Updated_Engineer's_Estimate_9_3_25.pdf
PDF 70 KB Posted
- Solicitation number
- IFB26-3
- Issued by
- Orange County, Woodlawn Beach CDP, Florida
About this file
This is an Engineer's Estimate prepared by the City of Winter Park Public Works for the Library and Event Center Parking Lot Expansion project in Florida. The project encompasses demolition, storm drainage installation, and roadway restoration work. Key project elements include clearing and grubbing operations, installation of 228 linear feet of 8-inch drain pipe with three yard drains, excavation and grading of a 75 cubic yard pond, asphalt paving of 1,542 square yards, installation of 383 square yards of sidewalk, placement of various curb types totaling 1,654 linear feet, and site finishing work including fencing, striping, and sod installation.
The Opinion of Probable Construction Cost totals $497,654.61, comprised of administration costs of $100,970.40, demolition and disposal at $68,523.50, storm drainage work at $30,232.44, and roadway and right-of-way restoration at $297,928.26. The cost estimate is based on final engineering plans dated January 24, 2025, and reflects an asphalt option for the parking expansion. Unit costs range from $2.00 per linear foot for striping to $85.00 per square yard for sidewalk installation, with larger expenses allocated to soil cement base work at $83,268.00 and asphalt placement at $22,050.60.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM # ITEM DESCRIPTION QUANTITY UNIT COST TOTAL
1 Mobilization 1 LS 50,647.80$ 50,647.80$
2 Bonds and Insurance 1 LS 14,929.64$ 12,550.49$
3 As-Builts 1 LS 5,000.00$ 5,000.00$
4 Maintenance of Traffic 1 LS 14,896.41$ 14,896.41$
5 Erosion and Sediment control 1 LS 17,875.70$ 17,875.70$
TOTAL 100,970.40$
ITEM # ITEM DESCRIPTION QUANTITY UNIT COST TOTAL
1 Clearing and Grubbing 1 LS 68,523.50$ 68,523.50$
DEMOLITION AND DISPOSAL TOTAL TOTAL 68,523.50$
ITEM # ITEM DESCRIPTION QUANTITY UNIT COST TOTAL
1 8" x 6" Yard Drain 3 EA 4,600.00$ 13,800.00$
2 8" Drain Pipe 228 LF 56.00$ 12,768.00$
3 8" Mitered End Section With Pad 1 EA 1,400.00$ 1,400.00$
4 Excavate Pond 75 CY 20.00$ 1,500.00$
5 Grade Pond Slopes 191 SY 4.00$ 764.44$
TOTAL 30,232.44$
ITEM # ITEM DESCRIPTION QUANTITY UNIT COST TOTAL
1 Asphalt 1.5" 1542 SY 14.30$ 22,050.60$
2 Install Sidewalk 383 SY 85.00$ 32,555.00$
3 Type B Curb (flush) 156 LF 29.00$ 4,524.00$
4 Type D Curb 1013 LF 43.00$ 43,559.00$
5 Type F Curb 43 LF 38.00$ 1,634.00$
6 2' Valley Curb 442 LF 58.00$ 25,636.00$
7 Grade and Compact Road Base 1542 SY 28.00$ 43,176.00$
8 Grade and Compact Roadway SubBase 1542 SY 16.00$ 24,672.00$
9 6" of Soil Cement Base 1542 SY 54.00$ 83,268.00$
10 Stabilization LBR40 Under Curb 520 SY 6.19$ 3,221.55$
11 Striping 1008 LF 2.00$ 2,016.00$
12 Wheel Stop 17 EA 65.00$ 1,105.00$
13 Sod 178 SY 4.00$ 711.11$
14 Fencing 350 LF 28.00$ 9,800.00$
TOTAL 297,928.26$
497,654.61$
ROADWAY AND RIGHT OF WAY RESTORATION TOTAL
OVERALL TOTAL
DEMOLITION AND DISPOSAL
STORM DRAINAGE
STORM DRAINAGE TOTAL
ROADWAY AND RIGHT OF WAY RESTORATION
ADMINISTRATION TOTAL
OPINION OF PROBABLE CONSTRUCTION COST
Project Name: Library and Event Center Parking Expansion
Plans Prepared by: City of Winter Park Public Works Stormwater Management
Cost Basis: Final Engineering Plans Asphalt Option 1/24/2025
ADMINISTRATION
File details come from the government source that posted it. Updated .