Winter Park Library and Event Center Parking Lot Expansion
Solicitation number
IFB26-3
Issued by
Orange County, Woodlawn Beach CDP, Florida

About this file

This is a technical specifications document for the Winter Park Library and Event Center Parking Lot Expansion project in Florida, detailing construction standards and requirements for site earthwork, grading, and concrete work. The project scope encompasses excavation and fill operations for curbs, gutters, sidewalks, driveways, roads, and parking lots, with work including site preparation, embankment construction, compaction, and material disposal. The specifications reference Florida Department of Transportation (FDOT) 2015 standards throughout and establish detailed requirements for regular excavation, subsoil excavation, material classifications, and unsuitable material removal. Contractors are responsible for determining required material volumes and securing borrow materials from off-site sources if on-site excavation proves insufficient. The document specifies precise standards for fill materials, compaction densities varying by location (98% for roadways and driveways, 90% for other areas), subgrade stabilization with bearing value requirements of 75 psi, concrete curb and driveway construction using Class I concrete with minimum 3,000 psi compressive strength, and site restoration including sidewalk and driveway replacement.

Key technical requirements include layer placement not exceeding eight inches in loose thickness, rock size restrictions limiting 3.5-inch diameter rock to interior fill and prohibiting rocks exceeding six inches in the top 12 inches of fill, final elevation tolerances of plus or minus 0.05 feet, topsoil placement depths of six inches for seeded areas and four and one-half inches for sodded areas, and mandatory testing for density compliance using AASHTO Method T-180. The contractor must protect existing utilities, fencing, trees, and landscaping, maintaining the site in clean condition throughout operations. Prime coat application for base courses requires adherence to FDOT specifications with application rates of 0.10 to 0.25 gallons per square yard depending on base material type. All material ownership for suitable excavated materials remains with the owner unless otherwise specified, and unsuitable materials must be disposed of outside project limits at the contractor's expense.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

02200-1

SECTION 02200

EARTHWORK

1.01 DESCRIPTION:

A. The work specified in this section consists of the excavation and fill required for:

1. Curb and Gutter

2. Sidewalks and Driveways

3. Roads and Parking Lots

B. The work shall include the preparation of sub-grades, the construction of embankments, compaction and dressing of excavated areas and embankments, and the disposing of excess suitable and unsuitable excavated materials.

C. Included as excavation under this section are materials of whatever nature, which are encountered within the required limits of the excavation. All work under this section shall be in accordance with the alignment, grades and section as shown in the plans or as directed by the Engineer.

1.02 RELATED WORK SPECIFIED ELSEWHERE:

A. Work not included within this section shall include excavation and embankment for all drainage structures and water pipes.

1.03 CLASSIFICATIONS OF EXCAVATION:

A. General: The excavation specified under this section is classified as (1) Regular Excavation; and (2) Subsoil Excavation.

B. Regular Excavation: Regular excavation shall include all excavation, excluding subsoil excavation and borrow excavation.

C. Subsoil Excavation: Subsoil excavation shall consist of the excavation and disposal of much clay, rock, cemented or dense (hardpan) soils, and/or other material that is unsuitable in its original condition and that is excavated below the finished grading template.

2.01 MATERIAL FOR FILLED SECTIONS:

A. Materials used for fill shall be free of much, stumps, roots, brush, vegetable matter, rubbish or other material that will not compact into a suitable building pad, roadbed, or other section as required on the plans.

02200-2

B. The maximum size of rock allowed in the completed section is 3-1/2 inches.

C. All borrow required for the work shall be secured by the contractor from off-site sources if there is an insufficient amount available from required on-site excavation.

3.01 REMOVAL OF UNSUITABLE MATERIALS:

A. Subsoil Excavation - Excavation of unsuitable subsoil shall be in accordance with the Florida D.O.T. Specifications (2015) Section 120-4.

