Summary: Addendum No. 2 – Questions and Answers for RFP UD-26-363
This document is Addendum No. 2 to Request for Proposal UD-26-363, issued by the Long Beach Public Utilities Department (LBPUD) for consulting services related to an Enterprise Asset Management (EAM) Readiness Assessment and Implementation Roadmap Project. The addendum provides responses to 120 questions submitted by prospective bidders regarding the scope, requirements, and evaluation criteria for the solicitation. Key project deliverables include a current-state business process assessment, technology and data readiness evaluation, future-state operating model recommendations, implementation roadmap, and cost estimates. The proposal submission deadline is 11:00 AM PT on Thursday, November 12, 2026. The contract term is 12 months from the Notice to Proceed, with optional extension for implementation support and post-assessment services. LBPUD has revised the Letter Proposal page limit from 8–10 pages to a maximum of 30 pages, which includes the transmittal letter and key personnel resumes while excluding tables, charts, graphic exhibits, required forms, and addenda acknowledgments from the page count. Major deliverable milestones include an in-person project kickoff and workshops at Milestones 3–5, with anticipated bi-weekly progress meetings and up to 30 additional meetings combining virtual and in-person sessions based on stakeholder needs.
The fee proposal should follow Exhibit E format and include labor classifications, hourly rates, and estimated hours for Tasks 1–6 (Non-Optional Tasks), with Optional Task 7 calculated as 20% of the base fee and Optional Task 8 as 15% of the base fee. The unit cost on Long Beach Buys should reflect the Grand Total of All Tasks. Participating in the Phase 1 assessment does not automatically preclude the selected consultant from competing on future software selection or implementation procurements, provided appropriate conflict-of-interest disclosures are made and safeguards are established; however, eligibility for future phases remains subject to applicable procurement rules and organizational conflict considerations at that time. No local business, small business, or disadvantaged business set-asides apply to this solicitation. The consulting contract is not considered public work under California Labor Code Section 1720, so DIR registration and certified payroll requirements do not apply. Proposers should disclose relationships with EAM or CMMS vendors and any other technology providers where conflicts of interest could reasonably arise, and must comply with the City of Long Beach's artificial intelligence use policy when handling city data. Budget reallocation among tasks within the overall not-to-exceed amount may be considered with LBPUD's prior written approval, subject to per-task limitations and required contractual approvals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 29, 2026
NOTICE TO BIDDERS
ADDENDUM NO. 2: Q & A
RFP UD-26-363
CONSULTING SERVICES FOR THE ENTERPRISE ASSET MANAGEMENT (EAM)
READINESS ASSESSMENT AND IMPLEMENTATION ROADMAP PROJECT
This addendum changes and supersedes the language in the original RFQ. Please acknowledge receipt of this addendum by signing and submitting with your bid. Any bidder who fails to submit this addendum may be disqualified.
As of October 29, 2026:
The following are answers to questions submitted:
Question 1. Exhibit B states a maximum of 8 to 10 pages. Is 10 pages acceptable, and are project reference tables excluded from this count?
Answer 1. Yes. The Long Beach Public Utilities Department (LBPUD) is revising the Letter Proposal page limit to a maximum of 30 pages. The page count will continue to include the transmittal/ offer letter and resumes of key personnel, while the Index/ Table of Contents, tables, charts, and graphic exhibits remain excluded from the page limit, consistent with Exhibit B ‐ Letter Proposal Requirements.
The signed Addendum No. 1, Addendum No. 2, the Equal Benefits Ordinance forms, proof of insurance, copies of certificates or licenses, subconsultant statements, the litigation and conflict disclosures and the agreement‐exceptions statement, and any other applicable signed forms are not counted toward the required page limit.
Question 2. Does performing the independent Phase 1 assessment restrict participation in subsequent software‐selection or implementation work, and what conflict disclosures are required?
Answer 2. Participating in the Phase 1 ‐ Enterprise Asset Management (EAM) Readiness Assessment and Implementation Roadmap does not by itself, automatically preclude the selected Consultant or its subconsultants from participating in a subsequent software‐selection or implementation procurement. However, eligibility for any future phase will be subject to the requirements of the applicable solicitation, procurement rules, and any conflict‐of‐interest or organizational‐conflict considerations identified at that time.
The Consultant shall disclose any actual, potential, or perceived conflicts of interest that could affect, or reasonably appear to affect, the independence and objectivity of the Phase 1 assessment. Such disclosures should include, as applicable, financial interests, reseller or implementation partnerships, referral or incentive arrangements, or other material relationships with EAM software vendors or service providers that may be evaluated or recommended as part of the engagement. LBPUD reserves the right to review disclosed conflicts and determine whether mitigation, additional safeguards, or other action is necessary.
Question 3. Should the Unit Cost for Item #1 on Long Beach Buys be the Exhibit E "Total for Non‐Optional Tasks (Tasks 1‐6)" or the "Grand Total (All Tasks)"? Will the Agreement's not‐to‐ exceed amount be the same figure?
Answer 3. The Unit Cost for Item #1 in Long Beach Buys should reflect the “Grand Total (All Tasks)” shown in Exhibit E ‐ Sample Fee Schedule. The agreement’s not‐to‐exceed amount is anticipated to be based on the same total, subject to successful negotiations and final approval by the LBPUD Board of Commissioners.
Question 4. If LBPUD directs data cleansing or migration under Task 3.2 that exceeds the assumptions stated in the proposal, may the additional effort be authorized under Task 8 Extra Services or under optional Task 7.2?
