This Addendum No. 1 to RFP UD-26-363 issued by Long Beach Utilities modifies key deadlines and provides clarifications for a consulting services contract to conduct an Enterprise Asset Management (EAM) Readiness Assessment and Implementation Roadmap Project. The revised deadlines are as follows: RSVP Due (Mandatory) on Tuesday, October 20, 2026 at 3:00 PM PT; Pre-Proposal Meeting (Mandatory) on Thursday, October 22, 2026 at 11:00 AM PT; Question Submittal by Monday, October 26, 2026 at 11:00 AM PT; Answers posted on Long Beach Buys on Thursday, October 29, 2026 at 3:00 PM PT; and Proposals Due on Thursday, November 12, 2026 at 11:00 AM PT. All times are California local time (Pacific Time). Proposals must be posted to Long Beach Buys no later than 11:00 AM PT on Thursday, November 12, 2026, and clearly marked "Enterprise Asset Management (EAM) Readiness Assessment and Implementation Roadmap: Proposal Submittal (UD-26-363)." The scope encompasses five primary tasks: Current-State Business Process and Stakeholder Discovery; Technology, Data, and Integration Readiness Assessment; EAM Maturity, Gap, Future-State Operating Model, and Requirements; and Implementation Strategy, Organizational Change, Roadmap, and Investment Planning.

The addendum addresses eleven questions submitted by prospective bidders. Key clarifications include that project teams may include subconsultants, but the prime consultant must RSVP and attend the mandatory pre-proposal meeting; a designated representative of the prime consultant may attend the conference on the firm's behalf, provided that representative communicates all information to the project team. The proposal electronic submission deadline is definitively 11:00 AM PT on Thursday, November 12, 2026. Regarding Task 3.2 data cleansing and migration requirements, proposers must use information from Exhibit F (General Project Background Information) regarding LBPUD's organizational structure, managed assets, and software systems, along with their professional experience and judgment, to estimate labor hours and costs. Any material assumptions regarding data volume, format, quality, source systems, receiving environments, or migration effort must be clearly stated in the proposal for pricing and evaluation purposes only and shall not limit the consultant's responsibility to complete the required scope. The Microsoft Teams meeting link will be provided to all individuals who have properly RSVP'd after the RSVP deadline has passed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

October 13, 2026

NOTICE TO BIDDERS

ADDENDUM NO. 1: Q & A

RFP UD-26-363

CONSULTING SERVICES FOR THE ENTERPRISE ASSET MANAGEMENT (EAM)

READINESS ASSESSMENT AND IMPLEMENTATION ROADMAP PROJECT

This addendum changes and supersedes the language in the original RFQ. Please acknowledge receipt of this addendum by signing and submitting with your bid. Any bidder who fails to submit this addendum may be disqualified.

As of October 13, 2026:

The following sections shall be modified:

Cover Letter (page 1)

DEADLINES DATE TIME (PT)

RSVP Due (Mandatory) Tuesday, October 20, 2026 3:00 PM

Pre-Proposal Meeting (Mandatory) Thursday, October 22, 2026 11:00 AM

Question Submittal Monday, October 26, 2026 11:00 AM

Answers to be posted on Long Beach Buys under Bid invitation

Thursday, October 29, 2026 3:00 PM

Proposals Due Thursday, November 12, 2026 11:00 AM

All times are California local time (Pacific Time)

Cover Letter (page 2)

Proposals must be posted to Long Beach Buys no later than 11:00 am PT on Thursday, November 12, 2026. The submittal must be clearly marked “Enterprise Asset Management (EAM) Readiness Assessment and Implementation Roadmap: Proposal Submittal (UD‐26‐363).”

The following are answers to questions submitted:

Question 1. Could you clarify whether a prime consultant can rely on named independent specialists for the technical and utility‐specific qualifications?

Answer 1. Project teams may include subconsultants. The prime consultant must RSVP and attend the pre‐proposal meeting. See LETTER PROPOSAL REQUIREMENTS section for subconsultant information required for proposal submission.