3.02 DISPOSAL OF SURPLUS AND UNSUITABLE MATERIAL:

A. Ownership of Excavated Materials - Ownership of all suitable excavated materials shall remain the Owner's and shall be used for embankments unless otherwise specified.

B. Disposal of Peat or Muck - Unsuitable material shall be stockpiled in an area designated by the Owner.

3.03 EMBANKMENT CONSTRUCTION:

A. General - Embankments shall be constructed true to lines, grades and cross sections shown in the plans or ordered by the Engineer within the tolerances specified herein.

B. Dry Fill Method - Embankments shall be placed in successive layers of not more than eight inches in thickness, measured loose, for the full width of embankments.

As far as practicable, traffic over the work during the construction of embankments shall be distributed as to cover the maximum area of the surface of each layer.

3.04 COMPACTION REQUIREMENTS:

A. Compaction of Pipes, Culverts, etc., - The backfill of trenches shall be compacted to the densities specified for embankment or sub-grade, as applicable, and in accordance with the requirements of those pertinent sections dealing with installation pipe.

Embankments over and around pipes, culverts, and bridges shall be thoroughly compacted, in a manner which will not place undue stress on the structures, and in accordance with the requirements of those pertinent sections.

02200-3

B. Compaction of Embankment Platforms - Compact earth platforms for areas of future construction as directed by the engineer but in no case less than 95% density, as determined; by AASO-T-80.

3.06 MAINTENANCE AND PROTECTION OF WORK:

A. Is to be in accordance with the Florida D.O.T. current specifications, section 120-11.

3.07 FINAL DRESSING:

A. Comply with Florida D.O.T. current specifications, section 120-12.

END OF SECTION

02210-4

SECTION 02210

SITE GRADING

PART I. - GENERAL

1.01 Description

A. Scope of Work: The work in this section consists of furnishing all necessary labor, equipment, material and transportation necessary to bring the limerock or soil cement, road access drives, driveways, and open areas to the lines and grades shown on the Drawings. The work includes removal of existing pavement, slabs, walks, footings, structures and debris.

B. The Contractor must determine for himself the volume of material required for the site.

C. Definitions:

1. Open Areas: Open areas shall be those areas that do not include limerock, or soil cement areas, access road right-of-way and parking areas.

2. Maximum Density: Maximum weight in pounds per cubic foot (pcf) of a specific material.

3. Optimum Moisture: Percentage of water in a specific material at maximum density.

4. Rock Excavation: Excavation of any hard natural substance which requires the use of explosives and/or special impact tools such as, jackhammers, sledges, chisels, or other similar devices specifically designed for use in cutting or breaking rock, but exclusive of trench excavating machinery.

D. Related Work Described Elsewhere:

1. Earthwork: ........................................................................... Section 02200

2. Excavating, Backfilling and Compaction: Section 02220

3. Stabilized Subgrade: .......................................................... Section 02240

02210-5

PART II. - PRODUCTS

2.01 Materials

A. Suitable: suitable materials for fills shall be classified as A-1, A-3 or A-2-4 in accordance with AASHTO Designation M-145 and shall be free from vegetation and organic material. Not more than 10% (ten percent) by weight of fill material shall pass the No. 200 sieve. The Contractor shall furnish all additional fill material required.

B. Suitable material to be placed in water: Suitable material for fills to be placed in water shall be classified as A-1 or A-3 in accordance with AASHTO Designation M-145.

C. Unsuitable: Unsuitable materials are classified as A-2-5, A-2-6, A-2-7, A-4, A-5, A-6, A-7 and A-8 in accordance with AASHTO Designation M-145.

PART III. - EXECUTION

3.01 Performance

A. Excavation:

1. Excavation shall conform to the limits indicated on the plans or specified herein. This work shall include shaping and sloping and other work necessary in bringing the earthwork to the required grade, alignment and cross section.