Answer 4. The appropriate task and funding mechanism will be determined by LBPUD based on the nature and extent of the additional work, project progress, available budget, and the applicable scope at the time the need is identified. Work that is reasonably within the requirements of Exhibit A ‐ Scope of Work, Task 3 ‐ Technology, Data, and Integration Readiness Assessment, Subtask 3.2 ‐ Asset Information and Data Readiness will remain part of that task and will not be considered extra services solely because it exceeds assumptions stated in the Consultant’s proposal.
If LBPUD determines that additional data cleansing or migration services are materially beyond the established scope of Subtask 3.2, such work may, as appropriate, be authorized under Optional Task 8 ‐ Extra Services or another applicable task, including Optional Task 7 ‐ Procurement, Implementation, and Post‐Assessment Support, subject to LBPUD’s prior written authorization, available funding, and any required contractual approvals. LBPUD will also consider the timing and extent of data cleansing and migration activities in relation to subsequent implementation and post‐implementation phases to determine the most appropriate approach. No additional services should be performed without prior written authorization from LBPUD.
Question 5. Please confirm the Letter Proposal page limit is 10 pages, and whether the signed Addendum No. 1, the Equal Benefits Ordinance forms, proof of insurance, subconsultant statements, the litigation and conflict disclosures and the agreement‐exceptions statement count toward that limit.
Answer 5. Please refer to Answer 1 of this Addendum for information.
Question 6. Are Gas Business Services and Gas Construction (Exhibit A, Section III) in scope for Task 2 discovery, although Exhibit F has no rows for them? Does "Utilities Resources" in Section III correspond to "Water Resources" in Exhibit F?
Answer 6. Yes. Gas Business, Gas Services, and Gas Construction Divisions are included in the scope of work. Information regarding the Gas Services Division can be found in Exhibit F ‐ General Project Background Information. Information regarding the Gas Business and Gas Construction Division’ functions, managed assets, and software/ platform used is included below.
“Utilities Resources” in Exhibit A ‐ Scope of Work, Section III ‐ Project Description and Overview includes “Gas Resources” and “Water Resources” Divisions. Information regarding the Water Resources Division can be found in Exhibit F. “Gas Resources” is handled by the Gas Business Bureau ‐ Natural Gas Procurement Division.
Please note that Exhibit F is revised to clarify that the Billing & Call Center Division is part of the Gas Business Bureau, not the Gas Services Bureau.
Question 7. Should hourly billing rates appear in the Letter Proposal, in the separate Fee Proposal only, or in both? Should the Fee Proposal (PDF and Excel) be uploaded on Long Beach Buys as separate attachments from the Letter Proposal, and are Excel files accepted there?
Answer 7. For clarity, the billing‐rate information referenced in Exhibit B ‐ Letter Proposal Requirements, Section 1.f ‐ Content & Format should be provided in the Fee Proposal required under Section 6 ‐ Fee Proposal and need not be duplicated within the Letter Proposal narrative.
The Fee Proposal pages are not included in the Letter Proposal page limit.
For submission, the Letter Proposal and Fee Proposal may be combined into a single PDF, provided the Fee Proposal is clearly identified as a separate section. The Fee Proposal shall also be submitted as a separate Excel file, consistent with Exhibit B, Section 6.f.
Question 8. Must the projects listed under Exhibit B, Section 3 have been performed by the proposing firm or its subconsultants, or may they include projects the named key staff performed for other organizations, with the organization and the individual's role identified?
Answer 8. Projects listed under Exhibit B ‐ Letter Proposal Requirements, Section 3 ‐ Statement of Qualifications, may include relevant projects performed by the proposing firm or its subconsultants, as well as projects performed by the proposed key personnel while employed by other organizations. For any project not performed by the proposing firm or a proposed subconsultant, the proposal should clearly identify the organization under which the work was performed and describe the individual’s specific role and responsibilities.
Such experience should be accurately attributed and should not be presented as experience of the proposing firm or subconsultant. LBPUD may consider both firm experience and the experience of proposed key personnel, as applicable, in accordance with the evaluation criteria set forth in the RFP.
Question 9. Will LBPUD post Exhibit E as an Excel file? If not, please confirm that proposers may submit their own Excel file following the Exhibit E layout, adding columns (and, if needed, sub‐ task rows).
Answer 9. Proposers may convert the Exhibit E ‐ Sample Fee Schedule table from the RFP PDF into Excel or another workable format for preparation purposes. However, the submitted fee schedule should follow the format and structure provided in Exhibit E without significant modifications to the required task rows or pricing categories. Proposers may revise the position titles to reflect the actual classifications of the personnel proposed to perform the work.
If additional sub‐task detail is necessary to explain the proposed fee, proposers may provide supplemental information, provided it is clearly tied to the applicable Exhibit E task and does not replace or alter the required fee schedule.
Question 10. For pricing, how many of the bi‐weekly progress meetings and how many of the up to 30 additional meetings should proposers assume will be held in person in Long Beach?
Are the Task 6.3 executive and technical presentations part of the in‐person Milestone 5 workshop, or separate sessions?
Answer 10. Please refer to Exhibit A ‐ Scope of Work, Task 1 ‐ Project Management, Communication and Meetings, Subtasks 1.5 to 1.8, for the applicable meeting requirements and anticipated meeting format, plus Exhibit A ‐ Scope of Work, Section X ‐ Anticipated Key Deliverables for the anticipated key project deliverables.
