.0N/A12.91N/A80N/A0N/A373N/A-293FAIL
320PHYSIOLOGICAL LAB--1661-0.02115.0N/A16.07N/A211N/A0N/A445N/A-234PASS
315BIOCHEMICAL LAB--25990.00615.0N/A6.81N/A295N/A0N/A0N/A295FAIL
314PHYSIOLOGICAL LAB--5301-0.02415.0N/A13.13N/A421N/A0N/A1160N/A-739FAIL
311GENERAL LAB--5301-0.00415.0N/A13.84N/A290N/A0N/A1223N/A-933FAIL
310HISTOPATOLOGY, ONC LAB--3649-0.00815.0N/A14.75N/A415N/A0N/A897N/A-482FAIL
344OPHTALMOLOGY, ENVI RE--31810.00615.0N/A3.70N/A196N/A0N/A670N/A-474FAIL
342PEPTIDE RECEPTOR LAB--33490.00415.0N/A3.28N/A183N/A0N/A610N/A-427FAIL
341MOLECULAR BIO INST--33500.00515.0N/A6.59N/A368N/A0N/A441N/A-73FAIL
340STEM CELL BIOLOGY--34220.00015.0N/A2.89N/A165N/A0N/A584N/A-419FAIL
339BRAIN DEV, MND LAB--34220.00215.0N/A3.23N/A184N/A0N/A561N/A-377FAIL
338CMJ STEM CELL, BRAIN RE--34220.00515.0N/A5.17N/A295N/A0N/A451N/A-156FAIL
335SKELETAL CELL, MOL BIO RM--34220.00515.0N/A4.63N/A264N/A0N/A595N/A-331FAIL
333PROSTATE CANCER--34220.00315.0N/A2.52N/A144N/A0N/A475N/A-331FAIL
332GLASS WASH, AUTO CL RM--2473-0.0815.0N/A35.18N/A1,060N/A0N/A1450N/A-390PASS
23

Total Rooms = 23

ANIMAL RESEARCH 3RD FL (2)

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/12/23

BLDG. 7 ANIMAL RESEARCH 3RD FLOOR
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

331COMMON INSTRUMENTS--2198-0.00815.0N/A16.60N/A130N/A0N/A608N/A-478PASS
334CELL CRYOPRESERVATION--1764-0.04515.0N/A39.12N/A134N/A0N/A1150N/A-1,016PASS
336CELL, TISSUE CULTURE--16580.02315.0N/A12.01N/A332N/A0N/A445N/A-113FAIL
337REARCH CLEAN ROOM--3484-0.06415.0N/A31.86N/A970N/A0N/A1850N/A-880PASS
345RESEARCH LAB--2630-0.00315.0N/A13.14N/A305N/A0N/A576N/A-271FAIL
CORRIDORCORRIDOR--204980.0024.0N/A3.56N/A1,215N/A0N/A398N/A817FAIL
6

Total Rooms = 6

BILL KLING CLINIC

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/20/23

BILL KLING (BROWARD) CLINIC
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