2. All suitable materials removed from the excavation shall be used as far as practicable in the formation of the embankments, subgrades, shoulders, building sites and other places as directed. No excavated material shall be wasted without permission, and where necessary to waste much material it shall be at the direction of the Engineer. Unsuitable material shall be removed to the required depth and replaced to the satisfaction of the Engineer with suitable material. Unsuitable material existing in open areas may remain, and these open areas may be used for disposal areas for the unsuitable material as directed by the Engineer.

3. All waste excavated material shall be considered property of the Owner and disposed of as directed by the Engineer. Excess unsuitable material shall be disposed of outside the limits of the project.

B. Fills

02210-6

1. Fills shall be formed of suitable material placed in layers of not more than eight (8) inches in depth measured loose and rolled and/or vibrated with suitable equipment until compacted. Thickness of layers may be increased provided the equipment and methods used are proven by field density testing to be capable of compacting thicker layers to specified densities. Layer thickness shall be decreased if equipment and methods used are proven to be incapable of compaction of the layers to specified densities.

2. Rock that will not pass through a six (6") inch diameter ring shall not be placed within the top 12 " of the surface of the completed fill. Rock that will not pass through a three (3") inch diameter ring shall not be placed within the top four (4") inches of the completed fill. Broken concrete or asphaltic pavement shall not be used in fills.

3. Fill within the roadways, and driveways shall be compacted to a density of not less than 98% of its modified proctor maximum dry density as determined by AASHTO Method T-180 or ASTM D-1557, and fill within other areas shall be compacted to a density of not less than 90% of its maximum modified proctor density by AASHTO Method T-180 or ASTM D1557.

4. Muck or other unsuitable material may not be used as backfill for any structure, or as sub base material beneath any paved surface.

5. Final elevations shall be within +/-0.05 foot of the required elevation and surfaces shall be sloped to drain as shown on the Drawings.

C. Roadway Subgrades:

1. The construction of roadway subgrades shall conform to the requirements set forth hereinafter and shall consist of bringing the top of the roadway subgrade between the outer limits of the base course, to a surface conforming to the grades, lines and cross section shown on the plans, of uniform density, ready to receive the base course.

2. All material of the subgrades within the indicated limits shown on the

Drawings which provide a Limerock Bearing Ratio of less than 40 shall be stabilized as specified under Section 02230: Stabilized Subgrade.

3. After the subgrade has been properly shaped and stabilized, if required, it shall be brought to a firm, unyielding surface by rolling the entire area with an approved three (3) wheel power roller weighing not less than 10 tons. All areas inaccessible to the roller shall be thoroughly compacted with hand tampers weighing not less than 50 pounds, the face of which shall not exceed

02528-7

100 square inches in area. Unless the subgrade material at the time of the rolling contains sufficient moisture to insure proper compaction, it shall be watered as directed and then compacted. Subgrade material containing excess moisture, as determined by the Testing Laboratory, shall be dried to the proper consistency before being compacted.

4. The top 12" of the subgrade, including cut and fill sections, shall be compacted to a density of not less than 98 % of the maximum density as determined by the AASHTO Method T-180.

5. After the roadway subgrade has been prepared, the Contractor shall maintain it free of ruts, depressions and damage resulting from the hauling and handling of any material, equipment, tools, etc. Ditches or drains shall be constructed and maintained along the completed subgrade section. Just before the base course is laid, the subgrade shall be checked for crown and elevation. The final elevation of the subgrade shall be within 0.1 foot of the required elevation.

02528-8

SECTION 02212

FINISH GRADING

PART I. - GENERAL

1.01 DESCRIPTION

A. Scope of Work:

1. Finish grade sub-soil.

2. Cut out areas to receive stabilizing base course materials for limerock, concrete, or soil cement road and driveway areas.

3. Place, finish grade and compact topsoil.

B. Related Work Described Elsewhere:

1. Earthwork: Section 02220.

2. Site Grading: ........................................................................... Section 02210.

3. Solid Sodding: ........................................................................ Section 02934.

1.02 PROTECTION

A. Prevent damage to existing fencing, trees, landscaping, natural features, bench marks and utility lines. Correct damage at no cost to the Owner.