For the allowance of up to 30 additional meetings, proposers should assume a practical mix of virtual and in‐person sessions based on stakeholder needs and project objectives and clearly state any material pricing assumptions. Meeting duration, participant coverage, and final format will be coordinated with LBPUD during project .
Question 11. Should the Task 7 allowance (20%) and the Task 8 extra services (15%) be shown on the fee schedule as lump sums, or broken down by staff classification and hours? Will each of Tasks 1 to 6 be capped at its fee‐schedule total under the Agreement (Exhibit D: "The Board will pay no more per task, or grouping of tasks, than the amount associated with that task or grouping of tasks", p.50)?
Answer 11. Optional Tasks 7 ‐ Procurement, Implementation, and Post‐Assessment Support and Optional Task 8 ‐ Extra Services should each be shown as separate lump‐sum allowances calculated in accordance with the percentages specified in the RFP. A separate staff‐ classification and hours breakdown is not required solely for these prescribed allowances.
If a proposer identifies or recommends specific additional optional or extra services beyond the defined scope, the associated staff classifications, hourly rates, estimated hours, and costs should be clearly identified to support LBPUD’s evaluation and any future scope and fee negotiations. Inclusion of such information does not constitute authorization to perform the work; any optional or extra services may proceed only upon LBPUD’s prior written authorization and in accordance with the agreement.
Reallocation of budget among tasks within the overall not‐to‐exceed amount may be considered where warranted by project needs. However, any reallocation must receive LBPUD’s prior written approval and comply with the established agreement, applicable per‐task limitations, delegated contracting authority, and any required amendment or approval process.
No reallocation should be assumed solely on the basis that the total not‐to‐exceed amount remains unchanged.
Question 12. If optional Task 7 is authorized, how will services extending beyond the 12‐month term be contracted? If the Notice to Proceed is issued after January 1, 2027, will the term run 12 months from the start of work, beyond the 12/31/2027 end date shown on Long Beach Buys?
Answer 12. Optional Task 7 ‐ Procurement, Implementation, and Post‐Assessment Support, if authorized, will follow the contract term established by the Notice to Proceed. If the NTP is issued after January 1, 2027, the 12-month term will run from the start of work, regardless of the placeholder end date shown on Long Beach Buys. The contract dates displayed on Long Beach Buys are estimated and do not supersede the contract term as defined in the executed agreement.
Question 13. Does LBPUD consider any part of this consulting contract to be public work under California Labor Code section 1720, such that DIR registration under Exhibit C, Section IV(h) applies to the prime or its subconsultants?
Answer 13. No.
Question 14. If interviews are held, when are they expected, will they be in person or virtual, and how long will they be?
Answer 14. If interviews are conducted as part of the proposal evaluation process, only short‐ listed firms will be invited. The anticipated interview date(s), format (in‐person or virtual), duration, and any presentation requirements will be provided directly to the short‐listed firms sufficiently in advance of the interviews. LBPUD reserves the right to determine whether interviews are necessary and to establish the final interview format and schedule as part of the evaluation process.
Question 15. Are electronic or scanned signatures accepted on the proposal, the Addendum No. 1 acknowledgment, the Equal Benefits Ordinance forms and the subconsultant statements?
Answer 15. Yes.
Question 16. Under Task 1.18, is the Consultant expected to attend site visits to peer utilities, and if so, should that travel be included in the base fee?
Answer 16. The Consultant is expected to support and facilitate the peer utility outreach and site‐visit activities identified under Exhibit A ‐ Scope of Work, Task 1 ‐ Project Management, Communication and Meeting, Subtask 1.18. However, in‐person attendance by the Consultant is not necessarily required for every visit. Proposers may use their professional judgment in determining the most effective approach, including virtual participation or other means of obtaining and documenting relevant information.
The Consultant will be responsible for appropriately incorporating information obtained from peer utilities into the assessment and project deliverables. Any Consultant travel considered necessary should be identified in the proposal, together with the associated assumptions and costs. The final approach, including the need for Consultant travel, will be coordinated with LBPUD during the project.
Question 17. Will LBPUD provide the confidentiality or non‐disclosure agreement referred to in Exhibit A, Section VI.8, and is it signed at contract execution?
Answer 17. Yes. LBPUD will provide the applicable confidentiality or non‐disclosure agreement, which will be executed as part of the contract execution process.
Question 18. What are the payment terms after invoice approval (number of days)?
Answer 18. LBPUD will issue payment in the normal course of processing, typically within thirty
(30) days after receipt and approval of the invoice.
Question 19. Would LBPUD consider increasing the maximum proposal page limit or, alternatively, excluding the required one‐page resumes of key personnel from the 8–10 page limit?
Answer 19. Please refer to Answer 1 of this Addendum for information.
Question 20. Given there would be a significant conflict of interest in a software provider or system integrator developing requirements for an SOW that they could then execute, can you confirm the prime contractor and any subcontractors that serve as the Phase 1 consultant, which includes developing future‐state requirements for an EAM system and an Implementation Roadmap, will be precluded from bidding on any subsequent phase work that would be included in software / system implementation contract(s)?
Answer 20. Please refer to Answer 2 of this Addendum for information.
Question 21. Can a cover letter, resumes, and exceptions or requested changes to the Standard Form Agreement, be excluded from the 8–10‐page max page limit? Can you confirm the 8–10‐ page max page limit for the Letter Proposal excludes the Fee Proposal and Statement of Offer & Signature section?