SP139PREP AREA3838.53,2560.0024.0N/A3.69N/A200N/A0N/A29N/A171FAIL
DC112ADENTAL CLEAN STORAGE438.33550.0014.0N/A19.28N/A114N/A65N/A0N/A49PASS
SM123CSCOPE STERILIZATION ROOM549.0486-0.0046.0N/A54.32N/A99N/A0N/A440N/A-341PASS
SM124SCOPE CLEAN ROOM579.05170.0014.0N/A5.81N/A50N/A0N/A0N/A50PASS
PC127STORAGE ROOM779.06930.0014.0N/A4.33N/A50N/A0N/A0N/A50PASS
DE107STORAGE ROOM669.05940.0014.0N/A4.44N/A44N/A0N/A0N/A44PASS
AD108BOOTH 1 STAFF726.5468-0.0016.0N/A0.00N/A50N/A60N/A0N/A-10FAIL
AD108BOOTH 1 PATIENT726.5468-0.0016.0N/A0.00N/A50N/A60N/A0N/A-10FAIL
AD108BOOTH 2 STAFF1076.5696-0.0066.0N/A0.00N/A52N/A101N/A0N/A-49FAIL
AD108BOOTH 2 PATIENT1066.568906.0N/A4.09N/A47N/A60N/A0N/A-13FAIL
AD108BOOTH 3 STAFF556.5358-0.0096.0N/A0.00N/A46N/A112N/A0N/A-66FAIL
AD108BOOTH 3 PATIENT556.53580.0036.0N/A20.31N/A121N/A61N/A0N/A60PASS
AD101RECEPTION1119.91,0990.0014.0N/A5.41N/A99N/A58N/A0N/A41PASS
AD102OFFICE / TREATMENT1359.01,2150.0014.0N/A2.17N/A44N/A23N/A0N/A21FAIL
AD106OFFICE / TREATMENT1119.0999-0.0094.0N/A0.00N/A58N/A130N/A0N/A-72FAIL
AD107OFFICE / TREATMENT1469.01,3140.0034.0N/A2.74N/A60N/A16N/A0N/A44FAIL
SM132EXAM ROOM 41569.01,4040.0024.0N/A3.38N/A79N/A40N/A0N/A39FAIL
SP138CLEAN STERILE STORAGE1999.01,7910.0024.0N/A2.28N/A68N/A0N/A112N/A-44FAIL
SP137DECONTAMINATION1829.01,641-0.0226.0N/A9.33N/A73N/A0N/A255N/A-182PASS
RD104RADIOLOGY RIGHT ROOM1089.51,026-0.0026.0N/A23.80N/A263N/A0N/A407N/A-144PASS*No barrier between spaces
RD104RADIOLOGY LEFT ROOM2409.02,160-0.0026.0N/A14.64N/A164N/A0N/A527N/A-363PASS*No barrier between spaces
Site Address: Broward Clinic 9800 West Commercial Blvd Sunrise, 33351, FL21

Total Rooms = 21

PEMBROKE CLINIC

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/20/23

PEMBROKE CLINIC
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

CorrAudiology Booth Staff537.338406.0N/A1.87N/A12N/A0N/A19N/A-7FAIL
CorrAudiology Booth Patient486.531206.0N/A5.58N/A29N/A0N/A12N/A17FAIL
Site Address: Pembroke Pines 7369 Sheridan St, Hollywood, FL, 330242

Total Rooms = 2

HOLLYWOOD CLINIC

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/20/23

HOLLYWOOD CLINIC
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

225Audiology2048.51,73406.0N/A6.16N/A178N/A155N/A0N/A23PASS
225Audiology Booth456.5293-0.0016.0N/A0.00N/A0N/A71N/A0N/A-71FAIL
226Audiology1088.5918-0.0036.0N/A0.00N/A80N/A208N/A0N/A-128FAIL
227Audiology1528.51,292-0.0016.0N/A0.00N/A212N/A235N/A0N/A-23FAIL
227Audiology Booth476.530606.0N/A9.62N/A49N/A42N/A0N/A7PASS
228Audiology978.582506.0N/A0.00N/A0N/A0N/A0N/A0FAIL
Site Address: Hollywood 3702 Washington St, Hollywood, FL, 330216

Total Rooms = 6

DEERFIELD CLINIC

AIR BALANCE SUMMARY SHEET

PROJECT NAME: 4/20/23

DEERFIELD CLINIC
PressureAir ChangesSupplyReturnExhaustInf. / Exf.PASS

or

FAIL

Room Volume
Cu. Ft.NEG

POS.

EQUAL

NRCODE
Req'dDesignActualDesignActualDesignActualDesignActualDesignActual

Room # Room Description Area Sq. Ft. Ceiling Height

110Audiology9310.0930EQUAL6.0N/A4.84N/A75N/A0N/A0N/A23FAIL*No return grille
113Audiology11310.01,130EQUAL6.0N/A0.27N/A5N/A0N/A0N/A24FAIL*No return grille
115Audiology17610.01,760EQUAL6.0N/A9.72N/A285N/A70N/A0N/A25PASS
115Audiology Booth516.5332EQUAL6.0N/A0.00N/A0N/A55N/A0N/A26FAIL
Site Address: Deerfield Beach 2100 SW 10th St, Deerfield Beach, FL, 334424