PART II - PRODUCTS

2.01 MATERIALS

A. Topsoil: Friable loam free from subsoil, roots, grass, excessive amounts of weeds, stones, and foreign matter; acidity ranges (pH) of 5.5 to 7.5; containing a minimum of four percent (4%) and a maximum of 25 percent (25%) organic matter. Use topsoil stockpiles on site if conforming to these requirements.

PART III - EXECUTION

3.01 SUB-SOIL PREPARATION

A. Rough grade sub-soil systematically to allow for a maximum amount of natural settlement and compaction. Eliminate uneven areas and low spots. Remove debris, roots, branches, stones, etc. Remove sub-soil which has been contaminated with petroleum products.

B. Cut out areas to sub-grade elevations, which are to receive stabilizing base for paving, 02528-9 curb, and driveway approaches.

C. Bring sub-soil to required levels, profiles, and contours. Make changes in grade gradual. Blend slopes into level areas.

D. Slope grade away from building minimum two (2) inches in ten feet unless indicated otherwise on the Drawings.

E. Cultivate sub-grade to a depth of three (3) inches, where topsoil is to be placed. Repeat cultivation in areas where equipment, used for hauling and spreading topsoil, has compact sub-soil.

3.02 PLACING TOPSOIL

A. Place topsoil in areas where seeding, sodding, and planting are to be performed. Place to the following minimum depths, up to finished grade elevations.

1. Six inches for seeded areas.

2. Four and one-half inches for sodded areas.

B. Use topsoil in relatively dry state. Place during dry weather.

C. Fine grade topsoil eliminating rough and low areas to ensure positive drainage.

Maintain levels, profiles, and contours of sub-grade.

D. Remove stone, roots, grass, weeds, debris and other foreign material while spreading.

E. Manually spread soil around trees, plants, buildings, to prevent damage which may be caused by grading equipment.

F. Lightly compact placed topsoil.

3.03 SURPLUS MATERIAL

A. Remove surplus sub-soil and topsoil from site.

B. Leave stockpile areas and entire job site clean and raked, ready to receive landscaping.

02528-10

SECTION 02230

SUB-GRADE STABILIZATION

DIVISION 2 - SITE WORK

A. Stabilizing, 12 inches of sub-grade to the limits shown on the construction plans, to a stability of 75 psi for the top 6 inches, as determined by the Florida Bearing Value method (FBV).

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Earthwork, Section 02200.

1.03 SUBMITTALS

A. The Contractor shall submit the materials and methods employed for stabilization.

PRODUCTS

2.01 MATERIALS

A. Selection of materials is at the option of the Contractor.

EXECUTION

3.01 STABILIZATION

A. It is the Contractor's responsibility that the finished sub-grade meets the bearing value requirements, regardless of type of quantity (if any) of stabilizing material.

B. The Engineer's responsibility in this operation is to insure that the materials and methods used will provide the required uniformity, particle size limitation, compaction and other desired results.

C. When additive stabilizing materials are required, the designated quantity will be spread uniformly over the area to be stabilized.

D. Mixing shall be completed with rotary tillers or other equipment meeting the approval of the Engineer.

E. At the completion of mixing, all particles of materials within the limits of the area

02528-11 to be stabilized shall pass a 3-1/2 inch ring.

3.02 BEARING VALUE REQUIREMENT

A. The soil-testing laboratory shall test the stabilized and compacted material and shall furnish the results in certified form to the Engineer.

B. A Florida Bearing Value with plus or minus 5.0 units shall be acceptable.

3.03 DENSITY REQUIREMENTS

A. The minimum density acceptable at any location as shown on the construction plans will be 98 percent of the maximum density and determined by AASHO T-180.