Answer 21. Please refer to Answer 1 of this Addendum for information.
Question 22. Task 7.4 states that Optional Task 7 (Procurement, Implementation, and Post‐ Assessment Support) must be calculated as a flat allowance equal to 20% of the total proposed base fee (Tasks 1–6), and Task 8.1 defines Task 8 as a 15% allowance. However, Exhibit E includes labor classification columns requiring weekly hours and hourly rates for Tasks 7 and 8.
Could LBPUD please clarify whether proposers should enter Optional Task 7 and Task 8 in Exhibit E as single lump‐sum allowance dollar amounts (calculated as 20% and 15% of the Tasks 1–6 total, respectively), rather than attempting to populate artificial weekly labor hours and hourly rates across the individual labor classification columns?
Answer 22. Please refer to Answer 11 of this Addendum for information.
Question 23. Contracting on a Firm‐Fixed‐Price / Milestone‐Based Deliverable basis provides substantial benefits to LBPUD, including complete budget certainty, transfer of cost overrun risks to the consultant, and reduced administrative burden associated with auditing monthly timesheets. Will LBPUD permit proposers to submit a Firm‐Fixed‐Price Fee Proposal structured by Task / Deliverable Milestone (where each milestone total represents a firm fixed fee)? If fixed‐price milestone pricing is permitted, may proposers provide total fixed fees per task/milestone in Exhibit E while maintaining underlying hourly billing rates as proprietary, or omitting granular hourly rate schedules?
Answer 23. Proposers should follow the pricing structure and level of detail required in Exhibit E, including applicable staff classifications, hourly rates, and estimated hours. A firm‐fixed‐price or milestone‐based structure may be included as supplemental information, but should not replace the required Exhibit E ‐ Sample Fee Schedule fee breakdown.
Final compensation terms remain subject to negotiation and contract approval.
Question 24. Can you please confirm a Certificate of Insurance aligned to the requirements in
Exhibit D – sample Agreement is not required to be provided in the proposal but would be required at a later time such as at time of contract execution?
Answer 24. The Certificate of Insurance is not required with proposal submission. The Consultant must meet insurance requirements, however, before a contract can be issued.
Question 25. Can you please provide the Pre‐Proposal Meeting presentation and list of attendees?
Answer 25. The Pre‐Proposal Meeting presentation slides and attendance list are included in this Addendum for information.
Question 26. Please confirm whether the page‐limit exclusion for tables and graphics includes task‐by‐task scope tables containing proposed activities and deliverables. How should pages containing both narrative and tables be counted?
Answer 26. Please refer to Answer 1 of this Addendum for information.
Question 27. Addendum 1 requires bidders to price full‐scale cleansing and/or migration while stating that estimating assumptions will not limit responsibility for the required scope. Exhibit F identifies assets and applications but does not define the datasets, correction requirements, receiving environments, or acceptance criteria. Will LBPUD establish a common scope baseline for pricing or permit a separately identified provisional allowance within the base fee, with the execution scope and any fee adjustment agreed following data profiling? If not, please define the maximum extent of Phase 1 execution and clarify the receiving environment where migration may precede EAM selection.
Answer 27. Proposers should use Exhibit F ‐ General Project Background Information, the requirements of Exhibit A ‐ Scope of Work, Task 3 ‐ Technology, Data, and Integration Readiness Assessment, Subtask 3.2 ‐ Asset Information and Data Readiness, and their professional judgment, including relevant experience with utilities of comparable size and complexity, to develop sufficient labor and cost for the required scope. Material assumptions regarding data volume, quality, source systems, correction effort, receiving or staging environments, and migration approach should be clearly identified for pricing and evaluation purposes.
Consistent with Subtask 3.2 – Asset Information and Data Readiness, the base Phase 1 scope is intended to assess data readiness; identify material data gaps and quality issues; and develop planning‐level recommendations for cleansing, normalization, enrichment, reconciliation, validation, governance, and pre‐implementation remediation. The Consultant should recommend the appropriate extent, priority, sequencing, and timing of data remediation based on the assessment findings. Full‐scale data cleansing or migration is not automatically required under the base Subtask 3.2 scope solely because the Consultant identifies or recommends such work. If LBPUD determines that full‐scale execution would materially advance implementation readiness, LBPUD will determine the appropriate delivery and funding mechanism, which may include an applicable optional or extra‐services task, a contract amendment, or a subsequent project phase, subject to prior written authorization, available funding, and applicable approval requirements.
Question 28. For Exhibit E Fee Schedule, can we update or modify the position titles to match the titles of the resources who will be performing the work?
Answer 28. Please refer to Answer 9 of this Addendum for information.
Question 29. Are exceptions and signed addenda excluded from the page count?
Answer 29. Please refer to Answer 1 of this Addendum for information.
Question 30. Do we need to submit Attachment A Equal Benefits Ordinance Disclosure Form?
Answer 30. Yes.
Question 31. Will you increase the page count?
Answer 31. Please refer to Answer 1 of this Addendum for information.
Question 32. Data volumes and condition
Reference: Exhibit A, Task 3.2; Addendum 1, Answers 5 and 11.
We understand that the base scope must account for full‐scale data cleansing or migration if required by LBPUD. Beyond Exhibit F, can LBPUD provide approximate record counts, file sizes, formats, known quality issues, data dictionaries, or representative extracts for the principal asset datasets that may require this work?
Answer 32. Please refer to Answer 27 of this Addendum for information.