Total Rooms = 4

ABBREVIATIONS TERMINOLOGIES

ABBREVIATIONS & TERMINOLOGYABBREVIATIONS & TERMINOLOGY
A:Nameplate AmpsEAT:Entering Air TemperaturesHVAC:Heating Ventilating & AirRND:Round
AHU:Air Handling UnitECON:Economizer - Controls & ComponentsConditioningRA:Return Air
AC:Air Conditionerthat allow an Air Handler to logicallyHWR:Hot Water Return or Heating WaterRAT:Return Air Temperature
ACU:Air Conditioning Unitutilize outdoor air for cooling asReturnREQ:Required
ACCU:Air Cooled Condensing Unitopposed to the use of mechanicalHWS:Hot Water Supply or Heating WaterRF:Return Air Fan
ACH:Air Changers Per Hourcooling.SupplyRHC:Re-Heat Coil
AMP:AmpereEDC:Electric Duct CoilHX:Heat ExchangerRPM:Revolutions Per Minute
AVG:AverageEDH:Electric Duct HeaterHydronic:Indicates the Use or Conveyance
EF:Exhaust Fanof Liquid for Thermal TransferSA:Supply Air
EH:Exhaust HoodSAT:Supply Air Temperature
BDD:Back Draft DamperEMS:Energy Management System (s)ID:Inside DiameterSCD:Static Control Damper
BHP:Brake HorsepowerEMCS:Energy Management Control System(s)IV:Inlet VanesSEF:Smoke Exhaust Fan
BTU:British Thermal UnitENT:EnteringSF:Supply Fan (Air)
BTUH:British Thermal Units Per HourER:Exhaust RegisterK:Correction FactorSHC:Steam Heating Coil
EWT:Entering Water TemperatureSP:Set Point
CAV:Constant Air VolumeLAT:Leaving Air TemperatureSPF:Stairwell Pressurization Fan
CC:Cooling CoilF:Degrees FahrenheitLPS:Low Pressure SteamSP 'WC':Static Pressure Resistance Measured
CD:Ceiling DiffuserFCU:Fan Coil UnitLV:Leavingin Inches of Water Column
CFM:Cubic Feet Per MinuteFD:Fire DamperLWG:Low Wall GrilleSWDSidewall Diffuser
CGCeiling GrilleFH:Fume HoodLWR:Low Wall RegisterSWG:Sidewall Grille
CH:ChillerFG:Floor GrilleLWT:Leaving Water TemperatureSWR:Sidewall Register
CHW:Chilled WaterFLA:Full Load Amperage
CHWR:Chilled Water ReturnFLTS:FiltersMUAH:Make-Up Air HandlerTAB:Testing, Adjusting and Balancing
CHWS:Chilled Water SupplyFPB:Fan Powered BoxMAU:Make-Up Air UnitTD:Differential Temperature, Net
CP:Circulating PumpFPM:Feet Per MinuteMBH:Thousand BTU's Per HourTemperature Decrease or Increase
CR:Ceiling RegisterFR:Floor RegisterTP:Traverse Point/Test Point
CT:Cooling TowerFSD:Fire/Smoke DamperN/A:Not Applicable or Not AvailableTSP:Total Static Pressure
CU:Condensing UnitFTU:Fan Terminal UnitN/L:Not Listed
CUH:Cabinet Unit HeaterNVL:No Valid LocationUH:Unit Heater
CW:Condensing WaterGPM:Gallons Per Minute
CWR:Condenser Water ReturnOD:Outside DiameterV:Voltage/Volt/Volts
CWS:Condenser Water SupplyHC:Heating CoilVAV:Variable Air Volume
CX:CommissioningHD:Head Pressure MeasuredOSA or OA:Outside AirVD:Volume Damper
in Inches or Feet of WaterOAT:Outside Air TemperatureVEL:Velocity
DAT:Discharge Air TemperatureHeater OL:Thermal Overload Protection forVFD:Variable Frequency Drive
DB:Dry BulbMotors Located at the Motor StarterP:Circulating Pump(Electric Motor Speed Controller)
DD:Direct DriveHEPA:High Efficiency ParticulatePD:Differential Pressure or Pressure DropVP:Velocity Pressure
DP:Delta Pressure, Difference, Net Decrease or IncreaseArrestancePF:Power Factor
DNA:Data Not AvailableHOA:Hand/Off/Auto SwitchPHC:Pre-Heat CoilW:Watts
DNG:Data Not GivenHP:Horse PowerPH:Phase (s)WB:Wet Bulb
DNL:Data Not ListedHPS:High Pressure SteamPSI:Pounds Per Square InchWG:Water Gauge