02528-12

SECTION 02528

CONCRETE CURBS, AND DRIVEWAYS

DIVISION 1 - SITE WORK

Furnish all material, equipment, transportation, tools and labor, unless otherwise specified, to construct concrete curbs, valley gutters, curb and gutter, and gravity retaining walls, with all appurtenances and all items called for or that can be reasonable inferred from the drawings, including excavating, backfilling, forming, jointing, placing of concrete, removing of forms, finishing, testing and curing for a complete job ready to operate. If any items for a complete job are omitted or not shown, the Contractor shall furnish and install the same without cost to the Owner.

DIVISION 2 - PRODUCTS

2.01 MATERIALS FOR CURBS

A. Concrete: FDOT Specifications for Road and Bridge Construction, 2015, Section 520, except that the word "Department" shall be taken as "Owner".

Make all concrete curbs with Class I concrete, minimum 28-day compressive strength of 3000 psi and a maximum slump of 4 inches.

B. Reinforcement: Steel reinforcement shall be in accordance with Section 415 and Section 931 of current FDOT Specifications for Road and Bridge Construction, 2015, Section 932-1.

C. Joint Materials: All joint materials shall conform to the requirements of the

FDOT current Standard Specifications for Road and Bridge Construction, 2015, Section 932-1.

D. Forms: All forms shall conform to the requirements of FDOT Standard

Specifications for Road and Bridge Construction, 2015, Section 520-3.

E. Curing Materials: Curing materials shall conform to the requirements of the FDOT Standard Specifications for Road and Bridge Construction, 2015, Section 925.

02528-13

2.02 MATERIALS FOR DRIVEWAY APPROACHES

A. Concrete: Concrete shall be Class I Concrete as specified in Section 345 of FDOT current Specifications. Minimum thickness within Public Right of Way will be 6”.

B. Reinforcement: Steel reinforcement shall be in accordance with Section 415 of

FDOT current Specifications.

C. Joint Materials: Joint materials shall be pre-formed joint filler for pavement and structures in accordance with Section 932-1.1 of FDOT current Specifications. Expansion joints will be hand tooled, containing a maximum surface area of 10sf.

D. Forms: Forms may be either wood or metal, at the Contractor's option. Forms shall be straight, free from warp or bend and of sufficient strength to withstand the pressure of the concrete, when staked, without deviation from line and grade. Forms shall be full depth and shall be cleaned after each use. They shall be oiled or saturated with water before concrete is placed against them.

DIVISION 3 - EXECUTION

3.01 CONSTRUCTING CURBS

All excavation, grading, formwork, joint construction, finishing, curing, backfilling and compaction shall be completed in accordance with Section 520 of FDOT current Specifications.

3.02 CONSTRUCTION OF WALKS & DRIVEWAYS

All excavating, grading, formwork, joint construction, finishing, curing, backfilling and compaction shall be completed in accordance with Section 522 of FDOT current Specifications.

02999-14

SECTION 02670

PRIME COAT FOR BASE COURSES

DIVISION 2- SITE WORK DESCRIPTION

Furnish all labor, materials, equipment and incidentals required to prime and tack coats for base courses the work includes, but is not limited to, cleaning, applying prime and tack material, covering rolling and any other miscellaneous work and clean-up required.

PRODUCTS

2.01 MATERIALS

Prime Coat: FDOT Spec. Section 300, Prime and Tack Coats for Base Courses, excluding the statement: “The Engineer will designate the actual temperature to ensure uniform distribution.” from Paragraph 300-6.1, General; and "The Engineer will designate the curing period for the tack coat" from Paragraph 300-7.5, Curing and Time of Application. The Contractor will be responsible for those determinations.

EXECUTION

3.01 GENERAL

A. Cleaning the Base: Before any bituminous material is applied, remove to the shoulders all loose material, dust, caked clay, and foreign material which might prevent proper bond with existing surface. Take particular care to clean the other edges of the strip to be treated to insure that tack coat will adhere. Where the prime or tack coat is applied adjacent to curb and gutter or valley gutter, such concrete surfaces are to be protected and kept free of bituminous material.