Question 33. Cleansing and migration execution
Reference: Exhibit A, Task 3.2.
At what stage and through what decision process would LBPUD determine that full‐scale cleansing or migration is required during Phase 1? What receiving environments, validation procedures, reconciliation tolerances, and acceptance criteria should proposers anticipate, particularly if a future EAM platform has not yet been selected?
Answer 33. Please refer to Answer 27 of this Addendum for information.
Question 34. System access and third‐party support
Reference: Exhibit A, Task 3; Exhibit F.
What assessment access will LBPUD provide, including read‐only application or database access, exports, API documentation, interface inventories, test environments, and incumbent‐ vendor assistance? If third‐party extraction, licensing, or access charges are necessary, should those costs be included in the consultant’s fee?
Answer 34. LBPUD will provide reasonable access to available systems, data, documentation, and subject‐matter resources necessary to support the assessment, subject to applicable security, licensing, confidentiality, and operational requirements. The specific form of access, such as read‐only access, data exports, Application Programming Interface (API) or interface documentation, test environments, or incumbent‐vendor support, will be determined during the project based on availability and need.
Proposers should identify any anticipated third‐party extraction, licensing, or access costs and related assumptions in their proposals. Known or reasonably foreseeable costs should be included in the proposed fee. Any unanticipated third‐party costs will be addressed by LBPUD, as appropriate, through the applicable authorization and contractual process.
Question 35. Technical assessment depth
Reference: Exhibit A, Tasks 3 and 4.
What minimum level of detail is expected for application inventories, dependency and interface mapping, data‐quality analysis, and the future‐state conceptual architecture? Are there preferred templates, documentation standards, or acceptance criteria beyond those stated in the RFP?
Answer 35. Deliverables should provide sufficient detail to clearly document the current‐state application environment, key dependencies and interfaces, material data‐quality conditions, and the proposed future‐state conceptual architecture needed to support LBPUD’s decision‐ making and implementation roadmap.
Unless otherwise specified in the RFP, LBPUD has not prescribed additional templates or documentation standards. Proposers should use their professional judgment and recognized industry practices to recommend an appropriate level of detail and format. Deliverables will be subject to LBPUD review and acceptance based on completeness, accuracy, clarity, consistency with the scope, and usefulness in supporting subsequent implementation and procurement activities.
Question 36. Cybersecurity and operational technology
Reference: Exhibit A, Tasks 3 and 4.
Should proposers anticipate a documentary cybersecurity assessment, configuration reviews, vulnerability scanning, or other technical testing? Please identify applicable IT/OT access boundaries, remote‐access restrictions, data‐storage requirements, personnel screening, and tool‐approval requirements.
Answer 36. Proposers should anticipate a primarily documentary and interview‐based cybersecurity assessment, including review of available policies, architecture, access controls, system configurations, and relevant Information Technology/ Operational Technology (IT/ OT) practices. If a proposer determines that vulnerability scanning, penetration testing, or other technical testing is necessary to support a complete and effective assessment, the proposed approach, purpose, and associated assumptions should be clearly identified in the proposal.
Any intrusive technical testing will be subject to LBPUD review and prior written authorization, as well as applicable IT/ OT security, confidentiality, operational, access, and tool‐ approval requirements.
Question 37. On‐site participation and meeting effort
Reference: Exhibit A, Tasks 1.3–1.8 and Task 2.
Beyond the required in‐person kickoff and Milestones 3–5, what field observations, site visits, or in‐person discovery sessions should proposers anticipate? Can LBPUD provide planning assumptions for meeting duration, participant coverage, and the expected mix of virtual and in‐ person meetings within the allowance of up to 30 additional meetings?
Answer 37. Beyond the in‐person meetings specifically identified in the RFP, discovery is expected to be conducted primarily through document review, stakeholder interviews, and facilitated workshops. Field observations, site visits, or additional in‐person sessions should be proposed where they are reasonably necessary to understand operational practices, validate findings, or address site‐specific conditions.
Please refer to Answer 10 of this Addendum for information regarding the additional meetings.
Question 38. Existing application inventory and customer systems
Reference: Exhibit A, Task 3; Exhibit F.
Is a current application and interface inventory available identifying versions, owners, support status, hosting environments, and known integrations? Please also clarify the meeting statement concerning the absence of a separate customer information system and its relationship to the CC&B applications listed in Exhibit F.
Answer 38. Exhibit F ‐ General Project Background Information provides the currently high‐level available information regarding LBPUD’s applications and systems. However, proposers should not assume that a complete, validated application and interface inventory, including versions, ownership, support status, hosting environments, and all integrations, is available at the outset.
Developing and validating this information is part of the Phase 1 assessment.
The statement made during the pre‐proposal meeting regarding the absence of a separate customer information system was intended to clarify that LBPUD does not maintain a separate standalone Customer Information System (CIS) apart from the customer‐related applications identified in Exhibit F. The listed Customer Care & Billing (CC&B) applications support customer care and billing functions and should be considered within the current application environment to be assessed.
Question 39. Previous assessments and supporting documentation
Reference: Exhibit A, Tasks 2–4; pre‐proposal meeting discussion.
Will the selected consultant receive the prior West Monroe IT assessment, previous EAM studies, process maps, architecture documents, and relevant security or data assessments?
Please identify when these materials would become available and whether LBPUD maintains a record of recommendations already implemented or superseded.