Question 2. Whether the scope includes business‐process mapping, asset/inventory data readiness, and operating‐change planning alongside the systems assessment?

Answer 2. Please refer to Exhibit A ‐ Scope of Work, Task 2 ‐ Current‐State Business Process and Stakeholder Discovery, Task 3 ‐ Technology, Data, and Integration Readiness Assessment, Task 4 ‐ EAM Maturity, Gap, Future‐State Operating Model, and Requirements, and Task 5 ‐ Implementation Strategy, Organizational Change, Roadmap, and Investment Planning, for details.

Question 3. The cover timeline lists proposals due November 12, 2026 at 11:00 a.m.; the subsequent cover paragraph gives 3:00 p.m. on that date, while the Long Beach Buys opening field is 11:00 a.m. Which time governs electronic submission?

Answer 3. See above modification to Cover Letter section. The proposal electronic submission due date will be 11:00 am PT on Thursday, November 12, 2026.

Question 4. The cover labels the October RSVP, meeting and question times as PST. Please confirm whether those events use local California time on each date, including the October 20 RSVP and October 22 meeting.

Answer 4. See above modification to Cover Letter section. All times are California local time (Pacific Time).

Question 5. Exhibit A, Task 3.2 allows the City to require full‐scale data cleansing or migration during Phase 1. For the base Task 3 fee, please identify any anticipated datasets, approximate volumes, receiving environments and completion criteria, or the source/volume assumptions proposers should use when estimating that work.

Answer 5. Please refer to Exhibit F ‐ General Project Background Information for the available information regarding LBPUD’s organizational structure, managed assets, and software systems. Proposers shall use this information, together with their professional experience and judgment, to develop sufficient labor hours and costs for the full scope of Task 3.2, including full‐scale data cleansing and/or migration if required during Phase 1.

Any material assumptions regarding data volume, format, quality, source systems, receiving environments, or migration effort shall be clearly stated in the proposal. Such assumptions are for pricing and evaluation purposes only and shall not limit the Consultant’s responsibility to complete the required scope.

Question 6. Could you please confirm that prospective subcontractors may attend the virtual meeting independently and advise whether the mandatory attendance requirement applies specifically to the submitting prime bidder?

Please share the Microsoft Teams joining details and any required registration instructions.

Answer 6. Please refer to Answer 1 of this Addendum for information.

The Microsoft Teams meeting link will be provided to all individuals who have properly RSVP’d after the RSVP deadline has passed. Attendees should ensure that their RSVP is submitted by the stated deadline so they can be included in the meeting invitation and distribution of access information.

Question 7. Please provide registration instructions and the virtual meeting link for the mandatory pre‐bid conference on October 22, 2026 at 11:00 a.m. Pacific. Can a designated company representative attend on the firm's behalf?

Answer 7. Please refer to Cover Letter (page 2) of the RFP and Answer 6 of this Addendum for RSVP information.

A designated representative of the prospective prime consultant can attend the mandatory pre‐ bid conference on the firm’s behalf, provided the representative is responsible for communicating all information, requirements, clarifications, and discussion from the meeting to the firm’s proposed project team.

Question 8. Please send the meeting invitation and confirm the local Pacific time for the meeting.

Answer 8. Please refer to Answer 4 and Answer 6 of this Addendum for information.

Question 9. Page 1 lists November 12 at 11 AM for proposals, while page 2 lists 3 PM. Which deadline controls?

Answer 9. Please refer to Answer 3 of this Addendum for information.

Question 10. Please confirm whether the October RSVP, meeting and question deadlines use local Pacific daylight time despite the PST label.

Answer 10. Please refer to Answer 4 of this Addendum for information.

Question 11. Task 3.2 allows full‐scale data cleansing or migration if LBPUD deems it necessary.

Should bidders price a defined allowance, an optional task, or this work within the base upper limit? What data volumes should be assumed?

Answer 11. Please refer to Answer 5 of this Addendum for information.

PREPARED BY:

Esme Houtepen, Utilities Procurement Representative

ACKNOWLEDGED BY:

Company Name

Print Name Title

Signature Date