B. Weather Limitations: Do not apply bituminous material when the air temperature is less than 40 degrees F. in the shade, when the weather conditions or the condition of the existing surface is unsuitable, while rain is falling or when there is water on the surface to be covered.

C. Equipment: Use a pressure distributor equipped with pneumatic tires having a sufficient width of rubber in contact with the road surface to avoid breaking the bond or forming a rut in the surface. The distance between the centers of the openings of the outside nozzles of the spray bar shall be equal to the width of the application required, within an allowable variation of two inches. The outside nozzle at each end of the spray bar shall have an area of opening not less than 25 percent, nor more than 75 percent in excess of the other nozzles.

All other nozzles shall have uniform openings. When the application covers less than the full width, the normal opening of the end nozzle at the junction line may remain the same as those of the interior nozzles.

02999-15

3.02 APPLICATION OF PRIME COAT

A. The surface to be primed will be clean and dry. For limerock bases, the glazed finish will have been removed as specified. Temperature of prime material will be between 100 and 150 degrees F. The exact temperature will be such as to insure uniform distribution. Apply bituminous material at the rate of approximately 0.10 to 0.25 gallons per square yard, dependent upon the type of base material, sufficient to coat the surface thoroughly and uniformly without having any excess to form pools or flow off the base. Application rates shall be in accordance with D.O.T. Specifications 300-6.

B. Apply a light, uniform application of clean sand or screenings prior to opening the primed base to traffic and roll with a traffic roller in conjunction with traffic to cure the prime coat. If warranted by traffic conditions, apply only on one-half of the width of the base at one time, care being taken to secure the correct amount of bituminous material at the joint.

02999-16

SECTION 02999

MISCELLANEOUS WORK AND CLEANUP

DIVISION 1

1.01 SCOPE OF WORK

A. This Section includes operations which cannot be specified in detail as separate items but can be sufficiently described as to the type and extent of work involved. The Contractor shall furnish all labor, materials, equipment, and incidentals to complete the work under this Section.

B. The work of this Section includes, but is not limited to, the following:

1. Restoring of sidewalks, driveways, and fences.

2. Crossing utilities.

3. Cleaning up.

4. Incidental work.

DIVISION 2 - PRODUCTS

2.01 MATERIALS

Materials required for this Section shall be of the same quality as materials that are to be restored. Where possible, the Contractor shall reuse existing materials that are removed and then replaced.

DIVISION 3 - EXECUTION

3.01 COOPERATION WITH OTHER CONTRACTORS

It will be necessary for the Contractor to plan his work and cooperate with the City Utilities Division insofar as possible to prevent any interference and delay.

3.02 RESTORING OF SIDEWALKS, DRIVEWAYS, AND WALLS

A. Existing public and private sidewalks and driveways disturbed by the Contractor shall be replaced. Paved sidewalks and drives shall be repaved to the limits and thickness existing prior to construction.

02999-17

B. At two locations shown on the Drawings, it may be necessary for the

Contractor to remove, and replace existing walls or columns.

Only the sections directed by the Engineer shall be removed. If any section of wall is damaged due to the Contractor's negligence, it shall be replaced equal to or better than that damaged, and the work shall be satisfactory to the engineer.

3.03 CROSSING UTILITIES

This item shall include any extra work required in crossing culverts, water courses, drains, water mains, and other utilities, including all sheeting and bracing, extra excavation and backfill, or any other work required for the crossing, whether or not shown on the Drawings.

3.04 CLEANING UP

The Contractor shall remove all construction material, excess excavation, structures, equipment and other debris remaining on the job as a result of construction operations and shall render the site of the work in a neat and orderly condition.

3.05 INCIDENTAL WORK

Do all incidental work not otherwise specified, but obviously necessary for the proper completion of the contract as specified and as shown on the Drawings.