Answer 39. LBPUD will make available to the selected Consultant relevant existing plans, assessments, process documentation, technology roadmaps, organizational studies, and related materials in LBPUD’s possession that are applicable to the scope and appropriate for release. Such materials will generally be provided during project initiation and discovery, or as they are identified and needed during the assessment.
To the extent available, LBPUD will also provide information regarding prior recommendations that have been implemented, remain outstanding, or have been superseded.
Proposers should not assume that each type of document identified in the question currently exists, is available, or is maintained in a single consolidated record unless specifically referenced in the RFP or Exhibit F ‐ General Project Background Information.
Question 40. Authoritative asset records and data governance
Reference: Exhibit A, Tasks 3 and 4; Exhibit F.
Does LBPUD maintain a documented designation of authoritative sources for asset identifiers, locations, maintenance history, inspection results, financial values, and supporting documents?
If available, will existing data ownership, stewardship, retention, and reconciliation standards be provided?
Answer 40. Please refer to Answer 39 of this Addendum for information.
Question 41. Process mapping and requirements detail
Reference: Exhibit A, Tasks 2 and 4.
How will LBPUD and the consultant establish which workflows require detailed mapping and which may be documented at a summary level? Please clarify the expected minimum detail for process maps and the requirements catalog, and how priorities or cost‐related tradeoffs will be approved while preserving the mandatory scope.
Answer 41. The Consultant should use its professional judgment, relevant experience with utilities of comparable size and complexity, assessment findings, and stakeholder input to determine the appropriate level of process‐mapping detail. Greater detail should be provided for workflows that are critical, complex, cross‐functional, high‐risk, or materially relevant to future EAM requirements, while less complex processes may be documented at a summary level. Process maps and the requirements catalog should be sufficiently detailed to identify key roles, activities, handoffs, systems, data dependencies, controls, gaps, and future‐state requirements. Prioritization and cost‐related tradeoffs should be presented as recommendations for LBPUD review and approval and shall not reduce or omit mandatory scope requirements without LBPUD’s prior authorization.
Question 42. Stakeholder availability and decision authority
Reference: Exhibit A, Tasks 1, 2, and 4.
Will participating divisions designate subject‐matter experts and provide scheduled availability for discovery and validation? What executive sponsor, steering committee, or decision authority will resolve conflicting requirements and approve enterprise standards and justified division‐specific practices?
Answer 42. Yes. Participating LBPUD divisions will designate appropriate subject‐matter experts and provide reasonable scheduled availability for discovery, review, and validation activities.
As listed in Exhibit A ‐ Scope of Work, the Consultant will be expected to facilitate stakeholder alignment, identify conflicting requirements, and provide clear, well‐supported recommendations regarding enterprise standards and any justified division‐specific practices.
Final decisions will be made by LBPUD, with the General Manager or designee serving as the ultimate decision authority, as appropriate. The specific governance and review process will be confirmed during project initiation.
Question 43. Review periods and deliverable acceptance
Reference: Exhibit A, Tasks 1–6 and Deliverable Standards.
What client review durations and number of review cycles should proposers assume for interim memoranda, supporting materials, and the final report? Please identify the approval authorities and acceptance process, including how consolidated comments will be coordinated across divisions.
Answer 43. For planning purposes, proposers could assume approximately 10 to 15 business days per LBPUD review cycle and up to two review cycles for major interim and final deliverables, unless otherwise coordinated with LBPUD. Review periods may vary based on the complexity of the deliverable and the extent of stakeholder coordination required.
The project schedule may be updated, as appropriate, to reflect actual LBPUD review periods, availability of requested information, and other dependencies outside the Consultant’s control. Any material schedule impacts should be documented and coordinated with LBPUD.
Please refer to Answer 42 of this Addendum for information about the approval authorities and acceptance process.
Question 44. Base‐scope budget
Reference: Exhibit B, Fee Proposal; Exhibit E.
Is an indicative budget range or funding ceiling available for Tasks 1–6? If budget constraints require prioritization, how does LBPUD intend to establish the appropriate level of effort while maintaining all mandatory deliverables?
Answer 44. Please refer to Answer 3, Answer 11, and Answer 23 of this Addendum for information regarding budget range and budget reallocation among tasks.
If budget constraints require prioritization, the Consultant should identify and recommend adjustments to the level of effort, sequencing, or methodology that preserve all mandatory scope requirements and deliverables. Any proposed prioritization should be supported by the assessment findings, project objectives, risk, and relative importance to the future EAM program. LBPUD will then review such recommendations and determine the appropriate approach based on available funding, project priorities, and contractual requirements. No mandatory scope or deliverable may be reduced or omitted without LBPUD’s prior written authorization.
Question 45. Optional support and subsequent implementation
Reference: Exhibit A, Tasks 7 and 8.
Beyond the written‐authorization requirements already stated, what procurement and approval procedures would govern optional continuity support and any subsequent implementation engagement? Are there additional eligibility restrictions for the assessment team beyond the vendor‐neutrality and relationship‐disclosure requirements in the RFP?
Answer 45. Optional continuity support will be subject to the executed agreement terms, available funding, LBPUD’s prior written authorization, and any required procurement or approval processes. Any subsequent EAM implementation engagement will be subject to the procurement and contracting requirements applicable at that time, unless expressly authorized under the existing agreement.
At this stage, no additional eligibility restrictions are identified beyond the vendor‐ neutrality, independence, and relationship‐disclosure requirements stated in the RFP.
However, LBPUD reserves the right to evaluate actual, potential, or perceived conflicts of interest or organizational conflicts and to establish appropriate mitigation measures or eligibility requirements for any future procurement.
Question 46. Proposal page limit
Reference: Exhibit B, Content and Format.
Please confirm whether the stated maximum of “8 to 10 pages” means a maximum of 10 counted pages. We understand that the transmittal or offer letter and resumes count, that the listed index, tables, charts, and graphic exhibits are excluded, and that the fee proposal is separate. Do required forms and signed addendum acknowledgments count toward the technical‐proposal limit?
Answer 46. Please refer to Answer 1 and Answer 7 of this Addendum for information.
Question 47. How deep should the gas assessment go on PHMSA integrity management requirements?
Answer 47. The gas assessment should address applicable Pipeline and Hazardous Materials Safety Administration (PHMSA) integrity management requirements to the extent necessary to evaluate their implications for asset information, inspection and maintenance practices, work management, recordkeeping, traceability, reporting, and future EAM capabilities. The Consultant should identify material gaps, dependencies, and system requirements relevant to the project.
A comprehensive PHMSA compliance audit or independent regulatory certification is not anticipated, unless otherwise identified as necessary by the Consultant and authorized by LBPUD. Proposers should use their professional judgment and relevant utility experience to determine the appropriate level of assessment.
Question 48. For Task 3.2 pricing, what record volumes and how many source systems should bidders assume for full‐scale data cleansing or migration?
Answer 48. Please refer to Answer 27 of this Addendum for information.
Question 49. How far into customer payment and cashiering workflows should Task 2 go, given there is no separate CIS or payment project?
Answer 49. Exhibit A ‐ Scope of Work, Task 2 ‐ Current‐State Business Process and Stakeholder Discovery should evaluate customer payment and cashiering workflows to the extent necessary to understand their interfaces, data dependencies, business processes, and impacts on asset and work management activities relevant to the EAM assessment.
A detailed redesign of customer information, billing, payment, or cashiering processes is not anticipated as a separate workstream. The Consultant should use professional judgment and relevant utility experiences to identify material dependencies, gaps, and future‐state requirements that should be considered in the project.
Question 50. Does the city have an AI use policy or approved AI tools for consultants handling city data?
Answer 50. Yes. The City of Long Beach has an established policy governing the use of artificial intelligence. Consultants handling City or LBPUD data must comply with applicable City policies, information‐security requirements, confidentiality obligations, and any restrictions regarding the use of AI‐enabled tools. Specific tool approvals or limitations, as applicable, will be coordinated with LBPUD during the project.
Please refer to Answer 17 of this Addendum for information regarding the execution of a non‐disclosure/ confidentiality agreement for this project.
Question 51. How many divisions, business functions, and stakeholder groups are expected to participate in the discovery and assessment activities?
Answer 51. The discovery and assessment effort is expected to include all the LBPUD divisions, business functions, stakeholder groups, facilities, and workflows necessary to support a representative and enterprise‐wide assessment. Proposers should use Exhibit F ‐ General Project Background Information, Exhibit A ‐ Scope of Work, and their professional judgment, including relevant experience with utilities of comparable size and complexity, to develop an efficient engagement and process‐mapping approach, including appropriate use of representative sampling, individual interviews, group workshops, document review, and field observations. The level of detail should reflect the complexity, criticality, cross‐functional dependencies, and relevance of each process to the future EAM program. Final participants, coverage, and documentation depth will be coordinated with LBPUD during project initiation.
Question 52. Does LBPUD anticipate a representative sampling approach across divisions and facilities, or comprehensive assessment of every operating unit and major workflow?
Answer 52. Please refer to Answer 51 of this Addendum for information.
Question 53. Approximately how many distinct business processes or workflows does LBPUD anticipate requiring detailed process mapping versus summary‐level documentation?
Answer 53. LBPUD has not established a predetermined number of workflows requiring detailed process mapping. The Consultant should use Exhibit A ‐ Scope of Work, Exhibit F ‐ General Project Background Information, assessment findings, and professional judgment to determine the appropriate level of documentation for each process.
Detailed process mapping should generally be applied to critical, complex, or cross‐ functional workflows that directly affect asset and work management, data quality, system integration, or future EAM requirements. For example, maintenance work management, asset inspection, construction turnover, or work‐order processes may warrant detailed mapping of roles, handoffs, systems, data, and decision points. Supporting functions with more limited interaction with the EAM program may be documented at a summary level, provided their relevant responsibilities, interfaces, dependencies, and requirements are adequately captured.
These examples are illustrative and do not predetermine the treatment of any specific division or workflow. Final mapping depth will be coordinated with LBPUD based on the assessment findings and project needs.
Question 54. Does LBPUD expect individual interviews with frontline personnel, or can group workshops be used where appropriate?
Answer 54. Please refer to Answer 51 of this Addendum for information.
Question 55. Can LBPUD provide a preliminary inventory of existing software applications, CMMS platforms, GIS systems, databases, and major integrations included in the assessment?
Answer 55. Please refer to Answer 6 of this Addendum and Exhibit F ‐ General Project Background Information for existing software/ platform used by each LBPUD group/ division/ bureau.
Question 56. Does the cybersecurity assessment require a formal security evaluation, or identification of cybersecurity considerations relevant to EAM readiness?
Answer 56. Please refer to Answer 36 of this Addendum for information.
Question 57. What is the approximate number of assets and asset records currently maintained across LBPUD’s water, sewer, gas, facilities, and fleet operations?
Answer 57. Please refer to Answer 6 of this Addendum and Exhibit F ‐ General Project Background Information for high‐level asset information of each LBPUD group/ division/ bureau.
Question 58. Does LBPUD expect a separate maturity score for each ISO 55000 clause?
Answer 58. No. LBPUD does not require a separate maturity score for each ISO 55000 clause.
Consistent with Exhibit A ‐ Scope of Work, Section XI ‐ Applicable Codes and Standards, the Consultant should evaluate LBPUD’s current practices and proposed future‐state EAM program against applicable ISO 55000 series principles, guidance, and related ISO 55001, 55002, 55010, and 55013 concepts, together with the other standards and industry practices identified in the
RFP.
The Consultant may use clause‐level scoring or another recognized maturity‐assessment methodology where appropriate, provided the approach is clearly explained and sufficiently identifies strengths, gaps, priorities, and improvement opportunities to support the project.
Question 59. Is the consultant expected to develop detailed RACI matrices for all major asset management processes?
Answer 59. LBPUD does not anticipate detailed Responsible‐Accountable‐Consulted‐Informed (RACI) matrices for every major asset management process. The Consultant should use professional judgment to identify processes where clearer definition of roles, responsibilities, accountability, and decision authority is important to the future‐state EAM program.
Detailed RACI matrices may be developed for selected critical or cross‐functional processes, while other processes may be documented at an appropriate summary level, provided the approach sufficiently supports the assessment and implementation roadmap.
Question 60. Is a formal business case or return‐on‐investment analysis expected?
Answer 60. A separate formal business case or return‐on‐investment analysis is not specifically required unless otherwise identified through the assessment. However, the Consultant should evaluate and document, as appropriate, the anticipated benefits, costs, risks, resource implications, and operational impacts of the recommended future‐state EAM program to support LBPUD’s decision‐making and implementation roadmap.
Where sufficient information is available, the Consultant may include quantitative cost‐ benefit or return‐on‐investment considerations to support prioritization of recommended initiatives.
Question 61. Does LBPUD expect the consultant to perform actual data cleansing or migration during Phase 1, or only assess data quality and develop a remediation plan?
Answer 61. Please refer to Answer 27 of this Addendum for information.
Question 62. Does LBPUD envision a single enterprise EAM platform, or is a federated architecture with multiple integrated systems an equally acceptable outcome?
Answer 62. LBPUD has not predetermined that the future‐state EAM environment must consist of a single enterprise platform. The Consultant should evaluate the Department’s business, operational, data, integration, technology, and governance requirements and recommend the architecture that best supports LBPUD’s long‐term needs.
A single enterprise EAM platform, a federated architecture with multiple integrated systems, or another appropriate model may be recommended, provided the approach is well supported, minimizes unnecessary complexity and duplication, promotes effective data and system integration, and aligns with the implementation roadmap.
Question 63. How many executive and technical presentations should be included in the base fee?
Answer 63. The base fee should include all anticipated executive and technical/ operational presentations and working sessions necessary to satisfy the requirements of Exhibit A ‐ Scope of Work, Task 6 ‐ Final EAM Readiness Assessment, Recommendations, and Project Closeout, Subtask 6.3 ‐ Final Executive and Stakeholder Presentations and the Milestone 5 ‐ Final EAM Readiness Assessment and Presentation Workshop. The Consultant should use professional judgment to structure the sessions appropriately for the intended audiences, with the final format and sequencing coordinated with LBPUD.
Question 64. Will the final report be reviewed by one consolidated LBPUD approval group or multiple divisions independently?
Answer 64. The final report may be reviewed by multiple participating LBPUD divisions and stakeholders. However, review comments will be coordinated through LBPUD’s Project Manager and provided to the Consultant in a consolidated manner.
Question 65. Will the consultant selected to perform the EAM Readiness Assessment remain eligible to compete for or participate in subsequent EAM software implementation, systems integration, data migration, and related consulting services, provided appropriate conflict‐of‐ interest disclosures and safeguards are maintained?
Answer 65. Please refer to Answer 2 of this Addendum for information.
Question 66. What constitutes formal acceptance of each milestone deliverable?
Answer 66. Formal acceptance of each milestone deliverable will occur upon LBPUD’s review and written confirmation that the deliverable satisfactorily addresses the applicable scope requirements and has appropriately resolved consolidated review comments. Acceptance will be coordinated through LBPUD’s Project Manager and the appropriate management or decision authority, as applicable.
Question 67. How many in‐person meetings, site visits, and workshops should consultants assume beyond the three mandatory in‐person milestone workshops and kickoff meeting?
Answer 67. Please refer to Answer 10 of this Addendum for information.
Question 68. What level of accuracy and detail is expected for future EAM implementation cost estimates, and does LBPUD have preliminary budget parameters?
Answer 68. The future‐state operating model, implementation roadmap, and cost estimates should be developed at a strategic and planning level, with sufficient detail to support LBPUD’s future budgeting, procurement, sequencing, resource planning, and implementation decisions.
Deliverables should identify recommended operating practices, governance and organizational considerations, implementation phases and dependencies, schedules, risks, key assumptions, and major cost and resource drivers. Cost estimates should include appropriate ranges and contingencies. Detailed design‐, implementation‐, or bid‐level specifications are not required.
Proposers should not assume a predetermined implementation budget. Any applicable budget parameters or constraints available during the project will be coordinated with the Consultant, as appropriate.
Question 69. How many review cycles should be assumed for each draft deliverable, and will LBPUD provide one consolidated set of comments per…